5422 W SMILEY DR 90016
Certificate Information: 5422 W SMILEY DR 90016
- Application / Permit
- 19010-30000-05983
- Plan Check / Job No.
- B19WL07201
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-story SFD with attached 2-car garage at front of the lot.
- Permit Issued
- Issued on 4/10/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Green Plans Picked Up | 1/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 1/24/2020 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 1/31/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/31/2020 | APPLICANT |
| Plan Check Approved | 3/3/2020 | JAHANSHAH POURHASSAN |
| Issued | 4/10/2020 | LADBS |
| CofO in Progress | 2/24/2021 | ROBERT VORHIS |
| Permit Finaled | 4/8/2021 | DEROLD HAUFF |
| Permit Finaled | 4/8/2021 | DEROLD HAUFF |
| CofO Issued | 4/8/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2020 | OSCAR GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2020 | OSCAR GUTIERREZ |
| Hydrant and Access approval | Cleared | 1/31/2020 | ROBERT DUFF |
| Sewer availability | Cleared | 1/31/2020 | OSCAR GUTIERREZ |
| Low Impact Development | Cleared | 2/10/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/10/2020 | ERIK BEASLEY |
| Green Code | Cleared | 2/11/2020 | RICHARD GARCIA |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/21/2020 | Approved | DAVID CHAN |
| Footing/Foundation/Slab | 4/28/2020 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 5/4/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2020 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 9/16/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 9/16/2020 | Corrections Issued | DAVID CHAN |
| BUILDING-Rough-Frame | 9/22/2020 | Not Ready for Inspection | DAVID CHAN |
| ELECTRICAL-Rough | 9/22/2020 | Approved | DAVID CHAN |
| Green Building Rough | 9/22/2020 | Approved | DAVID CHAN |
| Wood Frame | 9/24/2020 | Approved | DAVID CHAN |
| Insulation | 9/28/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 10/8/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 10/8/2020 | Not Ready for Inspection | DAVID CHAN |
| Interior/Exterior Lathing | 10/14/2020 | Approved | DAVID CHAN |
| Shower Pan | 10/14/2020 | Approved | DAVID CHAN |
| Gas Test | 1/28/2021 | Approved | OSVALDO PARAMO |
| HVAC-Final | 1/28/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 1/28/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/8/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 2/8/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 2/8/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 2/8/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 2/8/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 2/8/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 2/8/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 2/10/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 2/16/2021 | Approved | OSVALDO PARAMO |
| Final | 2/16/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 2/16/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 2/16/2021 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 2/16/2021 | Approved | OSVALDO PARAMO |
| Final | 2/23/2021 | OK to Issue CofO | ROBERT VORHIS |
| Service/Power Release | 2/23/2021 | Approved | ROBERT VORHIS |