12610 1/2 W VENICE BLVD 90066
Certificate Information: 12610 1/2 W VENICE BLVD 90066
- Application / Permit
- 19010-30000-05127
- Plan Check / Job No.
- B19WL06395
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New four story single family dwelling with attached garage per VTT-82822-SL. (Lot #9)
- Permit Issued
- Issued on 8/26/2021
- Issuing Office
- Current Status
- CofO Issued on 7/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 12/3/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 12/17/2019 | FELIX FIGUEROA |
| Applicant returned to address corrections | 1/16/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/2/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/21/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/30/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/2/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/29/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 11/20/2020 | APPLICANT |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| Applicant returned to address corrections | 3/4/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/18/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 6/6/2021 | KAMRAN GHOTBI RAVANDI |
| Issued | 8/26/2021 | APPLICANT |
| CofO in Progress | 7/18/2024 | RICHARD STEINBACH |
| Permit Finaled | 7/20/2024 | DANIEL ORRANTE |
| CofO Issued | 7/20/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/20/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/22/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2020 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 7/6/2020 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 8/5/2020 | JOE LUCKEY |
| Tract Map conditions | Cleared | 8/5/2020 | JOE LUCKEY |
| Highway dedication | Cleared | 8/17/2020 | RAYMOND MUGAMBWA |
| Address approval | Cleared | 8/19/2020 | RAYMOND MUGAMBWA |
| Permit | Cleared | 8/19/2020 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 9/15/2020 | ORVAL HERNANDEZ-MARCI |
| Miscellaneous | Cleared | 9/21/2020 | MAHELET GEBEYHU |
| Trees in Parkway | Cleared | 9/22/2020 | JOHN KIM |
| Roof/Waste drainage to street | Cleared | 9/30/2020 | DINAH GARIN |
| Specific Plan | Cleared | 10/12/2020 | PEDRO AYALA |
| Green Code | Cleared | 11/16/2020 | KAMRAN GHOTBI RAVANDI |
| Building over 3-story or 36-ft | Cleared | 6/6/2021 | CALOSHA APPROVED |
Contact Information
| Architect | Holtz,, Donald Lee; Lic. No.: C21677 | 2404 WILSHIRE BLVD SUITE 6F LOS ANGELES, CA 90057 |
| Contractor | Sun Developers Inc; Lic. No.: 865631-B | 23371 MULHOLLAND DRIVE #295 WOODLAND HILLS, CA 91364 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/5/2022 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 5/9/2022 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 5/25/2022 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 6/6/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/13/2022 | Approved | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 7/6/2022 | No Access for Inspection | DAVID FEILER |
| Deputy Wood Construction | 8/2/2022 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Partial Approval | RICHARD STEINBACH |
| Drywall Nailing | 8/8/2022 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 9/15/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Partial Approval | DAVID FEILER |
| Deputy Wood Construction | 10/11/2022 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | RICHARD STEINBACH |
| Drywall Nailing | 10/20/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 12/23/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 5/9/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/26/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 7/27/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/1/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/25/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/25/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 9/12/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 9/12/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 9/12/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/22/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/22/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/16/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 2/16/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 2/27/2024 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 2/27/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 3/1/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 5/8/2024 | Approved | JESUS RODRIGUEZ |
| Final | 7/17/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 7/17/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/17/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 7/17/2024 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 7/17/2024 | Approved | JESUS RODRIGUEZ |