19231 W CANTARA ST 91335

Certificate Information: 19231 W CANTARA ST 91335

Application / Permit
19010-30000-04934
Plan Check / Job No.
B19WL06204
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) 1-STORY TYPE VB DETACHED GARAGE IN REAR
Permit Issued
Issued on 2/26/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 SERGIO SILVA
Corrections Issued 12/3/2019 SERGIO SILVA
Quality Review Completed 12/11/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/12/2019 APPLICANT
Green Plans Picked Up 12/12/2019 APPLICANT
Applicant returned to address corrections 2/6/2020 SERGIO SILVA
Applicant returned to address corrections 2/18/2020 SERGIO SILVA
Plan Check Approved 2/24/2020 SERGIO SILVA
Issued 2/26/2020 LADBS
CofO in Progress 10/7/2021 VINCENT HANLEY
CofO Issued 10/13/2021 MICHAEL SMITH
Permit Finaled 10/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/21/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 1/21/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 1/21/2020 JEREMY CARTER
Permit Cleared 1/21/2020 ANTHONY MAINEZ
Sewer availability Cleared 1/21/2020 ANTHONY MAINEZ
Trees in Parkway Cleared 1/21/2020 ADRIAN SANCHEZ
Low Impact Development Cleared 1/22/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/22/2020 ERIK BEASLEY
Green Code Cleared 2/18/2020 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/1/2020 Approved VINCENT HANLEY
Footing/Foundation/Slab 7/1/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 9/24/2020 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 10/19/2020 Approved DONALD SUNSERI
ELECTRICAL-Rough 10/19/2020 Approved DONALD SUNSERI
Green Building Rough 10/19/2020 Approved DONALD SUNSERI
Interior/Exterior Lathing 10/19/2020 Approved DONALD SUNSERI
Drywall Nailing 10/26/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/26/2020 Approved VINCENT HANLEY
Final 7/12/2021 Corrections Issued VINCENT HANLEY
Green Building Final 7/12/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 7/12/2021 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 7/12/2021 Approved VINCENT HANLEY
Final 9/9/2021 No Access for Inspection VINCENT HANLEY
Service/Power Release 9/9/2021 No Access for Inspection VINCENT HANLEY
ELECTRICAL-Final 10/7/2021 Approved VINCENT HANLEY
Final 10/7/2021 OK to Issue CofO VINCENT HANLEY
Gas Test 10/7/2021 Approved VINCENT HANLEY
HVAC-Final 10/7/2021 Approved VINCENT HANLEY
PLUMBING-Final 10/7/2021 Approved VINCENT HANLEY
Service/Power Release 10/7/2021 Approved VINCENT HANLEY