937 S MUIRFIELD ROAD 90019

Certificate Information: 937 S MUIRFIELD ROAD 90019

Application / Permit
19010-30000-05030
Plan Check / Job No.
B19WL06298
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1-story Accessory Dwelling Unit (ADU) addition to rear side of (e) det. 2-car garage per AB 494 & SB 229. All work per IB/P/BC 2017-004 wood frame prescriptive provision.
Permit Issued
Issued on 12/2/2020
Issuing Office
Current Status
CofO Issued on 2/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 REZA HAGHIGHAT
Corrections Issued 11/14/2019 REZA HAGHIGHAT
Applicant returned to address corrections 6/24/2020 JASON JANGADA
Plan Check Approved 9/23/2020 PARISA ZAHABI
Issued 12/2/2020 APPLICANT
Building Plans Picked Up 12/7/2020 APPLICANT
CofO in Progress 1/13/2022 CHRIS CHRISTENSEN
Permit Finaled 2/2/2022 DEROLD HAUFF
CofO Issued 2/2/2022 DEROLD HAUFF
Permit Finaled 2/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/15/2019 MAHELET GEBEYHU
Hydrant and Access approval Cleared 11/18/2019 JOHN CONNEALLY
Construction near power lines Cleared 1/17/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 7/9/2020 PAMELA TENEZA
Sewer availability Cleared 7/9/2020 PAMELA TENEZA
Low Impact Development Cleared 9/10/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/15/2020 RENZ SORIANO

Contact Information

Architect Yoo,, Jenny I; Lic. No.: C37196 939 S. MUIRFIELD RD      LOS ANGELES, CA 90019
Contractor Alpha Infinity Construction Inc; Lic. No.: 971307-B 961 S CATALINA ST #2      LOS ANGELES, CA 90006

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/23/2020 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 12/23/2020 Conditional Approval CHRIS CHRISTENSEN
METHANE-Barrier 12/23/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 12/23/2020 Approved CHRIS CHRISTENSEN
Wood Frame 12/31/2020 Partial Approval CHRIS CHRISTENSEN
Insulation 1/5/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 1/5/2021 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/9/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 2/9/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Partial Approval JOSEPH MCGARRY
Green Building Rough 2/9/2021 Approved JOSEPH MCGARRY
HVAC-Rough 2/9/2021 Conditional Approval JOSEPH MCGARRY
METHANE-Rough 2/9/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 2/9/2021 Approved JOSEPH MCGARRY
Wood Frame 2/9/2021 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 2/18/2021 Approved CHRIS CHRISTENSEN
Wood Frame 2/18/2021 Approved CHRIS CHRISTENSEN
Insulation 2/26/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 3/8/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 3/8/2021 Approved STUART CHAPMAN
Shower Pan 3/8/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 7/7/2021 Approved CHARLES BOGHOSKHAN
Excavation/Setback/Form/Re-Bar 7/7/2021 Approved CHARLES BOGHOSKHAN
PLUMBING-Rough 7/7/2021 Approved CHARLES BOGHOSKHAN
Footing/Foundation/Slab 7/9/2021 Partial Approval CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 7/9/2021 Approved CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 7/23/2021 Partial Approval JOSEPH MCGARRY
Gas Test 8/18/2021 Corrections Issued ARTHUR SARGSYAN
PLUMBING-Rough 8/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
Gas Test 8/20/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 8/20/2021 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Final 9/14/2021 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 9/14/2021 Not Ready for Inspection ARTHUR SARGSYAN
Gas Test 9/14/2021 Approved ARTHUR SARGSYAN
PLUMBING-Final 10/7/2021 Approved ARTHUR SARGSYAN
PLUMBING-Final 10/26/2021 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Final 12/8/2021 Approved CHRIS CHRISTENSEN
Final 12/8/2021 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 12/8/2021 Approved CHRIS CHRISTENSEN
Green Building Final 12/8/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 12/8/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 12/8/2021 Approved CHRIS CHRISTENSEN
Final 12/17/2021 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 12/17/2021 Approved CHRIS CHRISTENSEN