2 N OAKMONT DR 90049
Certificate Information: 2 N OAKMONT DR 90049
- Application / Permit
- 19010-30000-05829
- Plan Check / Job No.
- B19WL07085
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- new tennis pavilion
- Permit Issued
- Issued on 3/11/2021
- Issuing Office
- Current Status
- CofO Issued on 9/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | TARIK SAOUD |
| Corrections Issued | 1/20/2020 | TARIK SAOUD |
| Quality Review Completed | 1/28/2020 | FELIX FIGUEROA |
| Applicant returned to address corrections | 5/19/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 9/15/2020 | TARIK SAOUD |
| Green Plans Picked Up | 10/23/2020 | APPLICANT |
| Applicant returned to address corrections | 10/27/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 12/22/2020 | TARIK SAOUD |
| Plan Check Approved | 3/5/2021 | TARIK SAOUD |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| Plan Check Approved | 3/11/2021 | TARIK SAOUD |
| Issued | 3/11/2021 | APPLICANT |
| CofO in Progress | 7/30/2024 | KEVIN SARGSYAN |
| Permit Finaled | 9/24/2024 | RICHARD STEINBACH |
| CofO Issued | 9/24/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/24/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/27/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 1/27/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/27/2020 | LEE GUILBEAUX |
| CPC | Cleared | 3/26/2020 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 9/7/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/21/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 11/24/2020 | MATTHEW CRAIG |
| Grading Pre-Inspection | Cleared | 3/5/2021 | TARIK SAOUD |
Contact Information
| Architect | Rios,, Mark William; Lic. No.: C15744 | 3101 W EXPOSITION PLACE LOS ANGELES, CA 90018 |
| Contractor | Holz Richard Inc; Lic. No.: 294504-B | 520 S SEPULVEDA BLVD #407 LOS ANGELES, CA 90049 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Kwan,, Denny Chi-Ho; Lic. No.: S4887 | 5638 NEWFIELDS LN DUBLIN, CA 94568 |
| Engineer | Rezaian,, Reza; Lic. No.: C62048 | 3665 MOUNTAIN VIEW AVENUE LOS ANGELES, CA 90066 |
| Geologist | Daugherty,, Daniel Thomas; Lic. No.: EG2569 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 5/24/2021 | Partial Approval | JUAN VALENZUELA |
| Piling/Pier/Caisson | 7/14/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 7/20/2021 | Conditional Approval | JUAN VALENZUELA |
| Underground Mechanical | 10/21/2022 | Approved | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 11/16/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 1/25/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/20/2023 | No Access for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 9/20/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/20/2023 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/29/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/29/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 9/29/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/29/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 10/16/2023 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 10/16/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 10/19/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 6/27/2024 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 6/27/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 6/27/2024 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/10/2024 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/11/2024 | Approved | KEVIN SARGSYAN |
| Green Building Final | 7/11/2024 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 7/11/2024 | Approved | KEVIN SARGSYAN |
| Final | 7/30/2024 | OK to Issue CofO | KEVIN SARGSYAN |
| Service/Power Release | 7/30/2024 | Approved | KEVIN SARGSYAN |