1230 N MARIPOSA AVE 90029
Certificate Information: 1230 N MARIPOSA AVE 90029
- Application / Permit
- 19010-30000-05628
- Plan Check / Job No.
- B19WL06926
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SFD SMALL LOT SUB DIVISION WITH ATTACHED GARAGE (LOT A)
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Current Status
- CofO Issued on 10/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 12/12/2019 | APPLICANT |
Assigned to Plan Check Engineer | 12/27/2019 | KAMRAN GHOTBI RAVANDI |
Corrections Issued | 12/30/2019 | KAMRAN GHOTBI RAVANDI |
Quality Review Completed | 1/13/2020 | FELIX FIGUEROA |
Applicant returned to address corrections | 3/9/2020 | KAMRAN GHOTBI RAVANDI |
Green Plans Picked Up | 6/19/2020 | APPLICANT |
Applicant returned to address corrections | 6/25/2020 | KAMRAN GHOTBI RAVANDI |
Applicant returned to address corrections | 7/29/2020 | KAMRAN GHOTBI RAVANDI |
Applicant returned to address corrections | 9/16/2020 | KAMRAN GHOTBI RAVANDI |
Plan Check Approved | 9/24/2020 | KAMRAN GHOTBI RAVANDI |
Issued | 6/25/2021 | APPLICANT |
Building Plans Picked Up | 11/1/2022 | APPLICANT |
CofO in Progress | 10/1/2024 | BRENDAN MORELLI |
CofO Issued | 10/1/2024 | RUBEN SALAS |
Permit Finaled | 10/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
Trees in Parkway | Cleared | 1/17/2020 | JOHN KIM |
Eng Process Fee Ord 176,300 | Cleared | 1/21/2020 | JUAN ASHTON |
Hydrant and Access approval | Cleared | 1/22/2020 | JEREMY CARTER |
Permit | Cleared | 1/22/2020 | CELINA MORENO |
Low Impact Development | Cleared | 2/28/2020 | ORVAL HERNANDEZ-MARCI |
Address approval | Cleared | 3/10/2020 | EMIL KYUPELYAN |
Miscellaneous | Cleared | 3/11/2020 | DENZEL HENDERSON |
Green Code | Cleared | 3/24/2020 | RICHARD GARCIA |
Roof/Waste drainage to street | Cleared | 6/12/2020 | EMIL KYUPELYAN |
Sewer availability | Cleared | 6/12/2020 | EMIL KYUPELYAN |
Highway dedication | Cleared | 6/17/2020 | ELENA LOPEZ |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
NICHOLAS LOPEZ, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 2/28/2022 | Partial Inspection | SCOTT FINNILA |
Excavation/Setback/Form/Re-Bar | 3/7/2022 | Corrections Issued | SCOTT FINNILA |
Underground Mechanical | 3/7/2022 | Partial Approval | SCOTT FINNILA |
Excavation/Setback/Form/Re-Bar | 3/18/2022 | Partial Approval | STUART CHAPMAN |
Deputy Reinf. Concrete | 3/22/2022 | Conditional Approval | SCOTT FINNILA |
Footing/Foundation/Slab | 4/12/2022 | Corrections Issued | SCOTT FINNILA |
Footing/Foundation/Slab | 4/26/2022 | Corrections Issued | SCOTT FINNILA |
Excavation/Setback/Form/Re-Bar | 4/27/2022 | Approved | SCOTT FINNILA |
Deputy Reinf. Concrete | 4/29/2022 | Partial Approval | SCOTT FINNILA |
Special/Order Compliance | 8/2/2022 | Corrections Issued | SCOTT FINNILA |
Deputy Wood Construction | 9/1/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
Deputy Wood Construction | 10/26/2022 | Partial Approval | SCOTT FINNILA |
Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Partial Approval | SCOTT FINNILA |
Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Partial Approval | SCOTT FINNILA |
PLUMBING-Rough | 11/14/2022 | Corrections Issued | SCOTT FINNILA |
Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
Interior/Exterior Lathing | 12/15/2022 | Partial Inspection | ALIZAH MAYAGOITIA |
ELECTRICAL-Rough | 12/20/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
Interior/Exterior Lathing | 12/20/2022 | Partial Inspection | ALIZAH MAYAGOITIA |
HVAC-Rough | 12/21/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
PLUMBING-Rough | 12/21/2022 | Approved | ALIZAH MAYAGOITIA |
BUILDING-Rough-Frame | 12/28/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
ELECTRICAL-Rough | 12/28/2022 | Approved | ALIZAH MAYAGOITIA |
Green Building Rough | 12/28/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
HVAC-Rough | 12/28/2022 | Approved | ALIZAH MAYAGOITIA |
Interior/Exterior Lathing | 12/28/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
Verify Sprinkler Sign Off | 12/28/2022 | Approved | ALIZAH MAYAGOITIA |
BUILDING-Rough-Frame | 1/3/2023 | Conditional Approval | SCOTT FINNILA |
Green Building Rough | 1/3/2023 | Approved | SCOTT FINNILA |
Interior/Exterior Lathing | 1/3/2023 | Partial Inspection | SCOTT FINNILA |
BUILDING-Rough-Frame | 1/10/2023 | Approved | ALIZAH MAYAGOITIA |
Insulation | 1/10/2023 | Approved | ALIZAH MAYAGOITIA |
Interior/Exterior Lathing | 1/10/2023 | Partial Inspection | ALIZAH MAYAGOITIA |
Drywall Nailing | 1/31/2023 | Approved | ALIZAH MAYAGOITIA |
Interior/Exterior Lathing | 4/4/2023 | Approved | ALIZAH MAYAGOITIA |
Shower Pan | 4/4/2023 | Approved | ALIZAH MAYAGOITIA |
Underground Mechanical | 5/12/2023 | Partial Approval | ALIZAH MAYAGOITIA |
Underground Mechanical | 8/28/2023 | Partial Approval | ALIZAH MAYAGOITIA |
Underground Mechanical | 10/11/2023 | Partial Approval | BRENDAN MORELLI |
Gas Test | 12/6/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
HVAC-Final | 12/6/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
PLUMBING-Final | 12/6/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
ELECTRICAL-Final | 12/19/2023 | Approved | ALIZAH MAYAGOITIA |
Footing/Foundation/Slab | 12/19/2023 | Approved | ALIZAH MAYAGOITIA |
Green Building Final | 12/19/2023 | Approved | ALIZAH MAYAGOITIA |
HVAC-Rough | 12/19/2023 | Approved | ALIZAH MAYAGOITIA |
PLUMBING-Rough | 12/19/2023 | Approved | ALIZAH MAYAGOITIA |
SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
Smoke Detectors | 12/19/2023 | Approved | ALIZAH MAYAGOITIA |
Service/Power Release | 1/19/2024 | Approved | BRENDAN MORELLI |
Final | 6/11/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
HVAC-Final | 6/11/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
PLUMBING-Final | 6/11/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Not Ready | JOSEPH MCGARRY |
Gas Test | 6/12/2024 | Approved | JOSEPH MCGARRY |
SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Approved | JOSEPH MCGARRY |
Final | 7/17/2024 | Partial Approval | BRENDAN MORELLI |
HVAC-Final | 7/17/2024 | Approved | BRENDAN MORELLI |
PLUMBING-Final | 7/17/2024 | Approved | BRENDAN MORELLI |
SGSOV-Seismic Gas S/O Valve | 7/17/2024 | SGSOV Approved | BRENDAN MORELLI |
Final | 10/1/2024 | OK to Issue CofO | BRENDAN MORELLI |