830 N FISKE ST 90272

Certificate Information: 830 N FISKE ST 90272

Application / Permit
19010-30000-05555
Plan Check / Job No.
B19WL06835
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story additio to existing SFD with attached garage with roof trusses.
Permit Issued
Issued on 1/22/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2019 APPLICANT
Green Plans Picked Up 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 KAVIAN REFAHI
Corrections Issued 12/30/2019 KAVIAN REFAHI
Quality Review Completed 1/13/2020 FELIX FIGUEROA
Building Plans Picked Up 1/13/2020 APPLICANT
Plan Check Approved 1/22/2020 KAVIAN REFAHI
Issued 1/22/2020 LADBS
CofO in Progress 1/4/2021 ANDREW NAVE
Permit Finaled 1/5/2021 VINCENT COTTON
CofO Issued 1/5/2021 VINCENT COTTON
Permit Finaled 1/5/2021 VINCENT COTTON

Permit Application Clearance Information

GPI Written Notices Cleared 12/24/2019 KAVIAN REFAHI
Grading Pre-Inspection Cleared 12/24/2019 KAVIAN REFAHI
Green Code Cleared 1/16/2020 DONALD CRICHLOW
Eng Process Fee Ord 176,300 Cleared 1/21/2020 CELINA MORENO
Low Impact Development Cleared 1/21/2020 MARTIN FRAGOSO
Permit Cleared 1/21/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 1/21/2020 CELINA MORENO
Sewer availability Cleared 1/21/2020 CELINA MORENO
Trees in Parkway Cleared 1/21/2020 STEPHEN DUPREY

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/1/2020 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 4/21/2020 Approved DANNY TOLENTINO
Footing/Foundation/Slab 4/21/2020 Approved DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Partial Approval DANNY TOLENTINO
Deputy Wood Construction 5/22/2020 Corrections Issued ROBERT SHELLY
Deputy Wood Construction 5/26/2020 No Access for Inspection DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Approved ANDREW NAVE
ELECTRICAL-Rough 6/15/2020 Approved ANDREW NAVE
HVAC-Rough 6/17/2020 Approved JOHN KIDWELL
HVAC-Rough 6/24/2020 No Access for Inspection ROBERT SHELLY
PLUMBING-Rough 6/26/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 7/8/2020 Approved JOHN KIDWELL
Shower Pan 7/8/2020 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 7/15/2020 Partial Approval ROBERT SHELLY
Shower Pan 7/17/2020 No Access for Inspection JOHN KIDWELL
Wood Frame 7/17/2020 No Access for Inspection JOHN KIDWELL
Shower Pan 7/21/2020 Approved ROBERT SHELLY
Wood Frame 7/21/2020 Corrections Issued ROBERT SHELLY
BUILDING-Rough-Frame 7/23/2020 Corrections Issued ROBERT SHELLY
Green Building Rough 7/23/2020 Not Ready for Inspection ROBERT SHELLY
BUILDING-Rough-Frame 7/27/2020 Not Ready for Inspection ROBERT SHELLY
Green Building Rough 7/27/2020 Approved ROBERT SHELLY
Insulation 7/28/2020 Approved ROBERT SHELLY
Drywall Nailing 8/4/2020 Approved ROBERT SHELLY
Interior/Exterior Lathing 8/13/2020 Not Ready for Inspection ROBERT SHELLY
Interior/Exterior Lathing 8/20/2020 Partial Approval ROBERT SHELLY
ELECTRICAL-Final 11/4/2020 Not Ready for Inspection JOHN KIDWELL
Gas Test 11/6/2020 No Access for Inspection JOHN KIDWELL
PLUMBING-Final 11/6/2020 No Access for Inspection JOHN KIDWELL
Gas Test 11/9/2020 No Access for Inspection JOHN KIDWELL
PLUMBING-Final 11/9/2020 No Access for Inspection JOHN KIDWELL
Gas Test 11/12/2020 Approved JOHN KIDWELL
PLUMBING-Final 11/12/2020 Approved JOHN KIDWELL
ELECTRICAL-Final 11/16/2020 Approved JOHN KIDWELL
HVAC-Final 11/20/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 11/24/2020 Approved JOHN KIDWELL
BUILDING-Rough-Frame 1/4/2021 Approved ANDREW NAVE
Final 1/4/2021 OK to Issue CofO ANDREW NAVE
Green Building Final 1/4/2021 Approved ANDREW NAVE
Green Building Rough 1/4/2021 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 1/4/2021 SGSOV Approved ANDREW NAVE
Service/Power Release 1/4/2021 Approved ANDREW NAVE
Smoke Detectors 1/4/2021 Approved ANDREW NAVE