1563 S ENSLEY AVE 90024
Certificate Information: 1563 S ENSLEY AVE 90024
- Application / Permit
- 19010-30000-05960
- Plan Check / Job No.
- B19WL07184
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) SFD (2-story over basement)
- Permit Issued
- Issued on 9/17/2021
- Issuing Office
- Current Status
- Issued on 9/17/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Green Plans Picked Up | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | KAVIAN REFAHI |
| Corrections Issued | 2/10/2020 | KAVIAN REFAHI |
| Quality Review Completed | 2/21/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 2/21/2020 | APPLICANT |
| Applicant returned to address corrections | 1/13/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/26/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 4/16/2021 | KAVIAN REFAHI |
| Plan Check Approved | 9/7/2021 | KAVIAN REFAHI |
| No Progress | 9/7/2021 | KAVIAN REFAHI |
| Plan Check Approved | 9/16/2021 | KAVIAN REFAHI |
| Issued | 9/17/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/21/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2020 | DINAH GARIN |
| Permit | Cleared | 2/21/2020 | DINAH GARIN |
| Sewer availability | Cleared | 2/21/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 4/7/2020 | ROBERT DUFF |
| Specific Plan | Cleared | 5/13/2020 | FREDDY GARCIA |
| Trees in Parkway | Cleared | 7/16/2020 | JOHN KIM |
| Excavation more than 5-ft deep | Cleared | 1/26/2021 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 2/23/2021 | ORVAL HERNANDEZ-MARCI |
| Permit | Cleared | 3/12/2021 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 3/12/2021 | DENNIS BRAGIN |
| GPI Written Notices | Cleared | 8/17/2021 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 8/17/2021 | KAVIAN REFAHI |
Contact Information
| Architect | Williger,, Paul Brant; Lic. No.: C24022 | 26176 FAIRSIDE ROAD MALIBU, CA 90265 |
| Contractor | Future Home Builders Inc; Lic. No.: 870227-B | 6860 CANBY AVE #111 RESEDA, CA 91335 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Kaligi,, Sean; Lic. No.: M37797 | 655 N CENTRAL AVE 17TH FL GLENDALE, CA 91203 |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 1/12/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 5/2/2022 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 5/2/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Methane Barrier | 5/10/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Methane Barrier | 5/11/2022 | Conditional Approval | BRENDAN LOONEY |
| Special/Order Compliance | 5/11/2022 | Approved | BRENDAN LOONEY |
| Deputy Methane Barrier | 5/12/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/31/2022 | Partial Approval | BRENDAN LOONEY |
| Deputy Methane Barrier | 6/1/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 6/3/2022 | Conditional Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 6/22/2022 | Conditional Approval | MICHAEL PELHAM |
| Reinforced Concrete Frame | 6/22/2022 | Partial Approval | MICHAEL PELHAM |
| Special/Order Compliance | 6/22/2022 | Partial Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 7/6/2022 | Corrections Issued | CHRISTOPHER WILSON |
| METHANE-Barrier | 7/6/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| METHANE-Subgrade | 7/6/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/11/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/13/2022 | Approved | MICHAEL PELHAM |
| Deputy Methane Barrier | 8/2/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 8/5/2022 | No Access for Inspection | PATRICK QUALEY |
| Deputy Drilled-In Anchors | 8/24/2022 | Approved | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 8/26/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 8/26/2022 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Barrier | 8/26/2022 | Approved | STEPHANIE SWANSON |
| METHANE-Subgrade | 8/26/2022 | Approved | ANDREW NAVE |
| Deputy Methane Barrier | 9/1/2022 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Methane Barrier | 9/30/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/2/2022 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/8/2022 | Partial Approval | STEPHANIE SWANSON |
| Deputy Methane Barrier | 11/16/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 11/17/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/28/2022 | Partial Approval | RICHARD STEINBACH |
| Deputy Methane Barrier | 12/16/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2023 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Methane Barrier | 5/2/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2023 | Partial Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 5/3/2023 | Partial Inspection | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Methane Barrier | 5/9/2023 | Conditional Approval | BRENDAN LOONEY |
| Deputy Methane Barrier | 6/13/2023 | Conditional Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 11/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 11/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/6/2023 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 12/6/2023 | Approved | STEPHANIE SWANSON |
| Deputy Methane Barrier | 1/3/2024 | Conditional Approval | MICHAEL PELHAM |
| Special/Order Compliance | 1/10/2024 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 1/10/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2024 | Partial Approval | STEPHANIE SWANSON |
| Pre-Inspection | 7/22/2024 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/25/2024 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/25/2024 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/20/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/10/2024 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 10/23/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/23/2024 | Partial Approval | STEPHANIE SWANSON |
| Service/Power Release | 11/7/2024 | Partial Approval | STEPHANIE SWANSON |
| Pre-Inspection | 7/2/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 10/15/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 10/15/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 10/15/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Rough | 10/15/2025 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 10/15/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Rough | 10/20/2025 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Rough | 10/24/2025 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 10/24/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Rough | 11/7/2025 | Corrections Issued | RUBEN RIVAS |
| Underground Mechanical | 12/23/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 3/16/2026 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/16/2026 | Approved | EVAN COOPER |