3667 S KELTON AVE 90034

Certificate Information: 3667 S KELTON AVE 90034

Application / Permit
19010-30000-05025
Plan Check / Job No.
B19WL06295
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY TYPE VB ACCESSORY DWELLING UNIT WITH ATTACHED 1-CAR GARAGE, PER ORDINANCE.
Permit Issued
Issued on 12/21/2020
Issuing Office
Current Status
CofO Issued on 11/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 SERGIO SILVA
Corrections Issued 12/11/2019 SERGIO SILVA
Quality Review Completed 12/17/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 12/30/2019 APPLICANT
Applicant returned to address corrections 8/17/2020 SERGIO SILVA
Plan Check Approved 10/13/2020 SERGIO SILVA
Issued 12/21/2020 APPLICANT
Building Plans Picked Up 12/22/2020 APPLICANT
CofO in Progress 10/28/2021 JOHNNY MIRANDA
Permit Finaled 11/3/2021 KENNETH NAGLE
CofO Issued 11/3/2021 KENNETH NAGLE
Permit Finaled 11/3/2021 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/6/2020 DINAH GARIN
Permit Cleared 3/6/2020 DINAH GARIN
Construction near power lines Cleared 6/10/2020 RIDWAN HARDY
Green Code Cleared 6/10/2020 RICHARD GARCIA
Address approval Cleared 6/16/2020 ANTHONY MAINEZ
Sewer availability Cleared 6/30/2020 ANTHONY MAINEZ
Hydrant and Access approval Cleared 7/8/2020 MATTHEW CRAIG
GPI Written Notices Cleared 8/5/2020 SERGIO SILVA
Grading Pre-Inspection Cleared 8/5/2020 SERGIO SILVA
Low Impact Development Cleared 8/5/2020 SARAH YOUSSEF
Miscellaneous Cleared 10/13/2020 SERGIO SILVA
Roof/Waste drainage to street Cleared 11/25/2020 ANTHONY MAINEZ

Contact Information

Contractor K N Engineering & Construction Company; Lic. No.: 599652-B P O BOX 3784      CHATSWORTH, CA 91323

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/19/2021 Partial Approval RICHARD ROBLES
Footing/Foundation/Slab 2/24/2021 Corrections Issued RICHARD ROBLES
Footing/Foundation/Slab 5/5/2021 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 5/14/2021 No Access for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 5/17/2021 Partial Approval EVAN COOPER
Green Building Rough 5/17/2021 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 5/17/2021 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 5/21/2021 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 6/14/2021 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/14/2021 Corrections Issued EVAN COOPER
HVAC-Rough 6/14/2021 Corrections Issued EVAN COOPER
PLUMBING-Rough 6/14/2021 Approved EVAN COOPER
Special/Order Compliance 6/14/2021 Corrections Issued EVAN COOPER
Insulation 6/23/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/23/2021 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 7/1/2021 Approved EVAN COOPER
Green Building Rough 7/1/2021 Approved EVAN COOPER
Interior/Exterior Lathing 7/1/2021 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 7/14/2021 Partial Approval OGANES TARAKHCHYAN
Gas Test 8/16/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/25/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 8/25/2021 Corrections Issued JUAN VALENZUELA
Final 8/25/2021 Corrections Issued JUAN VALENZUELA
Green Building Final 8/25/2021 Corrections Issued JUAN VALENZUELA
HVAC-Final 8/25/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Final 8/25/2021 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 8/25/2021 SGSOV Approved JUAN VALENZUELA
Service/Power Release 8/25/2021 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 8/25/2021 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 8/25/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 10/18/2021 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Final 10/18/2021 Approved JOHNNY MIRANDA
Final 10/18/2021 Corrections Issued JOHNNY MIRANDA
Green Building Final 10/18/2021 Approved JOHNNY MIRANDA
HVAC-Final 10/18/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 10/18/2021 Approved JOHNNY MIRANDA
Service/Power Release 10/18/2021 Approved JOHNNY MIRANDA
Verify Sprinkler Sign Off 10/18/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 10/21/2021 Approved JOHNNY MIRANDA
Final 10/21/2021 OK to Issue CofO JOHNNY MIRANDA