1431 W 45TH ST 90062

Certificate Information: 1431 W 45TH ST 90062

Application / Permit
19010-30000-05557
Plan Check / Job No.
B19WL06841
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ADU per AB494 and SB229.
Permit Issued
Issued on 2/18/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 MANUEL GARCIA
Corrections Issued 12/24/2019 MANUEL GARCIA
Green Plans Picked Up 12/27/2019 APPLICANT
Quality Review Completed 1/9/2020 MARJAN SHENASI
Building Plans Picked Up 1/10/2020 APPLICANT
Plan Check Approved 2/4/2020 MANUEL GARCIA
Issued 2/18/2020 LADBS
CofO in Progress 1/25/2021 ROBERT MCDOWELL
Permit Finaled 2/18/2021 DEROLD HAUFF
CofO Issued 2/18/2021 DEROLD HAUFF
Permit Finaled 2/18/2021 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 1/14/2020 SOPHIE GABEL-SCHEINBAU
ZI Cleared 1/14/2020 SOPHIE GABEL-SCHEINBAU
Low Impact Development Cleared 1/23/2020 ORVAL HERNANDEZ-MARCI
Hydrant and Access approval Cleared 1/24/2020 JOHN CONNEALLY
Address approval Cleared 1/29/2020 TRACY TATE
Roof/Waste drainage to street Cleared 1/29/2020 TRACY TATE
Sewer availability Cleared 1/29/2020 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 2/4/2020 ANTHONY MAINEZ
Green Code Cleared 2/4/2020 MANUEL GARCIA

Contact Information

Contractor Elite Construction; Lic. No.: 927909-B 412 S 5TH STREET      ALHAMBRA, CA 91801

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/9/2020 Partial Approval ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 3/18/2020 Corrections Issued ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 3/24/2020 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 3/24/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Approved ROBERT MCDOWELL
Green Building Rough 5/1/2020 Not Ready for Inspection ROBERT MCDOWELL
Verify Sprinkler Sign Off 5/1/2020 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 5/8/2020 Not Ready for Inspection ROBERT MCDOWELL
Green Building Rough 5/8/2020 Not Ready for Inspection ROBERT MCDOWELL
Verify Sprinkler Sign Off 5/8/2020 Not Ready for Inspection ROBERT MCDOWELL
Interior/Exterior Lathing 5/13/2020 Approved ROBERT MCDOWELL
Wood Frame 5/13/2020 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 5/19/2020 Conditional Approval ROBERT MCDOWELL
ELECTRICAL-Rough 5/19/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 5/19/2020 Approved ROBERT MCDOWELL
Sewer 5/19/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 5/21/2020 Conditional Approval SABAS ALONSO
Green Building Rough 5/21/2020 Approved SABAS ALONSO
Insulation 5/21/2020 Approved SABAS ALONSO
Drywall Nailing 5/27/2020 Approved SABAS ALONSO
Service/Power Release 6/23/2020 Corrections Issued ROBERT MCDOWELL
BUILDING-Rough-Frame 7/1/2020 Conditional Approval ROBERT MCDOWELL
ELECTRICAL-Final 7/1/2020 Approved ROBERT MCDOWELL
Final 7/1/2020 Corrections Issued ROBERT MCDOWELL
Green Building Final 7/1/2020 Approved ROBERT MCDOWELL
HVAC-Final 7/1/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 7/1/2020 SGSOV Not Ready ROBERT MCDOWELL
Service/Power Release 7/1/2020 Approved ROBERT MCDOWELL
Smoke Detectors 7/1/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 7/1/2020 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 7/16/2020 Not Ready for Inspection ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 7/16/2020 SGSOV Not Ready ROBERT MCDOWELL
Verify Sprinkler Sign Off 7/16/2020 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 8/28/2020 Conditional Approval ROBERT MCDOWELL
Final 8/28/2020 Order to Comply Issued ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 8/28/2020 SGSOV Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 8/28/2020 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 9/8/2020 Approved ROBERT MCDOWELL
Final 9/8/2020 Not Ready for Inspection ROBERT MCDOWELL
Verify Sprinkler Sign Off 9/8/2020 Approved ROBERT MCDOWELL
Final 9/14/2020 Not Ready for Inspection DAVID FEILER
Final 1/25/2021 OK to Issue CofO ROBERT MCDOWELL