2914 S MOTOR AVE 90064
Certificate Information: 2914 S MOTOR AVE 90064
- Application / Permit
- 19010-30000-05694
- Plan Check / Job No.
- B19WL06985
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD w/ att. 2-car garage
- Permit Issued
- Issued on 2/25/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2019 | APPLICANT |
| Green Plans Picked Up | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2019 | REZA HAGHIGHAT |
| Corrections Issued | 1/6/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 1/17/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/21/2020 | APPLICANT |
| Plan Check Approved | 2/25/2020 | REZA HAGHIGHAT |
| Issued | 2/25/2020 | LADBS |
| CofO in Progress | 12/2/2020 | KEVIN SARGSYAN |
| Permit Finaled | 1/7/2021 | KENNETH NAGLE |
| CofO Issued | 1/7/2021 | KENNETH NAGLE |
| Permit Finaled | 1/7/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 1/31/2020 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 2/11/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 2/11/2020 | ORVAL HERNANDEZ-MARCIAL |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2020 | JUAN ASHTON |
| Permit | Cleared | 2/12/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 2/12/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 2/12/2020 | JUAN ASHTON |
| Green Code | Cleared | 2/20/2020 | DONALD CRICHLOW |
| GPI Written Notices | Cleared | 2/25/2020 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 2/25/2020 | REZA HAGHIGHAT |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/24/2020 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 4/24/2020 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 4/28/2020 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 4/28/2020 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/6/2020 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/8/2020 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 5/8/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 5/8/2020 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2020 | Conditional Approval | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 5/29/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2020 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2020 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 6/30/2020 | Partial Approval | KENNETH NAGLE |
| Interior/Exterior Lathing | 7/13/2020 | Approved | KEVIN SARGSYAN |
| Shower Pan | 7/13/2020 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/14/2020 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 7/14/2020 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 7/14/2020 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/14/2020 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/16/2020 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/16/2020 | Approved | KEVIN SARGSYAN |
| Gas Test | 7/16/2020 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 7/16/2020 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 7/16/2020 | Corrections Issued | KEVIN SARGSYAN |
| METHANE-Rough | 7/16/2020 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/16/2020 | Approved | KEVIN SARGSYAN |
| Shower Pan | 7/16/2020 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 7/16/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/27/2020 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 7/27/2020 | Approved | KEVIN SARGSYAN |
| Shower Pan | 7/27/2020 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 7/27/2020 | Approved | KEVIN SARGSYAN |
| Insulation | 8/3/2020 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 8/11/2020 | Corrections Issued | KEVIN SARGSYAN |
| Drywall Nailing | 8/12/2020 | Approved | KEVIN SARGSYAN |
| Insulation | 8/12/2020 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/7/2020 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 10/7/2020 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 10/7/2020 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/7/2020 | SGSOV Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/9/2020 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/9/2020 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 11/23/2020 | Approved | KEVIN SARGSYAN |
| Final | 12/2/2020 | OK to Issue CofO | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/2/2020 | Approved | KEVIN SARGSYAN |
| Green Building Final | 12/2/2020 | Approved | KEVIN SARGSYAN |
| METHANE-Barrier | 12/2/2020 | Approved | KEVIN SARGSYAN |
| METHANE-Subgrade | 12/2/2020 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 12/2/2020 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 12/2/2020 | Approved | KEVIN SARGSYAN |