865 E ROSE AVE 90291

Certificate Information: 865 E ROSE AVE 90291

Application / Permit
19010-30000-05530
Plan Check / Job No.
B19WL06813
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE
Permit Issued
Issued on 1/21/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 REZA HAGHIGHAT
Green Plans Picked Up 12/20/2019 APPLICANT
Corrections Issued 12/23/2019 REZA HAGHIGHAT
Quality Review Completed 1/10/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/10/2020 APPLICANT
Plan Check Approved 1/21/2020 REZA HAGHIGHAT
Issued 1/21/2020 LADBS
CofO in Progress 12/16/2020 DAVID HEINE
CofO Issued 1/12/2021 VINCENT COTTON
Permit Finaled 1/12/2021 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/14/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 1/14/2020 GEORGE SUCHAND
Low Impact Development Cleared 1/14/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/14/2020 LEE GUILBEAUX
Sewer availability Cleared 1/14/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/14/2020 LEE GUILBEAUX
Green Code Cleared 1/16/2020 DONALD CRICHLOW

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/22/2020 Partial Approval DAVID HEINE
Sewer 4/22/2020 Partial Approval DAVID HEINE
Excavation/Setback/Form/Re-Bar 4/30/2020 Corrections Issued DAVID HEINE
Footing/Foundation/Slab 4/30/2020 Corrections Issued DAVID HEINE
Excavation/Setback/Form/Re-Bar 5/4/2020 Approved DAVID HEINE
Footing/Foundation/Slab 5/4/2020 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 5/28/2020 Partial Inspection DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Partial Approval DAVID HEINE
Deputy Wood Construction 7/14/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 7/14/2020 Corrections Issued DAVID HEINE
ELECTRICAL-Rough 7/23/2020 Corrections Issued DAVID HEINE
Interior/Exterior Lathing 7/23/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 7/28/2020 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 7/28/2020 Approved DAVID HEINE
PLUMBING-Rough 7/28/2020 Approved DAVID HEINE
HVAC-Rough 7/29/2020 Approved DAVID HEINE
Interior/Exterior Lathing 7/30/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 8/3/2020 Approved DAVID HEINE
Green Building Rough 8/3/2020 Approved DAVID HEINE
Verify Sprinkler Sign Off 8/3/2020 Approved DAVID HEINE
Insulation 8/11/2020 Approved DAVID HEINE
Interior/Exterior Lathing 8/19/2020 Approved DAVID HEINE
Drywall Nailing 8/20/2020 Approved DAVID HEINE
Insulation 8/20/2020 Approved DAVID HEINE
ELECTRICAL-Final 10/15/2020 Approved DAVID HEINE
PLUMBING-Final 10/15/2020 Approved DAVID HEINE
Service/Power Release 10/15/2020 Not Ready for Inspection DAVID HEINE
PLUMBING-Final 11/4/2020 Approved DAVID HEINE
Final 11/12/2020 Conditional Approval DAVID HEINE
Green Building Final 11/12/2020 Approved DAVID HEINE
HVAC-Final 11/12/2020 Approved DAVID HEINE
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Approved DAVID HEINE
Service/Power Release 11/12/2020 Not Ready for Inspection DAVID HEINE
Smoke Detectors 11/12/2020 Approved DAVID HEINE
Final 11/17/2020 Corrections Issued JUAN VALENZUELA
Service/Power Release 11/17/2020 Not Ready for Inspection JUAN VALENZUELA
Verify Rec and Parks Fee Memo 11/17/2020 Partial Inspection JUAN VALENZUELA
Final 12/16/2020 OK to Issue CofO DAVID HEINE
Service/Power Release 12/16/2020 Approved DAVID HEINE