4691 N GLENALBYN DR 90065
Certificate Information: 4691 N GLENALBYN DR 90065
- Application / Permit
- 19010-30000-05937
- Plan Check / Job No.
- B19WL07171
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) Single family dwelling with attached garage. Equipped with fire sprinkler system NFPA-13D. PER ZA-2020-4071-ZAD-SPP-HCA
- Permit Issued
- Issued on 12/6/2023
- Issuing Office
- Current Status
- CofO Issued on 11/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | ALFREDO JARA |
| Corrections Issued | 2/11/2020 | ALFREDO JARA |
| Quality Review Completed | 2/21/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/9/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 2/10/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 3/2/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 3/31/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 11/1/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 11/16/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 1/5/2022 | ALFREDO JARA |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Applicant returned to address corrections | 6/6/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 9/6/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 10/21/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 3/13/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 4/24/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 5/5/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 6/16/2023 | ALFREDO JARA |
| Plan Check Approved | 11/7/2023 | ALFREDO JARA |
| Issued | 12/6/2023 | APPLICANT |
| CofO in Progress | 11/20/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 11/23/2025 | DEROLD HAUFF |
| CofO Issued | 11/23/2025 | DEROLD HAUFF |
| Permit Finaled | 11/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 7/17/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2020 | CECILIO NAVARRO |
| Green Code | Cleared | 8/25/2020 | RICHARD GARCIA |
| Excavation more than 5-ft deep | Cleared | 9/15/2020 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 11/3/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/23/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/2/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 2/9/2021 | CECILIO NAVARRO |
| Permit | Cleared | 10/29/2021 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 11/9/2021 | KHOUNG LE |
| BHO/Hillside ordinance | Cleared | 11/23/2021 | JEANIE LAM |
| Miscellaneous | Cleared | 3/7/2022 | ROBIN ETNIEL |
| Certificate of Compliance | Cleared | 3/15/2022 | MARC WOERSCHING |
| Trees in Parkway | Cleared | 5/19/2022 | ADALBERTO VERA |
| Specific Plan | Cleared | 5/26/2022 | ANACANY HURTADO |
| GPI Written Notices | Cleared | 5/18/2023 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 5/18/2023 | ALFREDO JARA |
Contact Information
| Contractor | Molina Carlos Alberto Construction; Lic. No.: 973892-B | 4348 LYND AVENUE ARCADIA, CA 91006 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 1551 RANDALL ST GLENDALE, CA 91201 |
| Geologist | Haenschke,, Eirik Francis; Lic. No.: EG1597 | 9616 GIERSON AVE CHATSWORTH, CA 91311 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/3/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/3/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 5/13/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/13/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 5/22/2024 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/22/2024 | Partial Approval | OSVALDO PARAMO |
| Reinforced Concrete Frame | 5/29/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 6/24/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 7/1/2024 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/1/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/14/2024 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/21/2024 | Approved | LUIS CASTRO |
| Deputy Grading | 9/11/2024 | Conditional Approval | OSVALDO PARAMO |
| Reinforced Concrete Frame | 9/24/2024 | Partial Approval | OSVALDO PARAMO |
| Reinforced Concrete Frame | 10/7/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Reinforced Concrete Frame | 10/24/2024 | Partial Approval | OSVALDO PARAMO |
| Reinforced Concrete Frame | 11/14/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Partial Approval | WILLIAM SIERRA |
| Reinforced Concrete Frame | 2/19/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/4/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/4/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/28/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/28/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/28/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/3/2025 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 4/3/2025 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 4/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/9/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 5/22/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 6/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 6/2/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 9/25/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 9/25/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 9/25/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/2/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Service/Power Release | 10/2/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/16/2025 | Corrections Issued | RONNIE MEDINA |
| Green Building Final | 10/16/2025 | Approved | RONNIE MEDINA |
| HVAC-Final | 10/16/2025 | Approved | RONNIE MEDINA |
| Service/Power Release | 10/16/2025 | Corrections Issued | RONNIE MEDINA |
| ELECTRICAL-Final | 10/31/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 10/31/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 11/14/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV No Gas | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 11/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 11/20/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |