5422 W SMILEY DR 90016

Certificate Information: 5422 W SMILEY DR 90016

Application / Permit
19010-30000-05983
Plan Check / Job No.
B19WL07201
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-story SFD with attached 2-car garage at front of the lot.
Permit Issued
Issued on 4/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Green Plans Picked Up 1/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 JAHANSHAH POURHASSAN
Corrections Issued 1/24/2020 JAHANSHAH POURHASSAN
Quality Review Completed 1/31/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/31/2020 APPLICANT
Plan Check Approved 3/3/2020 JAHANSHAH POURHASSAN
Issued 4/10/2020 LADBS
CofO in Progress 2/24/2021 ROBERT VORHIS
Permit Finaled 4/8/2021 DEROLD HAUFF
Permit Finaled 4/8/2021 DEROLD HAUFF
CofO Issued 4/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/31/2020 OSCAR GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 1/31/2020 OSCAR GUTIERREZ
Hydrant and Access approval Cleared 1/31/2020 ROBERT DUFF
Sewer availability Cleared 1/31/2020 OSCAR GUTIERREZ
Low Impact Development Cleared 2/10/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 2/10/2020 ERIK BEASLEY
Green Code Cleared 2/11/2020 RICHARD GARCIA

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/21/2020 Approved DAVID CHAN
Footing/Foundation/Slab 4/28/2020 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 5/4/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 5/28/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2020 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Partial Approval STUART CHAPMAN
HVAC-Rough 9/16/2020 Approved DAVID CHAN
PLUMBING-Rough 9/16/2020 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 9/22/2020 Not Ready for Inspection DAVID CHAN
ELECTRICAL-Rough 9/22/2020 Approved DAVID CHAN
Green Building Rough 9/22/2020 Approved DAVID CHAN
Wood Frame 9/24/2020 Approved DAVID CHAN
Insulation 9/28/2020 Approved DAVID CHAN
Drywall Nailing 10/8/2020 Approved DAVID CHAN
Interior/Exterior Lathing 10/8/2020 Not Ready for Inspection DAVID CHAN
Interior/Exterior Lathing 10/14/2020 Approved DAVID CHAN
Shower Pan 10/14/2020 Approved DAVID CHAN
Gas Test 1/28/2021 Approved OSVALDO PARAMO
HVAC-Final 1/28/2021 Approved OSVALDO PARAMO
PLUMBING-Final 1/28/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 2/8/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 2/8/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 2/8/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 2/8/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 2/8/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 2/8/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 2/8/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 2/10/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 2/16/2021 Approved OSVALDO PARAMO
Final 2/16/2021 Corrections Issued OSVALDO PARAMO
Green Building Final 2/16/2021 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/16/2021 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 2/16/2021 Approved OSVALDO PARAMO
Final 2/23/2021 OK to Issue CofO ROBERT VORHIS
Service/Power Release 2/23/2021 Approved ROBERT VORHIS