127 W VIA MARINA 90292

Certificate Information: 127 W VIA MARINA 90292

Application / Permit
19010-30000-05731
Plan Check / Job No.
B19WL07019
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) story 4-story SFD w/ attached garage
Permit Issued
Issued on 10/8/2020
Issuing Office
Current Status
CofO Corrected on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/31/2019 TARIK SAOUD
Corrections Issued 1/6/2020 TARIK SAOUD
Quality Review Completed 1/13/2020 FELIX FIGUEROA
Green Plans Picked Up 9/10/2020 APPLICANT
Plan Check Approved 9/24/2020 TARIK SAOUD
Issued 10/8/2020 APPLICANT
Building Plans Picked Up 10/13/2020 APPLICANT
CofO in Progress 8/5/2022 STEPHANIE SWANSON
CofO Issued-Status Void 8/10/2022 DANIEL ORRANTE
Permit Finaled-Status Void 8/10/2022 DANIEL ORRANTE
Re-Activate Permit 12/20/2022 DANIEL ORRANTE
Permit Finaled 5/11/2023 DANIEL ORRANTE
CofO Corrected 5/11/2023 DANIEL ORRANTE
Permit Finaled 5/11/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/15/2020 DINAH GARIN
Miscellaneous Cleared 1/15/2020 DENZEL HENDERSON
Miscellaneous Cleared 1/15/2020 DENZEL HENDERSON
Permit Cleared 1/15/2020 DINAH GARIN
Sewer availability Cleared 1/15/2020 DINAH GARIN
ZA Case Cleared 1/15/2020 DENZEL HENDERSON
ZA Case Cleared 1/15/2020 DENZEL HENDERSON
Trees in Parkway Cleared 1/17/2020 ADRIAN SANCHEZ
Construction near power lines Cleared 1/28/2020 OSCAR CASTRO
ZA Case Cleared 2/21/2020 DENZEL HENDERSON
Hydrant and Access approval Cleared 4/9/2020 ROBERT DUFF
Coastal Zone Cleared 4/27/2020 DENZEL HENDERSON
Miscellaneous Cleared 4/27/2020 DENZEL HENDERSON
Specific Plan Cleared 4/27/2020 DENZEL HENDERSON
ZA Case Cleared 4/27/2020 DENZEL HENDERSON
Low Impact Development Cleared 6/25/2020 MITESH PATEL
Green Code Cleared 7/14/2020 DONALD CRICHLOW
Roof/Waste drainage to street Cleared 9/29/2020 DINAH GARIN

Contact Information

Architect Lee,, Michael R; Lic. No.: C26726 3119 BAYVIEW DRIVE      MANHATTAN BEACH, CA 90266
Contractor Lee Michael Robert Construction Inc; Lic. No.: 639772-B 2200 HIGHLAND AVENUE      MANHATTAN BEACH, CA 90266
Engineer Mccullum,, Eric William; Lic. No.: C68850 727 2ND ST STE 104      HERMOSA BEACH, CA 90254
Geologist Miller,, Jonathan Steven; Lic. No.: EG2391 1423 S BEVERLY GLEN BLVD APT B      LOS ANGELES, CA 90024

