11205-11205 1/2 W OXNARD ST 91606
Certificate Information: 11205-11205 1/2 W OXNARD ST 91606
- Application / Permit
- 19010-30000-04996
- Plan Check / Job No.
- B19WL06269
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 3-STORY DUPLEX WITH ATTACHED 4 CAR GARAGE (MIDDLE-DUPLEX B)
- Permit Issued
- Issued on 3/31/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2019 | TARIK SAOUD |
| Corrections Issued | 11/25/2019 | TARIK SAOUD |
| Quality Review Completed | 11/26/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 11/27/2019 | APPLICANT |
| Green Plans Picked Up | 12/27/2019 | APPLICANT |
| Plan Check Approved | 3/16/2020 | TARIK SAOUD |
| Issued | 3/31/2020 | LADBS |
| CofO in Progress | 3/25/2021 | DANIEL ORRANTE |
| Permit Finaled | 3/26/2021 | DANIEL ORRANTE |
| CofO Issued | 3/26/2021 | DANIEL ORRANTE |
| Permit Finaled | 3/26/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/27/2019 | ELAINE LEI |
| Permit | Cleared | 11/27/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 12/3/2019 | JOHN CONNEALLY |
| Sewer availability | Cleared | 12/3/2019 | ERIK BEASLEY |
| ZA Case | Cleared | 12/3/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 12/3/2019 | SOPHIE GABEL-SCHEINBAU |
| Trees in Parkway | Cleared | 12/6/2019 | JOHN KIM |
| Frnt yard landscape/Water mgmt | Cleared | 1/22/2020 | TERRI OSBORNE |
| Opn space landscape/Water mgmt | Cleared | 1/22/2020 | TERRI OSBORNE |
| Low Impact Development | Cleared | 2/5/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/10/2020 | ERIK BEASLEY |
| Green Code | Cleared | 2/11/2020 | RICHARD GARCIA |
| Highway dedication | Cleared | 3/13/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/15/2020 | Corrections Issued | BEAU COLLINS |
| Footing/Foundation/Slab | 4/27/2020 | Corrections Issued | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2020 | Partial Approval | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 9/9/2020 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 9/9/2020 | Approved | DANIEL DREW |
| Green Building Rough | 9/9/2020 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Rough | 9/9/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 9/9/2020 | Approved | DANIEL DREW |
| Verify Sprinkler Sign Off | 9/9/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 9/23/2020 | Approved | DANIEL DREW |
| Green Building Rough | 9/23/2020 | Approved | DANIEL DREW |
| Insulation | 9/23/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 10/5/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 10/5/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 10/13/2020 | Partial Approval | MATTHEW NELSON |
| Shower Pan | 10/13/2020 | Partial Approval | MATTHEW NELSON |
| Shower Pan | 10/15/2020 | Approved | DANIEL DREW |
| Final | 3/2/2021 | Not Ready for Inspection | DANIEL DREW |
| Footing/Foundation/Slab | 3/2/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 3/2/2021 | Not Ready for Inspection | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 3/2/2021 | SGSOV Not Ready | DANIEL DREW |
| Service/Power Release | 3/2/2021 | Not Ready for Inspection | DANIEL DREW |
| Smoke Detectors | 3/2/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Final | 3/3/2021 | Corrections Issued | DANIEL DREW |
| HVAC-Final | 3/3/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 3/3/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 3/5/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 3/5/2021 | Approved | DANIEL DREW |
| HVAC-Final | 3/8/2021 | Approved | DANIEL DREW |
| Pre-Inspection | 3/8/2021 | Approved | DANIEL DREW |
| Final | 3/25/2021 | OK to Issue CofO | DANIEL ORRANTE |
| Footing/Foundation/Slab | 3/25/2021 | Approved | DANIEL ORRANTE |
| Green Building Final | 3/25/2021 | Approved | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 3/25/2021 | SGSOV Approved | DANIEL ORRANTE |
| Service/Power Release | 3/25/2021 | Approved | DANIEL ORRANTE |
| Smoke Detectors | 3/25/2021 | Approved | DANIEL ORRANTE |