333 N TIGERTAIL ROAD 90049

Certificate Information: 333 N TIGERTAIL ROAD 90049

Application / Permit
19010-30000-05339
Plan Check / Job No.
B19WL06647
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
(n) detached covered porch.
Permit Issued
Issued on 1/23/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 12/10/2019 VLADIMIR ARUTYUNYAN
Green Plans Picked Up 12/10/2019 APPLICANT
Quality Review Completed 12/20/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/17/2020 JAHANSHAH POURHASSAN
Plan Check Approved 1/23/2020 VLADIMIR ARUTYUNYAN
Issued 1/23/2020 LADBS
Building Plans Picked Up 12/15/2020 APPLICANT
CofO in Progress 6/24/2022 JUAN VALENZUELA
Permit Finaled 6/29/2022 DANIEL ORRANTE
CofO Issued 6/29/2022 DANIEL ORRANTE
Permit Finaled 6/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/14/2020 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 1/14/2020 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 1/14/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/14/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 1/14/2020 GEORGE SUCHAND
Low Impact Development Cleared 1/14/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/14/2020 LEE GUILBEAUX
Sewer availability Cleared 1/14/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/14/2020 LEE GUILBEAUX
Green Code Cleared 1/16/2020 RICHARD GARCIA

Contact Information

Contractor Pillar Building Group Llc; Lic. No.: 1017041-B 8109 ORION AVE      VAN NUYS, CA 91406
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/8/2021 Approved JUAN VALENZUELA
Footing/Foundation/Slab 4/8/2021 Approved JUAN VALENZUELA
ELECTRICAL-Rough 5/6/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Approved JUAN VALENZUELA
Special/Order Compliance 6/18/2021 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 8/3/2021 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 3/15/2022 Approved JOHN KIDWELL
Green Building Final 3/15/2022 Approved JOHN KIDWELL
Green Building Rough 3/15/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 3/15/2022 SGSOV Approved JOHN KIDWELL
Service/Power Release 3/15/2022 Approved JOHN KIDWELL
Smoke Detectors 3/15/2022 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 3/15/2022 Approved JOHN KIDWELL
Final 4/26/2022 No Access for Inspection JUAN VALENZUELA
Final 5/24/2022 Corrections Issued JOHN KIDWELL
ELECTRICAL-Final 6/2/2022 Approved JUAN VALENZUELA
Final 6/2/2022 Corrections Issued JUAN VALENZUELA
HVAC-Final 6/2/2022 Approved JUAN VALENZUELA
PLUMBING-Final 6/2/2022 Approved JUAN VALENZUELA
Final 6/24/2022 OK to Issue CofO JUAN VALENZUELA