4691 N GLENALBYN DR 90065

Certificate Information: 4691 N GLENALBYN DR 90065

Application / Permit
19010-30000-05937
Plan Check / Job No.
B19WL07171
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) Single family dwelling with attached garage. Equipped with fire sprinkler system NFPA-13D. PER ZA-2020-4071-ZAD-SPP-HCA
Permit Issued
Issued on 12/6/2023
Issuing Office
Current Status
CofO Issued on 11/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 ALFREDO JARA
Corrections Issued 2/11/2020 ALFREDO JARA
Quality Review Completed 2/21/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/9/2021 ALFREDO JARA
Applicant returned to address corrections 2/10/2021 ALFREDO JARA
Applicant returned to address corrections 3/2/2021 ALFREDO JARA
Applicant returned to address corrections 3/31/2021 ALFREDO JARA
Applicant returned to address corrections 11/1/2021 ALFREDO JARA
Applicant returned to address corrections 11/16/2021 ALFREDO JARA
Applicant returned to address corrections 1/5/2022 ALFREDO JARA
Building Plans Picked Up 1/24/2022 APPLICANT
Applicant returned to address corrections 6/6/2022 ALFREDO JARA
Applicant returned to address corrections 9/6/2022 ALFREDO JARA
Applicant returned to address corrections 10/21/2022 ALFREDO JARA
Applicant returned to address corrections 3/13/2023 ALFREDO JARA
Applicant returned to address corrections 4/24/2023 ALFREDO JARA
Applicant returned to address corrections 5/5/2023 ALFREDO JARA
Applicant returned to address corrections 6/16/2023 ALFREDO JARA
Plan Check Approved 11/7/2023 ALFREDO JARA
Issued 12/6/2023 APPLICANT
CofO in Progress 11/20/2025 ALIZAH MAYAGOITIA
Permit Finaled 11/23/2025 DEROLD HAUFF
CofO Issued 11/23/2025 DEROLD HAUFF
Permit Finaled 11/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/17/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 7/17/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/21/2020 CECILIO NAVARRO
Green Code Cleared 8/25/2020 RICHARD GARCIA
Excavation more than 5-ft deep Cleared 9/15/2020 CALOSHA APPROVED
Hydrant and Access approval Cleared 11/3/2020 MATTHEW CRAIG
Low Impact Development Cleared 12/23/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/2/2021 CECILIO NAVARRO
Sewer availability Cleared 2/9/2021 CECILIO NAVARRO
Permit Cleared 10/29/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 11/9/2021 KHOUNG LE
BHO/Hillside ordinance Cleared 11/23/2021 JEANIE LAM
Miscellaneous Cleared 3/7/2022 ROBIN ETNIEL
Certificate of Compliance Cleared 3/15/2022 MARC WOERSCHING
Trees in Parkway Cleared 5/19/2022 ADALBERTO VERA
Specific Plan Cleared 5/26/2022 ANACANY HURTADO
GPI Written Notices Cleared 5/18/2023 ALFREDO JARA
Grading Pre-Inspection Cleared 5/18/2023 ALFREDO JARA

Contact Information

Contractor Molina Carlos Alberto Construction; Lic. No.: 973892-B 4348 LYND AVENUE      ARCADIA, CA 91006
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 1551 RANDALL ST      GLENDALE, CA 91201
Geologist Haenschke,, Eirik Francis; Lic. No.: EG1597 9616 GIERSON AVE      CHATSWORTH, CA 91311

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/3/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/3/2024 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 5/13/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/13/2024 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 5/22/2024 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/22/2024 Partial Approval OSVALDO PARAMO
Reinforced Concrete Frame 5/29/2024 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 6/24/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 7/1/2024 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 8/1/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 8/14/2024 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 8/21/2024 Approved LUIS CASTRO
Deputy Grading 9/11/2024 Conditional Approval OSVALDO PARAMO
Reinforced Concrete Frame 9/24/2024 Partial Approval OSVALDO PARAMO
Reinforced Concrete Frame 10/7/2024 Partial Approval ALIZAH MAYAGOITIA
Reinforced Concrete Frame 10/24/2024 Partial Approval OSVALDO PARAMO
Reinforced Concrete Frame 11/14/2024 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 Partial Approval WILLIAM SIERRA
Reinforced Concrete Frame 2/19/2025 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 3/4/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 3/4/2025 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/28/2025 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Rough 3/28/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 3/28/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/3/2025 Approved ALIZAH MAYAGOITIA
Wood Frame 4/3/2025 Approved ALIZAH MAYAGOITIA
Shower Pan 4/17/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/9/2025 Partial Approval ALIZAH MAYAGOITIA
Insulation 5/22/2025 Approved REGINA MENDEZ
Drywall Nailing 6/2/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 6/2/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/25/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 9/25/2025 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Final 9/25/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 10/2/2025 Corrections Issued ALIZAH MAYAGOITIA
Service/Power Release 10/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 10/16/2025 Corrections Issued RONNIE MEDINA
Green Building Final 10/16/2025 Approved RONNIE MEDINA
HVAC-Final 10/16/2025 Approved RONNIE MEDINA
Service/Power Release 10/16/2025 Corrections Issued RONNIE MEDINA
ELECTRICAL-Final 10/31/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 10/31/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/14/2025 Approved ALIZAH MAYAGOITIA
Final 11/14/2025 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV No Gas ALIZAH MAYAGOITIA
Service/Power Release 11/14/2025 Approved ALIZAH MAYAGOITIA
Smoke Detectors 11/14/2025 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 11/14/2025 Approved ALIZAH MAYAGOITIA
Final 11/20/2025 OK to Issue CofO ALIZAH MAYAGOITIA