4406 N FULTON AVE 91423

Certificate Information: 4406 N FULTON AVE 91423

Application / Permit
19010-30000-05024
Plan Check / Job No.
B19WL06287
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 4-story 25 units apartment building (Type V-A ) over 1-level of subterranean parking (Type I-A) utilizing a 35% density bonus with 2 very low income units with two incentives (FAR & Height).
Permit Issued
Issued on 10/8/2021
Issuing Office
Current Status
CofO Issued on 8/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 MARJAN SHENASI
Corrections Issued 12/26/2019 MARJAN SHENASI
Disabled Access Plans Picked Up 12/26/2019 APPLICANT
Quality Review Completed 1/10/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/22/2020 MARJAN SHENASI
Applicant returned to address corrections 9/1/2020 MARJAN SHENASI
Green Plans Picked Up 9/1/2020 APPLICANT
Applicant returned to address corrections 9/28/2020 MARJAN SHENASI
Applicant returned to address corrections 11/5/2020 MARJAN SHENASI
Building Plans Picked Up 12/17/2020 APPLICANT
Applicant returned to address corrections 2/16/2021 MARJAN SHENASI
Applicant returned to address corrections 2/23/2021 MARJAN SHENASI
Applicant returned to address corrections 3/10/2021 MARJAN SHENASI
Applicant returned to address corrections 6/18/2021 MARJAN SHENASI
Applicant returned to address corrections 9/7/2021 MARJAN SHENASI
Applicant returned to address corrections 9/20/2021 MARJAN SHENASI
Applicant returned to address corrections 10/4/2021 MARJAN SHENASI
Plan Check Approved 10/4/2021 MARJAN SHENASI
Issued 10/8/2021 APPLICANT
CofO in Progress 8/16/2024 JOHN KITCKO
Permit Finaled 8/23/2024 RICKEY JACKSON
CofO Issued 8/23/2024 RICKEY JACKSON
Permit Finaled 8/23/2024 RICKEY JACKSON

Permit Application Clearance Information

Construction near power lines Cleared 5/22/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 5/28/2020 JOHN LIN
Sewer availability Cleared 5/28/2020 JOHN LIN
Address approval Cleared 6/3/2020 HOWARD COOPER
Trees in Parkway Cleared 6/4/2020 JOHN KIM
Highway dedication Cleared 9/14/2020 JOHN LIN
Building over 3-story or 36-ft Cleared 11/18/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/18/2020 CALOSHA APPROVED
"Q" conditions Cleared 1/25/2021 MIGUEL GAMBOA
Frnt yard landscape/Water mgmt Cleared 1/25/2021 MIGUEL GAMBOA
Opn space landscape/Water mgmt Cleared 1/25/2021 MIGUEL GAMBOA
Density Bonus 12.22.A.25 Cleared 1/27/2021 JAMES MCCARTHY
ZI Cleared 1/27/2021 MIGUEL GAMBOA
Hydrant and Access approval Cleared 1/28/2021 JOHN CONNEALLY
Low Impact Development Cleared 2/9/2021 JORGE MEJIA LEMUS
Fire Marshall Fire Life Safety Cleared 4/12/2021 ANDREW KO
Roof/Waste drainage to street Cleared 4/23/2021 ADRIAN CASTRO
DAS Clearance Cleared 5/6/2021 MARJAN SHENASI
Green Code Cleared 5/17/2021 RICHARD GARCIA
Miscellaneous Cleared 7/28/2021 MIGUEL GAMBOA
Miscellaneous Cleared 7/31/2021 LEE GUILBEAUX
Permit Cleared 7/31/2021 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 8/30/2021 LEE GUILBEAUX

