1316 N VISTA ST 90046

Certificate Information: 1316 N VISTA ST 90046

Application / Permit
19010-30000-05955
Plan Check / Job No.
B19WL07181
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New single family dwelling with attached garage per small lot subdivision VTT-82081-SL (Lot #1, Unit A)
Permit Issued
Issued on 5/6/2022
Issuing Office
Current Status
CofO Issued on 10/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Green Plans Picked Up 1/31/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 2/18/2020 KAMRAN GHOTBI RAVANDI
Quality Review Completed 2/25/2020 FELIX FIGUEROA
Applicant returned to address corrections 9/16/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/5/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/2/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/23/2021 VLADIMIR ARUTYUNYAN
Applicant returned to address corrections 2/1/2022 JASON JANGADA
Applicant returned to address corrections 3/17/2022 JASON JANGADA
Plan Check Approved 3/18/2022 JASON JANGADA
Issued 5/6/2022 APPLICANT
Building Plans Picked Up 5/18/2022 APPLICANT
CofO in Progress 10/10/2024 BRENDAN MORELLI
Permit Finaled 10/11/2024 RUBEN SALAS
CofO Issued 10/11/2024 RUBEN SALAS
Permit Finaled 10/11/2024 RUBEN SALAS

Permit Application Clearance Information

Trees in Parkway Cleared 2/26/2020 JOHN KIM
Hydrant and Access approval Cleared 8/10/2020 MATTHEW CRAIG
Green Code Cleared 8/13/2020 RICHARD GARCIA
Eng Process Fee Ord 176,300 Cleared 8/17/2020 PAMELA TENEZA
Address approval Cleared 8/18/2020 CECILIO NAVARRO
Permit Cleared 8/18/2020 CECILIO NAVARRO
Highway dedication Cleared 9/29/2020 ELAINE LEI
Sewer availability Cleared 4/15/2021 WALLIE JONG
Low Impact Development Cleared 11/5/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/8/2021 WALLIE JONG
Miscellaneous Cleared 3/8/2022 LINDA MARGARET
Tract Map conditions Cleared 3/11/2022 DANIEL CORONADO
Building over 3-story or 36-ft Cleared 3/17/2022 CALOSHA APPROVED

Contact Information

Contractor Carteng Construction Corporation; Lic. No.: 1032972-B 820 CAYO GRANDE CT      NEWBURY PARK, CA 91320
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/22/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/29/2022 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/4/2022 Partial Approval SCOTT FINNILA
Grounding or Bonding 10/4/2022 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 10/5/2022 Conditional Approval ALEJANDRO DE ARTOLA
Special/Order Compliance 10/17/2022 Corrections Issued SCOTT FINNILA
Underground Mechanical 10/17/2022 Corrections Issued SCOTT FINNILA
Deputy Reinf. Concrete 10/18/2022 Conditional Approval ALEJANDRO DE ARTOLA
Underground Mechanical 10/20/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 11/3/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 11/4/2022 Conditional Approval STUART CHAPMAN
Deputy Steel/Welding 12/19/2022 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Steel/Welding 12/21/2022 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Steel/Welding 12/29/2022 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 12/29/2022 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/3/2023 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/11/2023 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 2/10/2023 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 2/23/2023 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Steel/Welding 3/2/2023 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 3/15/2023 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/14/2023 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 4/25/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 5/23/2023 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 6/8/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Rough 8/29/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 9/5/2023 Conditional Approval BRENDAN MORELLI
PLUMBING-Rough 10/2/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 10/6/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 10/12/2023 Partial Approval BRENDAN MORELLI
HVAC-Rough 11/3/2023 Corrections Issued BRENDAN MORELLI
HVAC-Rough 11/8/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/15/2023 Conditional Approval BRENDAN MORELLI
Insulation 11/17/2023 Conditional Approval BRENDAN MORELLI
Drywall Nailing 12/18/2023 Conditional Approval BRENDAN MORELLI
Green Building Rough 12/18/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 12/18/2023 Partial Approval BRENDAN MORELLI
Shower Pan 12/18/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 12/26/2023 Approved BRENDAN MORELLI
Underground Mechanical 4/16/2024 Partial Approval BRENDAN MORELLI
Underground Mechanical 5/1/2024 Partial Approval SCOTT FINNILA
Gas Test 7/11/2024 Approved BRENDAN MORELLI
PLUMBING-Final 8/2/2024 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 8/6/2024 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 8/7/2024 Approved BRENDAN MORELLI
PLUMBING-Final 8/9/2024 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/9/2024 SGSOV Approved BRENDAN MORELLI
HVAC-Final 8/16/2024 Partial Approval SCOTT FINNILA
HVAC-Final 9/3/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 10/7/2024 Approved BRENDAN MORELLI
Drywall Nailing 10/7/2024 Approved BRENDAN MORELLI
Final 10/7/2024 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 10/7/2024 Approved BRENDAN MORELLI
Green Building Final 10/7/2024 Approved BRENDAN MORELLI
Service/Power Release 10/7/2024 Approved BRENDAN MORELLI
Smoke Detectors 10/7/2024 Approved BRENDAN MORELLI
Structural Steel Frame 10/7/2024 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 10/7/2024 Approved BRENDAN MORELLI
Final 10/10/2024 OK to Issue CofO BRENDAN MORELLI