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/12/2020 Partial Approval DAVID HEINE
Special/Order Compliance 11/12/2020 Partial Inspection PIERRE VEGA
Deputy Methane Barrier 12/4/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 12/4/2020 Partial Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 12/4/2020 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 12/4/2020 Partial Approval JUAN VALENZUELA
Grounding or Bonding 12/4/2020 Partial Inspection JUAN VALENZUELA
METHANE-Barrier 12/4/2020 Partial Inspection JUAN VALENZUELA
METHANE-Subgrade 12/4/2020 Partial Inspection JUAN VALENZUELA
Deputy Reinf. Concrete 12/8/2020 Partial Approval DAVID HEINE
PLUMBING-Rough 12/14/2020 Partial Inspection JUAN VALENZUELA
Sewer 12/14/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 12/16/2020 Partial Approval DAVID HEINE
Sewer 12/16/2020 Approved DAVID HEINE
METHANE-Subgrade 12/18/2020 Approved DAVID HEINE
Deputy Methane Barrier 12/22/2020 Partial Approval DAVID HEINE
Deputy Methane Barrier 12/24/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 12/28/2020 Partial Approval DAVID HEINE
METHANE-Barrier 12/28/2020 Approved DAVID HEINE
METHANE-Final 12/28/2020 Not Ready for Inspection DAVID HEINE
Deputy Steel/Welding 1/7/2021 Partial Approval DAVID HEINE
Green Building Rough 1/13/2021 Not Ready for Inspection JUAN VALENZUELA
METHANE-Rough 1/13/2021 Not Ready for Inspection JUAN VALENZUELA
Structural Steel Frame 1/13/2021 Partial Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 1/13/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Partial Approval JUAN VALENZUELA
Deputy Methane Barrier 2/2/2021 Conditional Approval JOHNNY MIRANDA
Deputy Methane Barrier 2/3/2021 Approved JOHNNY MIRANDA
Deputy Steel/Welding 2/4/2021 Conditional Approval JOHNNY MIRANDA
Deputy Steel/Welding 2/5/2021 Conditional Approval JOHNNY MIRANDA
Deputy Steel/Welding 2/18/2021 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 2/18/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/3/2021 Conditional Approval JOHNNY MIRANDA
Deputy Steel/Welding 3/26/2021 Conditional Approval JOHNNY MIRANDA
Deputy Steel/Welding 3/30/2021 Corrections Issued JOHNNY MIRANDA
Deputy Steel/Welding 4/1/2021 Conditional Approval JOHNNY MIRANDA
PLUMBING-Rough 4/12/2021 Partial Approval JOHNNY MIRANDA
Deputy Wood Construction 4/15/2021 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Approval JOHNNY MIRANDA
Gas Test 5/21/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 5/21/2021 Partial Approval JOHNNY MIRANDA
Deputy Methane Barrier 6/14/2021 Conditional Approval JOHNNY MIRANDA
Insulation 6/14/2021 Partial Approval JOHNNY MIRANDA
Deputy Wood Construction 6/16/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/16/2021 Partial Approval JOHNNY MIRANDA
METHANE-Rough 6/16/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 6/29/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 7/2/2021 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 7/6/2021 Conditional Approval JOHNNY MIRANDA
HVAC-Rough 7/15/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 7/20/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 8/11/2021 Approved JOHNNY MIRANDA
Green Building Rough 8/11/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 8/11/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 9/14/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 9/14/2021 Not Ready for Inspection JOHNNY MIRANDA
Verify Sprinkler Sign Off 9/14/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 10/5/2021 Approved JOHNNY MIRANDA
Green Building Rough 10/5/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 10/5/2021 Partial Approval JOHNNY MIRANDA
Insulation 10/21/2021 Partial Approval BOBBY KEY
Insulation 10/25/2021 Approved JOHN KAYON
Drywall Nailing 11/1/2021 Approved RYAN SALAZAR
Shower Pan 11/2/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 12/13/2021 Approved BOBBY KEY
ELECTRICAL-Final 6/16/2022 No Access for Inspection PATRICK QUALEY
Pre-Inspection 6/16/2022 Partial Inspection PATRICK QUALEY
Service/Power Release 6/16/2022 Not Ready for Inspection PATRICK QUALEY
ELECTRICAL-Final 6/22/2022 Corrections Issued DAVID FEILER
Gas Test 6/22/2022 Approved DAVID FEILER
PLUMBING-Final 6/22/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Final 6/29/2022 Approved DAVID FEILER
HVAC-Final 6/29/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 6/29/2022 Partial Approval DAVID FEILER
HVAC-Final 7/6/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 7/6/2022 Not Ready for Inspection DAVID FEILER
Final 7/8/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 7/8/2022 Approved DAVID FEILER
Green Building Final 7/8/2022 Not Ready for Inspection DAVID FEILER
HVAC-Final 7/8/2022 Partial Approval DAVID FEILER
PLUMBING-Final 7/8/2022 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 7/8/2022 SGSOV Not Ready DAVID FEILER
Service/Power Release 7/8/2022 Not Ready for Inspection DAVID FEILER
Smoke Detectors 7/8/2022 Approved DAVID FEILER
Structural Steel Frame 7/8/2022 Approved DAVID FEILER
Service/Power Release 7/20/2022 Approved MICHAEL PELHAM
Final 7/22/2022 Partial Approval DAVID FEILER
Green Building Final 7/22/2022 Approved DAVID FEILER
HVAC-Final 7/22/2022 Approved DAVID FEILER
PLUMBING-Final 7/22/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Approved DAVID FEILER
Final 8/3/2022 Not Ready for Inspection STEPHANIE SWANSON
Final 8/4/2022 Not Ready for Inspection STEPHANIE SWANSON
Final 8/5/2022 OK to Issue CofO STEPHANIE SWANSON