Contact Information

Architect Kostic,, Vasa; Lic. No.: C10740 1827-10TH ST_#4      SANTA MONICA, CA 90404
Contractor Summerland Partners Inc; Lic. No.: 865002-B 23622 CALABASAS ROAD SUITE 121      CALABASAS, CA 91302
Engineer Azarbin,, Hamid; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2021 Partial Inspection DANIEL VARNUM
Deputy Grading 12/2/2021 Approved JOHN KITCKO
Footing/Foundation/Slab 1/18/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 1/19/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 1/21/2022 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 1/24/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 1/26/2022 Approved JOHN KITCKO
Deputy Shotcrete 1/26/2022 Approved JOHN KITCKO
Green Building Rough 1/26/2022 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 1/26/2022 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 1/26/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 1/27/2022 Approved JOHN KITCKO
Deputy Shotcrete 1/27/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 1/28/2022 Approved JOHN KITCKO
Deputy Shotcrete 1/28/2022 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/9/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 3/8/2022 Approved JOHN KITCKO
Reinforced Masonry Frame 3/8/2022 Partial Approval JOHN KITCKO
Deputy Methane Barrier 3/25/2022 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 3/29/2022 Not Ready for Inspection JOHN KITCKO
Green Building Rough 3/30/2022 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 3/30/2022 Partial Approval JOHN KITCKO
Deputy Shotcrete 5/11/2022 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 6/21/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 6/21/2022 Conditional Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/21/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 6/22/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 6/22/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 6/23/2022 Approved JOHN KITCKO
Deputy Reinf. Masonry 6/23/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 6/24/2022 Approved JOHN KITCKO
Deputy Reinf. Masonry 6/24/2022 Approved JOHN KITCKO
Deputy Steel/Welding 7/5/2022 Conditional Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 7/5/2022 Partial Approval JOHN KITCKO
Deputy Steel/Welding 7/6/2022 Approved JOHN KITCKO
Masonry Wall/Backfill 7/7/2022 Partial Approval JOHN KITCKO
Deputy Steel/Welding 7/8/2022 Approved JOHN KITCKO
Deputy Steel/Welding 7/11/2022 Approved JOHN KITCKO
Deputy Steel/Welding 7/12/2022 Approved JOHN KITCKO
Deputy Steel/Welding 7/13/2022 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 7/14/2022 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 7/15/2022 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/22/2022 Partial Approval JOHN KITCKO
Deputy Wood Construction 8/1/2022 Conditional Approval JOHN KITCKO
Reinforced Concrete Frame 8/10/2022 Corrections Issued ANDREW DORSO
Deputy Wood Construction 8/11/2022 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 8/12/2022 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 8/16/2022 Partial Approval JOHN KITCKO
Deputy Wood Construction 8/26/2022 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Partial Approval ROBERT DAVIS
Deputy Wood Construction 9/20/2022 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Partial Approval JOHN KITCKO
Deputy Wood Construction 9/29/2022 Approved JOHN KITCKO
Deputy Wood Construction 9/30/2022 Conditional Approval ROBERT DAVIS
Deputy Wood Construction 10/13/2022 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Partial Approval JOHN KITCKO
Drywall Nailing 11/15/2022 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Corrections Issued DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Partial Approval JOHN KITCKO
Drywall Nailing 12/2/2022 Partial Approval JOHN KITCKO
Green Building Rough 12/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/9/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 12/12/2022 Not Ready for Inspection JOHN KITCKO
Insulation 12/14/2022 Partial Approval JOHN KITCKO
Drywall Nailing 12/15/2022 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Partial Approval JOHN KITCKO
Deputy Wood Construction 12/27/2022 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/3/2023 Partial Approval JOHN KITCKO
Insulation 1/5/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 1/12/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Partial Approval JOHN KITCKO
Insulation 1/20/2023 Partial Approval JOHN KITCKO
Special/Order Compliance 1/20/2023 Partial Approval STEVEN LEVITT
Insulation 1/31/2023 Corrections Issued ANDREW DORSO
Green Building Rough 2/3/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 2/3/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 2/8/2023 Not Ready for Inspection ROBERT DAVIS
Wood Frame 2/8/2023 Partial Approval ROBERT DAVIS
Insulation 2/10/2023 Partial Approval ROBERT DAVIS
Green Building Rough 2/17/2023 Partial Approval JOHN KITCKO
Wood Frame 2/17/2023 Partial Approval JOHN KITCKO
Drywall Nailing 2/22/2023 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 3/7/2023 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 3/7/2023 Partial Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 3/14/2023 Approved JOHN KITCKO
Special/Order Compliance 3/14/2023 Partial Approval STEVEN LEVITT
Green Building Rough 3/23/2023 Approved JOHN KITCKO
Wood Frame 3/23/2023 Approved JOHN KITCKO
Insulation 3/24/2023 Partial Approval JOHN KITCKO
Special/Order Compliance 3/24/2023 Partial Approval STEVEN LEVITT
Insulation 3/29/2023 Partial Approval JOHN KITCKO
Wood Frame 3/31/2023 Partial Inspection JEFFREY FULTON
Insulation 4/4/2023 Partial Approval JOHN KITCKO
Drywall Nailing 4/7/2023 Partial Approval JOHN KITCKO
Wood Frame 4/7/2023 Partial Approval JOHN KITCKO
Drywall Nailing 4/10/2023 Partial Approval JOHN KITCKO
Insulation 4/10/2023 Partial Inspection JOHN KITCKO
Drywall Nailing 4/12/2023 Partial Approval JOHN KITCKO
Drywall Nailing 4/18/2023 Corrections Issued JOHN KITCKO
Drywall Nailing 4/20/2023 Partial Approval JOHN KITCKO
Drywall Nailing 4/21/2023 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 5/9/2023 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 5/15/2023 Partial Approval JOHN KITCKO
Pre-Inspection 8/24/2023 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 8/28/2023 Partial Inspection JOHN KITCKO
Final 8/13/2024 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 8/13/2024 Approved JOHN KITCKO
Green Building Final 8/13/2024 Approved JOHN KITCKO
Reinforced Concrete Frame 8/13/2024 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 8/13/2024 SGSOV Approved JOHN KITCKO
Smoke Detectors 8/13/2024 Approved JOHN KITCKO
Wood Frame 8/13/2024 Approved JOHN KITCKO
Final 8/14/2024 Partial Inspection JOHN KITCKO
Final 8/16/2024 OK to Issue CofO JOHN KITCKO