865 E ROSE AVE 90291
Certificate Information: 865 E ROSE AVE 90291
- Application / Permit
- 19010-30000-05530
- Plan Check / Job No.
- B19WL06813
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE
- Permit Issued
- Issued on 1/21/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | REZA HAGHIGHAT |
| Green Plans Picked Up | 12/20/2019 | APPLICANT |
| Corrections Issued | 12/23/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 1/10/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/10/2020 | APPLICANT |
| Plan Check Approved | 1/21/2020 | REZA HAGHIGHAT |
| Issued | 1/21/2020 | LADBS |
| CofO in Progress | 12/16/2020 | DAVID HEINE |
| CofO Issued | 1/12/2021 | VINCENT COTTON |
| Permit Finaled | 1/12/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 1/14/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 1/14/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Green Code | Cleared | 1/16/2020 | DONALD CRICHLOW |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/22/2020 | Partial Approval | DAVID HEINE |
| Sewer | 4/22/2020 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 4/30/2020 | Corrections Issued | DAVID HEINE |
| Footing/Foundation/Slab | 4/30/2020 | Corrections Issued | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 5/4/2020 | Approved | DAVID HEINE |
| Footing/Foundation/Slab | 5/4/2020 | Approved | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2020 | Partial Inspection | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2020 | Partial Approval | DAVID HEINE |
| Deputy Wood Construction | 7/14/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2020 | Corrections Issued | DAVID HEINE |
| ELECTRICAL-Rough | 7/23/2020 | Corrections Issued | DAVID HEINE |
| Interior/Exterior Lathing | 7/23/2020 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 7/28/2020 | Approved | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 7/28/2020 | Approved | DAVID HEINE |
| HVAC-Rough | 7/29/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 7/30/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 8/3/2020 | Approved | DAVID HEINE |
| Green Building Rough | 8/3/2020 | Approved | DAVID HEINE |
| Verify Sprinkler Sign Off | 8/3/2020 | Approved | DAVID HEINE |
| Insulation | 8/11/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 8/19/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 8/20/2020 | Approved | DAVID HEINE |
| Insulation | 8/20/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 10/15/2020 | Approved | DAVID HEINE |
| PLUMBING-Final | 10/15/2020 | Approved | DAVID HEINE |
| Service/Power Release | 10/15/2020 | Not Ready for Inspection | DAVID HEINE |
| PLUMBING-Final | 11/4/2020 | Approved | DAVID HEINE |
| Final | 11/12/2020 | Conditional Approval | DAVID HEINE |
| Green Building Final | 11/12/2020 | Approved | DAVID HEINE |
| HVAC-Final | 11/12/2020 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 11/12/2020 | SGSOV Approved | DAVID HEINE |
| Service/Power Release | 11/12/2020 | Not Ready for Inspection | DAVID HEINE |
| Smoke Detectors | 11/12/2020 | Approved | DAVID HEINE |
| Final | 11/17/2020 | Corrections Issued | JUAN VALENZUELA |
| Service/Power Release | 11/17/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Rec and Parks Fee Memo | 11/17/2020 | Partial Inspection | JUAN VALENZUELA |
| Final | 12/16/2020 | OK to Issue CofO | DAVID HEINE |
| Service/Power Release | 12/16/2020 | Approved | DAVID HEINE |