229-229 1/2 E 28TH ST 90011

Certificate Information: 229-229 1/2 E 28TH ST 90011

Application / Permit
19010-30000-05608
Plan Check / Job No.
B19WL06908
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-story duplex at front of lot. NFPA-13D fully sprinklered thru-out.
Permit Issued
Issued on 2/21/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 1/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 ALFREDO JARA
Green Plans Picked Up 12/27/2019 APPLICANT
Corrections Issued 12/31/2019 ALFREDO JARA
Quality Review Completed 1/16/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/17/2020 APPLICANT
Plan Check Approved 2/13/2020 ALFREDO JARA
Issued 2/21/2020 LADBS
CofO in Progress 12/15/2020 ROBERT MCDOWELL
Permit Finaled 1/2/2021 DEROLD HAUFF
CofO Issued 1/2/2021 DEROLD HAUFF
Permit Finaled 1/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/21/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 1/21/2020 ANTHONY MAINEZ
Sewer availability Cleared 1/21/2020 ANTHONY MAINEZ
Community Plan Implem. Overlay Cleared 1/22/2020 TERRI OSBORNE
Highway dedication Cleared 1/22/2020 THOMAS LANG
Hydrant and Access approval Cleared 1/22/2020 JEREMY CARTER
Low Impact Development Cleared 1/29/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 1/29/2020 THOMAS LANG
Community Plan Implem. Overlay Cleared 2/10/2020 COLLINS ALLAN
Community Plan Implem. Overlay Cleared 2/10/2020 JOHN KIM
Community Plan Implem. Overlay Cleared 2/10/2020 JUAN ASHTON
Community Plan Implem. Overlay Cleared 2/10/2020 OSCAR CASTRO
Green Code Cleared 2/13/2020 DONALD CRICHLOW

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/6/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 3/6/2020 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 3/23/2020 Not Ready for Inspection ROBERT MCDOWELL
Footing/Foundation/Slab 3/23/2020 Not Ready for Inspection ROBERT MCDOWELL
METHANE-Barrier 3/23/2020 Not Ready for Inspection ROBERT MCDOWELL
METHANE-Subgrade 3/23/2020 Not Ready for Inspection ROBERT MCDOWELL
Underground Mechanical 3/23/2020 Not Ready for Inspection ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 3/25/2020 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/25/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/31/2020 Conditional Approval JOAQUIN GREENOUGH
METHANE-Barrier 3/31/2020 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 3/31/2020 Approved JOAQUIN GREENOUGH
Sewer 3/31/2020 Approved JOAQUIN GREENOUGH
Underground Mechanical 3/31/2020 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/7/2020 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 5/12/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 6/2/2020 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 6/2/2020 Not Ready for Inspection COREY HUPP
Green Building Rough 6/2/2020 Not Ready for Inspection COREY HUPP
METHANE-Rough 6/2/2020 Not Ready for Inspection COREY HUPP
Verify Sprinkler Sign Off 6/2/2020 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Conditional Approval ROBERT MCDOWELL
Deputy Wood Construction 6/25/2020 No Access for Inspection ELMER BLAND
Interior/Exterior Lathing 6/29/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 6/29/2020 Partial Approval COREY HUPP
HVAC-Rough 7/1/2020 Corrections Issued COREY HUPP
Interior/Exterior Lathing 7/1/2020 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 7/6/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/6/2020 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 7/6/2020 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/6/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 7/6/2020 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/7/2020 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 7/7/2020 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 7/7/2020 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 7/7/2020 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Rough 7/7/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 7/7/2020 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 7/7/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 7/9/2020 Approved FREDDIE RIVERA
HVAC-Rough 7/9/2020 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 7/9/2020 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 7/13/2020 Approved ROBERT MCDOWELL
Green Building Rough 7/13/2020 Approved ROBERT MCDOWELL
HVAC-Rough 7/13/2020 Approved ROBERT MCDOWELL
METHANE-Rough 7/13/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 7/13/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 7/13/2020 Approved ROBERT MCDOWELL
Insulation 7/17/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/17/2020 Partial Approval SABAS ALONSO
Shower Pan 7/17/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/30/2020 Partial Approval SABAS ALONSO
Drywall Nailing 8/3/2020 Not Ready for Inspection SABAS ALONSO
Shower Pan 8/3/2020 Approved SABAS ALONSO
Drywall Nailing 8/12/2020 Approved SABAS ALONSO
ELECTRICAL-Final 11/24/2020 Approved ROBERT MCDOWELL
Final 11/24/2020 Corrections Issued ROBERT MCDOWELL
Footing/Foundation/Slab 11/24/2020 Approved ROBERT MCDOWELL
Green Building Final 11/24/2020 Approved ROBERT MCDOWELL
HVAC-Final 11/24/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 11/24/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 11/24/2020 Approved ROBERT MCDOWELL
Smoke Detectors 11/24/2020 Approved ROBERT MCDOWELL
Final 12/15/2020 OK to Issue CofO ROBERT MCDOWELL