333 N TIGERTAIL ROAD 90049
Certificate Information: 333 N TIGERTAIL ROAD 90049
- Application / Permit
- 19010-30000-05338
- Plan Check / Job No.
- B19WL06647
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-story SFD with basement and attached garage.
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 12/10/2019 | VLADIMIR ARUTYUNYAN |
| Green Plans Picked Up | 12/10/2019 | APPLICANT |
| Quality Review Completed | 12/20/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/17/2020 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 1/23/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 1/23/2020 | LADBS |
| Building Plans Picked Up | 12/15/2020 | APPLICANT |
| CofO in Progress | 6/3/2022 | JUAN VALENZUELA |
| Permit Finaled | 6/29/2022 | DANIEL ORRANTE |
| CofO Issued | 6/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/14/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 1/14/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 1/14/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 1/14/2020 | SARAH YOUSSEF |
| Permit | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Green Code | Cleared | 1/16/2020 | RICHARD GARCIA |
| Trees in Parkway | Cleared | 1/21/2020 | STEPHEN DUPREY |
Contact Information
| Contractor | Pillar Building Group Llc; Lic. No.: 1017041-B | 8109 ORION AVE VAN NUYS, CA 91406 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 5/19/2020 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/19/2020 | Partial Inspection | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 5/20/2020 | Partial Inspection | TIM CHRISTENSEN |
| Underground Mechanical | 5/20/2020 | Partial Inspection | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 6/10/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Shotcrete | 6/22/2020 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/23/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Shotcrete | 6/24/2020 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/9/2020 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Wood Frame | 8/3/2020 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2020 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/31/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 8/31/2020 | Partial Approval | TIM CHRISTENSEN |
| Sewer | 8/31/2020 | Partial Inspection | TIM CHRISTENSEN |
| Deputy Wood Construction | 9/4/2020 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/14/2020 | Partial Approval | TIM CHRISTENSEN |
| Sewer | 9/23/2020 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2020 | Partial Approval | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 11/9/2020 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/9/2020 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2020 | Conditional Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/7/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/7/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Sewer | 1/7/2021 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 1/7/2021 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 1/14/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 1/14/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Shower Pan | 1/14/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 1/22/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Rough | 1/22/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 1/22/2021 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 1/22/2021 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 1/22/2021 | Approved | JUAN VALENZUELA |
| Wood Frame | 1/22/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 1/25/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 1/25/2021 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 1/25/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 1/25/2021 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/1/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2021 | Conditional Approval | JUAN VALENZUELA |
| Insulation | 2/1/2021 | Approved | JUAN VALENZUELA |
| Wood Frame | 2/1/2021 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 2/9/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 2/9/2021 | Approved | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/6/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/6/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Sewer | 6/15/2021 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 7/22/2021 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Final | 3/7/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 3/8/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 3/10/2022 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Final | 3/11/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 3/14/2022 | Approved | JUAN VALENZUELA |
| Service/Power Release | 3/14/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 3/15/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 4/26/2022 | No Access for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/26/2022 | No Access for Inspection | JUAN VALENZUELA |
| Green Building Final | 4/26/2022 | No Access for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 4/26/2022 | SGSOV Not Ready | JUAN VALENZUELA |
| Service/Power Release | 4/26/2022 | No Access for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 4/26/2022 | No Access for Inspection | JUAN VALENZUELA |
| Final | 5/24/2022 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/24/2022 | Approved | JOHN KIDWELL |
| Green Building Final | 5/24/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 5/24/2022 | Approved | JOHN KIDWELL |
| Smoke Detectors | 5/24/2022 | Approved | JOHN KIDWELL |
| Final | 5/26/2022 | Corrections Issued | CARLOS MATAMOROS |
| Final | 6/2/2022 | OK to Issue CofO | JUAN VALENZUELA |
| HVAC-Final | 6/2/2022 | Approved | JUAN VALENZUELA |