3819 S LYCEUM AVE 90066
Certificate Information: 3819 S LYCEUM AVE 90066
- Application / Permit
- 19010-30000-05598
- Plan Check / Job No.
- B19WL06899
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-story SFD with attached 1-car garage with roof trusses.
- Permit Issued
- Issued on 2/6/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Green Plans Picked Up | 1/2/2019 | APPLICANT |
| Submitted | 12/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2019 | JAHANSHAH POURHASSAN |
| Corrections Issued | 1/6/2020 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 1/16/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/17/2020 | APPLICANT |
| Applicant returned to address corrections | 1/31/2020 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 2/6/2020 | JAHANSHAH POURHASSAN |
| Issued | 2/6/2020 | LADBS |
| CofO in Progress | 3/19/2021 | ENRIQUE MIRELES |
| CofO Issued | 4/9/2021 | VINCENT COTTON |
| Permit Finaled | 4/9/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 1/28/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2020 | ERIK BEASLEY |
| Green Code | Cleared | 1/28/2020 | JAHANSHAH POURHASSAN |
| Hydrant and Access approval | Cleared | 1/28/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 1/28/2020 | MITESH PATEL |
| Permit | Cleared | 1/28/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/28/2020 | ERIK BEASLEY |
| Trees in Parkway | Cleared | 1/28/2020 | STEPHEN DUPREY |
| Roof/Waste drainage to street | Cleared | 1/29/2020 | ANTHONY MAINEZ |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/30/2020 | Partial Approval | DAVID FEILER |
| Sewer | 4/30/2020 | Approved | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 5/11/2020 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 5/11/2020 | Corrections Issued | DAVID FEILER |
| Sewer | 5/11/2020 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 5/13/2020 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 5/13/2020 | Approved | DAVID FEILER |
| Deputy Reinf. Concrete | 5/14/2020 | Conditional Approval | DAVID FEILER |
| Sewer | 5/19/2020 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2020 | Partial Approval | DAVID HEINE |
| Deputy Wood Construction | 7/15/2020 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 7/22/2020 | Approved | DAVID HEINE |
| HVAC-Rough | 8/3/2020 | Approved | DAVID HEINE |
| Sewer | 8/5/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 8/27/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 8/31/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 9/8/2020 | Approved | DAVID HEINE |
| Green Building Rough | 9/8/2020 | Approved | DAVID HEINE |
| Verify Sprinkler Sign Off | 9/8/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 9/10/2020 | Approved | DAVID HEINE |
| Insulation | 9/14/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 9/14/2020 | Partial Approval | DAVID HEINE |
| Drywall Nailing | 9/21/2020 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 1/22/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 1/22/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 1/26/2021 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 1/28/2021 | Approved | ENRIQUE MIRELES |
| Final | 3/19/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Green Building Final | 3/19/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/19/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 3/19/2021 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/19/2021 | Approved | ENRIQUE MIRELES |