Piling/Pier/Caisson
|
1/4/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
1/13/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
4/27/2021
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Sewer
|
4/27/2021
|
Approved
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
5/6/2021
|
Not Ready for Inspection
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
5/12/2021
|
Approved
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
5/13/2021
|
Conditional Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
6/8/2021
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Reinforced Concrete Frame
|
6/9/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
6/14/2021
|
Approved
|
RAUL BARAJAS
|
|
Sewer
|
6/29/2021
|
Partial Approval
|
RICHARD STEINBACH
|
|
Gas Test
|
7/27/2021
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
7/27/2021
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Pre-Inspection
|
7/29/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
8/10/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
9/3/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
9/21/2021
|
Partial Approval
|
RICHARD STEINBACH
|
|
Deputy Reinf. Concrete
|
9/27/2021
|
Conditional Approval
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
9/30/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
10/1/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
10/4/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
1/11/2022
|
Approved
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
1/12/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
1/18/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/25/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/15/2022
|
Approved
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/18/2022
|
Corrections Issued
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/6/2022
|
Approved
|
RAUL BARAJAS
|
|
HVAC-Rough
|
6/29/2022
|
Approved
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
6/29/2022
|
Approved
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
7/7/2022
|
Approved
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/28/2022
|
Approved
|
RAUL BARAJAS
|
|
Shower Pan
|
7/28/2022
|
Corrections Issued
|
RAUL BARAJAS
|
|
Wood Frame
|
7/28/2022
|
Approved
|
RAUL BARAJAS
|
|
Insulation
|
8/11/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
9/9/2022
|
Approved
|
RAUL BARAJAS
|
|
Insulation
|
10/12/2022
|
Approved
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
12/9/2022
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Insulation
|
12/19/2022
|
Approved
|
STUART CHAPMAN
|
|
Interior/Exterior Lathing
|
1/5/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Drywall Nailing
|
1/11/2023
|
Approved
|
RICHARD DOCKUS
|
|
Green Building Rough
|
1/11/2023
|
Approved
|
RICHARD DOCKUS
|
|
Interior/Exterior Lathing
|
1/17/2023
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Interior/Exterior Lathing
|
2/27/2023
|
Approved
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
6/30/2023
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Service/Power Release
|
6/30/2023
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
PLUMBING-Final
|
8/31/2023
|
Approved
|
RAUL BARAJAS
|
|
Service/Power Release
|
9/8/2023
|
Corrections Issued
|
STUART CHAPMAN
|
|
Excavation/Setback/Form/Re-Bar
|
9/22/2023
|
Approved
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
10/2/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
10/5/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
ELECTRICAL-Final
|
10/17/2023
|
Approved
|
RAUL BARAJAS
|
|
Service/Power Release
|
10/17/2023
|
Approved
|
RAUL BARAJAS
|
|
HVAC-Final
|
10/24/2023
|
Approved
|
STUART CHAPMAN
|
|
BUILDING-Rough-Frame
|
5/10/2024
|
Approved
|
RAUL BARAJAS
|
|
Final
|
5/10/2024
|
Corrections Issued
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
5/10/2024
|
Approved
|
RAUL BARAJAS
|
|
Green Building Final
|
5/10/2024
|
Approved
|
RAUL BARAJAS
|
|
SGSOV-Seismic Gas S/O Valve
|
5/10/2024
|
SGSOV Approved
|
RAUL BARAJAS
|
|
Smoke Detectors
|
5/10/2024
|
Approved
|
RAUL BARAJAS
|
|
Structural Steel Frame
|
5/10/2024
|
Approved
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
5/10/2024
|
Approved
|
RAUL BARAJAS
|
|
Final
|
6/12/2024
|
OK to Issue CofO
|
BRIAN SULLIVAN
|