1008 S OAKWOOD AVE 90291

Certificate Information: 1008 S OAKWOOD AVE 90291

Application / Permit
19010-30000-04650
Plan Check / Job No.
B19WL05861
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2 story SFD (2842 sf) w./ att. carport (349 sf) and roof deck
Permit Issued
Issued on 10/16/2022
Issuing Office
Current Status
CofO Issued on 9/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 11/6/2019 VLADIMIR ARUTYUNYAN
Quality Review Completed 11/14/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 6/12/2020 APPLICANT
Plan Check Approved 3/23/2021 VLADIMIR ARUTYUNYAN
No Progress 12/7/2021 VLADIMIR ARUTYUNYAN
Plan Check Approved 12/17/2021 VLADIMIR ARUTYUNYAN
No Progress 8/12/2022 REZA HAGHIGHAT
Issued 10/16/2022 APPLICANT
Building Plans Picked Up 10/27/2022 APPLICANT
CofO in Progress 9/12/2024 HERBERT GIRON
Permit Finaled 9/16/2024 RICHARD STEINBACH
CofO Issued 9/16/2024 RICHARD STEINBACH
Permit Finaled 9/16/2024 RICHARD STEINBACH

Permit Application Clearance Information

Green Code Cleared 6/8/2020 RICHARD GARCIA
Permit Cleared 6/19/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/22/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/22/2020 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 1/4/2021 MATTHEW CRAIG
Trees in Parkway Cleared 1/7/2021 JOHN KIM
Coastal Zone Cleared 1/25/2021 LOUIS ORTEGA
Specific Plan Cleared 1/25/2021 LOUIS ORTEGA
ZA Case Cleared 1/25/2021 LOUIS ORTEGA
ZA Case Cleared 1/25/2021 LOUIS ORTEGA
ZA Case Cleared 1/25/2021 LOUIS ORTEGA
ZA Case Cleared 1/25/2021 LOUIS ORTEGA
Low Impact Development Cleared 2/19/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/22/2021 ANTHONY MAINEZ

Contact Information

Architect Lepair,, Yoram A; Lic. No.: C36127 850 S ROBERTSON BLVD      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Judd,, Shane Dennis; Lic. No.: C70991 17 E HIGH ST STE A      MOORPARK, CA 93021
Engineer Tsao,, Tze-Tzong; Lic. No.: C46886 9428 ETON AVE STE M      CHATSWORTH, CA 91311

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/1/2022 Partial Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 5/15/2023 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 5/15/2023 Partial Approval EVAN COOPER
Underground Mechanical 5/15/2023 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 5/23/2023 Partial Approval EVAN COOPER
Sewer 5/23/2023 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 6/7/2023 Approved EVAN COOPER
Footing/Foundation/Slab 6/7/2023 Approved EVAN COOPER
Underground Mechanical 6/7/2023 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 6/9/2023 Conditional Approval EVAN COOPER
Deputy Steel/Welding 7/28/2023 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Corrections Issued EVAN COOPER
Deputy Wood Construction 10/6/2023 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 10/24/2023 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/9/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 11/9/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 11/16/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 11/16/2023 Corrections Issued HERBERT GIRON
Special/Order Compliance 11/17/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 12/12/2023 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Partial Approval HERBERT GIRON
HVAC-Rough 12/12/2023 Approved HERBERT GIRON
PLUMBING-Rough 12/12/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 12/15/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/26/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 1/12/2024 Corrections Issued HERBERT GIRON
Green Building Rough 1/12/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 1/12/2024 Partial Approval HERBERT GIRON
Verify Sprinkler Sign Off 1/12/2024 Approved HERBERT GIRON
Insulation 1/16/2024 Partial Approval TEMISTOCLES CAAL
Special/Order Compliance 1/16/2024 Corrections Issued TEMISTOCLES CAAL
Insulation 1/18/2024 Not Ready for Inspection HERBERT GIRON
Insulation 1/19/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 1/29/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 1/29/2024 Approved JESUS RODRIGUEZ
Shower Pan 2/7/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 2/9/2024 Approved HERBERT GIRON
Underground Mechanical 3/12/2024 Approved HERBERT GIRON
Gas Test 4/3/2024 Approved HERBERT GIRON
HVAC-Final 4/15/2024 Corrections Issued HERBERT GIRON
HVAC-Final 4/19/2024 Approved HERBERT GIRON
ELECTRICAL-Final 4/23/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 4/24/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 4/26/2024 Approved HERBERT GIRON
Final 4/26/2024 Corrections Issued HERBERT GIRON
Green Building Final 4/26/2024 Approved HERBERT GIRON
PLUMBING-Final 4/26/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 4/26/2024 Approved HERBERT GIRON
Structural Steel Frame 4/26/2024 Approved HERBERT GIRON
Final 5/3/2024 Corrections Issued HERBERT GIRON
Service/Power Release 5/3/2024 Not Ready for Inspection HERBERT GIRON
Final 8/30/2024 Not Ready for Inspection HERBERT GIRON
Final 9/11/2024 OK to Issue CofO HERBERT GIRON
Service/Power Release 9/11/2024 Approved HERBERT GIRON