628-628 1/2 E SANTA CLARA AVE 90291
Certificate Information: 628-628 1/2 E SANTA CLARA AVE 90291
- Application / Permit
- 19010-30000-05991
- Plan Check / Job No.
- B19WL07204
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2-STORY TYPE VA DUPLEX WITH ATTACHED 2-CAR GARAGE WITH PARKING LIFT, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 11/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | SERGIO SILVA |
| Corrections Issued | 2/13/2020 | SERGIO SILVA |
| Quality Review Completed | 2/21/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 2/24/2020 | APPLICANT |
| Applicant returned to address corrections | 11/5/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 11/30/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 1/15/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 3/26/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 4/28/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 1/13/2022 | SERGIO SILVA |
| Applicant returned to address corrections | 2/2/2022 | SERGIO SILVA |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| Plan Check Approved | 4/4/2022 | SERGIO SILVA |
| Issued | 4/26/2022 | APPLICANT |
| CofO in Progress | 11/17/2023 | HERBERT GIRON |
| Permit Finaled | 11/29/2023 | DANIEL ORRANTE |
| CofO Issued | 11/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/22/2020 | MARTIN FRAGOSO |
| Address approval | Cleared | 1/20/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | CECILIO NAVARRO |
| Permit | Cleared | 1/20/2021 | CECILIO NAVARRO |
| Trees in Parkway | Cleared | 2/4/2021 | JOHN KIM |
| Roof/Waste drainage to street | Cleared | 3/12/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 4/27/2021 | KURT CORRAL |
| Sewer availability | Cleared | 7/28/2021 | DINAH GARIN |
| Coastal Zone | Cleared | 3/30/2022 | NOAH MCCOY |
| Frnt yard landscape/Water mgmt | Cleared | 3/30/2022 | NOAH MCCOY |
| Miscellaneous | Cleared | 3/30/2022 | NOAH MCCOY |
| Miscellaneous | Cleared | 3/30/2022 | NOAH MCCOY |
| Miscellaneous | Cleared | 3/30/2022 | NOAH MCCOY |
| Miscellaneous | Cleared | 3/30/2022 | NOAH MCCOY |
| Specific Plan | Cleared | 3/30/2022 | NOAH MCCOY |
| ZI | Cleared | 3/30/2022 | NOAH MCCOY |
| Green Code | Cleared | 4/4/2022 | RICHARD GARCIA |
| Miscellaneous | Cleared | 4/4/2022 | SERGIO SILVA |
| Miscellaneous | Cleared | 4/4/2022 | SERGIO SILVA |
Contact Information
| Architect | Radziner,, Ronald Mark; Lic. No.: C22228 | MARMOL RADZINER & ASSOCIATES 12210 NEBRASKA AVE LOS ANGELES, CA 90025 |
| Contractor | Marmol Radziner An Architectural Corporation; Lic. No.: 734381-B | 12210 NEBRASKA AVENUE LOS ANGELES, CA 90025 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Mccormick,, Charles Norman; Lic. No.: C32534 | 462 GLENSTONE DR MOUNTIAN HOME, AR 72653 |
| Engineer | Wavering,, Derek Evan; Lic. No.: S6239 | 1371 COLE LANE UPLAND, CA 91784 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/4/2022 | Partial Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| METHANE-Barrier | 6/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| METHANE-Subgrade | 6/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/21/2022 | Partial Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 6/28/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 6/28/2022 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 6/28/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 7/15/2022 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 7/25/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 7/28/2022 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 9/7/2022 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Rough | 9/7/2022 | Not Ready for Inspection | DAVID FEILER |
| Verify Sprinkler Sign Off | 9/7/2022 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 9/15/2022 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 9/15/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Rough | 9/15/2022 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 9/15/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Corrections Issued | DAVID FEILER |
| Wood Frame | 9/23/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 10/5/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 10/25/2022 | Partial Approval | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 10/27/2022 | Partial Approval | CLAYTON GRAHAM |
| Underground Mechanical | 10/31/2022 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 11/1/2022 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 11/3/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 11/17/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 12/1/2022 | Approved | DAVID FEILER |
| Underground Mechanical | 12/1/2022 | Not Ready for Inspection | DAVID FEILER |
| Sewer | 12/7/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 12/13/2022 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 12/16/2022 | Partial Approval | EVAN COOPER |
| Green Building Rough | 12/16/2022 | Partial Approval | EVAN COOPER |
| Verify Sprinkler Sign Off | 12/16/2022 | Approved | EVAN COOPER |
| Insulation | 12/29/2022 | Approved | DAVID FEILER |
| Deputy Wood Construction | 1/4/2023 | Conditional Approval | EVAN COOPER |
| Drywall Nailing | 1/5/2023 | Approved | EVAN COOPER |
| Green Building Rough | 1/5/2023 | Approved | EVAN COOPER |
| Shower Pan | 1/13/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/25/2023 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 3/28/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/24/2023 | Approved | EVAN COOPER |
| Deputy Steel/Welding | 6/20/2023 | Conditional Approval | EVAN COOPER |
| Grounding or Bonding | 7/13/2023 | Partial Approval | EVAN COOPER |
| Underground Mechanical | 7/18/2023 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 7/19/2023 | Partial Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 8/2/2023 | Conditional Approval | RICHARD STEINBACH |
| Underground Mechanical | 8/10/2023 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Final | 9/15/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 9/27/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 9/29/2023 | Approved | HERBERT GIRON |
| Service/Power Release | 9/29/2023 | Approved | HERBERT GIRON |
| Final | 10/5/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 10/5/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 10/10/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 10/10/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 10/10/2023 | Approved | HERBERT GIRON |
| Final | 10/24/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 10/24/2023 | Not Ready for Inspection | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 10/24/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 10/24/2023 | Approved | HERBERT GIRON |
| Final | 11/13/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 11/13/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/13/2023 | SGSOV Not Required | HERBERT GIRON |
| Final | 11/16/2023 | OK to Issue CofO | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Approved | HERBERT GIRON |