1431 W 45TH ST 90062
Certificate Information: 1431 W 45TH ST 90062
- Application / Permit
- 19010-30000-05557
- Plan Check / Job No.
- B19WL06841
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New ADU per AB494 and SB229.
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | MANUEL GARCIA |
| Corrections Issued | 12/24/2019 | MANUEL GARCIA |
| Green Plans Picked Up | 12/27/2019 | APPLICANT |
| Quality Review Completed | 1/9/2020 | MARJAN SHENASI |
| Building Plans Picked Up | 1/10/2020 | APPLICANT |
| Plan Check Approved | 2/4/2020 | MANUEL GARCIA |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 1/25/2021 | ROBERT MCDOWELL |
| Permit Finaled | 2/18/2021 | DEROLD HAUFF |
| CofO Issued | 2/18/2021 | DEROLD HAUFF |
| Permit Finaled | 2/18/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 1/14/2020 | SOPHIE GABEL-SCHEINBAU |
| ZI | Cleared | 1/14/2020 | SOPHIE GABEL-SCHEINBAU |
| Low Impact Development | Cleared | 1/23/2020 | ORVAL HERNANDEZ-MARCI |
| Hydrant and Access approval | Cleared | 1/24/2020 | JOHN CONNEALLY |
| Address approval | Cleared | 1/29/2020 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 1/29/2020 | TRACY TATE |
| Sewer availability | Cleared | 1/29/2020 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2020 | ANTHONY MAINEZ |
| Green Code | Cleared | 2/4/2020 | MANUEL GARCIA |
Contact Information
| Contractor | Elite Construction; Lic. No.: 927909-B | 412 S 5TH STREET ALHAMBRA, CA 91801 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/9/2020 | Partial Approval | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 3/18/2020 | Corrections Issued | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 3/24/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 3/24/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 5/1/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/1/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/8/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Green Building Rough | 5/8/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/8/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 5/13/2020 | Approved | ROBERT MCDOWELL |
| Wood Frame | 5/13/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/19/2020 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/19/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/19/2020 | Approved | ROBERT MCDOWELL |
| Sewer | 5/19/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/21/2020 | Conditional Approval | SABAS ALONSO |
| Green Building Rough | 5/21/2020 | Approved | SABAS ALONSO |
| Insulation | 5/21/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/27/2020 | Approved | SABAS ALONSO |
| Service/Power Release | 6/23/2020 | Corrections Issued | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/1/2020 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Final | 7/1/2020 | Approved | ROBERT MCDOWELL |
| Final | 7/1/2020 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 7/1/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 7/1/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 7/1/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Service/Power Release | 7/1/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 7/1/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 7/1/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/16/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 7/16/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 7/16/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 8/28/2020 | Conditional Approval | ROBERT MCDOWELL |
| Final | 8/28/2020 | Order to Comply Issued | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 8/28/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 8/28/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 9/8/2020 | Approved | ROBERT MCDOWELL |
| Final | 9/8/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 9/8/2020 | Approved | ROBERT MCDOWELL |
| Final | 9/14/2020 | Not Ready for Inspection | DAVID FEILER |
| Final | 1/25/2021 | OK to Issue CofO | ROBERT MCDOWELL |