4044 S MICHAEL AVE 90066
Certificate Information: 4044 S MICHAEL AVE 90066
- Application / Permit
- 19010-30000-05730
- Plan Check / Job No.
- B19WL07012
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2-story addition to (e) SFD, add an att. 2-car garage
- Permit Issued
- Issued on 2/25/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2019 | APPLICANT |
| Green Plans Picked Up | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2019 | REZA HAGHIGHAT |
| Corrections Issued | 1/6/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 1/17/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/21/2020 | APPLICANT |
| Plan Check Approved | 2/25/2020 | REZA HAGHIGHAT |
| Issued | 2/25/2020 | LADBS |
| CofO in Progress | 1/7/2021 | ENRIQUE MIRELES |
| Permit Finaled | 1/25/2021 | VINCENT COTTON |
| CofO Issued | 1/25/2021 | VINCENT COTTON |
| Permit Finaled | 1/25/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 1/31/2020 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 2/11/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 2/11/2020 | ORVAL HERNANDEZ-MARCIAL |
| Permit | Cleared | 2/11/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 2/11/2020 | THOMAS LANG |
| Sewer availability | Cleared | 2/11/2020 | THOMAS LANG |
| Green Code | Cleared | 2/20/2020 | DONALD CRICHLOW |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/4/2020 | Corrections Issued | DAVID FEILER |
| Sewer | 6/4/2020 | Approved | DAVID FEILER |
| Underground Mechanical | 6/4/2020 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 6/5/2020 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/11/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2020 | Conditional Approval | DAVID HEINE |
| PLUMBING-Rough | 8/12/2020 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/13/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 8/20/2020 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 9/16/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/25/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 9/25/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/30/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Shower Pan | 9/30/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/5/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 10/5/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 10/5/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/5/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 10/13/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 10/13/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 10/14/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Gas Test | 12/4/2020 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 12/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 12/9/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 12/9/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 12/9/2020 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 12/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/10/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/15/2020 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 12/15/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 12/18/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/18/2020 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/18/2020 | Approved | ENRIQUE MIRELES |
| Final | 1/7/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 1/7/2021 | Approved | ENRIQUE MIRELES |