1563 S ENSLEY AVE 90024
Certificate Information: 1563 S ENSLEY AVE 90024
- Application / Permit
- 19010-30000-05961
- Plan Check / Job No.
- B19WL07184
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (n) detached garage w/ pool bathroom
- Permit Issued
- Issued on 9/17/2021
- Issuing Office
- Current Status
- Issued on 9/17/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Green Plans Picked Up | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | KAVIAN REFAHI |
| Corrections Issued | 2/10/2020 | KAVIAN REFAHI |
| Quality Review Completed | 2/21/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 2/21/2020 | APPLICANT |
| Applicant returned to address corrections | 1/13/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/26/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 4/16/2021 | KAVIAN REFAHI |
| Plan Check Approved | 9/7/2021 | KAVIAN REFAHI |
| Issued | 9/17/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 4/7/2020 | ROBERT DUFF |
| Construction within easement | Cleared | 1/15/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/23/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/12/2021 | DENNIS BRAGIN |
| GPI Written Notices | Cleared | 8/17/2021 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 8/17/2021 | KAVIAN REFAHI |
Contact Information
| Architect | Williger,, Paul Brant; Lic. No.: C24022 | 26176 FAIRSIDE ROAD MALIBU, CA 90265 |
| Contractor | Future Home Builders Inc; Lic. No.: 870227-B | 6860 CANBY AVE #111 RESEDA, CA 91335 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Kaligi,, Sean; Lic. No.: M37797 | 655 N CENTRAL AVE 17TH FL GLENDALE, CA 91203 |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 10/11/2022 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/11/2022 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 10/11/2022 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 10/14/2022 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/2/2022 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Barrier | 11/2/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Subgrade | 11/2/2022 | Partial Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 11/2/2022 | Partial Inspection | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/4/2022 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/8/2022 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/28/2022 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 12/19/2022 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Barrier | 12/19/2022 | Approved | STEPHANIE SWANSON |
| METHANE-Subgrade | 12/19/2022 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Partial Approval | STEPHANIE SWANSON |