16011 W MIAMI WAY 90272
Certificate Information: 16011 W MIAMI WAY 90272
- Application / Permit
- 19010-30000-04583
- Plan Check / Job No.
- B19WL05765
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-story Single Family Dwelling with attached garage.
- Permit Issued
- Issued on 6/16/2021
- Issuing Office
- Current Status
- CofO Issued on 1/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | MARJAN SHENASI |
| Corrections Issued | 11/4/2019 | MARJAN SHENASI |
| Green Plans Picked Up | 11/4/2019 | APPLICANT |
| Quality Review Completed | 11/14/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/18/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 11/20/2020 | MARJAN SHENASI |
| Building Plans Picked Up | 11/23/2020 | APPLICANT |
| Applicant returned to address corrections | 4/12/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 4/26/2021 | MARJAN SHENASI |
| Plan Check Approved | 6/16/2021 | MARJAN SHENASI |
| Issued | 6/16/2021 | APPLICANT |
| CofO in Progress | 11/10/2022 | BRENDAN LOONEY |
| Permit Finaled | 1/25/2023 | DANIEL ORRANTE |
| CofO Issued | 1/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 4/17/2020 | JOHN KIM |
| Address approval | Cleared | 8/21/2020 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 9/8/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2020 | DINAH GARIN |
| Sewer availability | Cleared | 9/9/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 10/15/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/29/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/6/2020 | DINAH GARIN |
| Coastal Zone | Cleared | 3/19/2021 | LOUIS ORTEGA |
| GPI Written Notices | Cleared | 6/7/2021 | MARJAN SHENASI |
| Grading Pre-Inspection | Cleared | 6/7/2021 | MARJAN SHENASI |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Haddad,, Raymond Mounir; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/2/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 8/9/2021 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 11/15/2021 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Partial Approval | ANDREW NAVE |
| Sewer | 12/3/2021 | Not Ready for Inspection | ANDREW NAVE |
| Deputy Wood Construction | 12/6/2021 | Approved | ANDREW NAVE |
| Sewer | 12/6/2021 | Approved | ANDREW NAVE |
| Sewer | 12/7/2021 | Approved | ANDREW NAVE |
| Underground Mechanical | 12/7/2021 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 1/11/2022 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2022 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 1/12/2022 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 2/3/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 2/3/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 2/10/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 2/10/2022 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 2/17/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Approved | ANDREW NAVE |
| Green Building Rough | 3/3/2022 | Approved | ANDREW NAVE |
| Shower Pan | 3/3/2022 | Partial Approval | ANDREW NAVE |
| Special/Order Compliance | 3/3/2022 | Corrections Issued | ANDREW NAVE |
| Verify Rec and Parks Fee Memo | 3/3/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 3/10/2022 | Partial Approval | ANDREW NAVE |
| Insulation | 3/29/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 4/5/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 4/5/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 8/2/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 8/2/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 8/12/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 8/12/2022 | Corrections Issued | BRENDAN LOONEY |
| Final | 8/17/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 8/17/2022 | Approved | BRENDAN LOONEY |
| Green Building Final | 8/17/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 8/17/2022 | Partial Approval | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Not Ready | BRENDAN LOONEY |
| Service/Power Release | 8/17/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Smoke Detectors | 8/17/2022 | Approved | BRENDAN LOONEY |
| Gas Test | 8/23/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 8/23/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 8/23/2022 | SGSOV Not Ready | BRENDAN LOONEY |
| Final | 11/9/2022 | OK to Issue CofO | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 11/9/2022 | Approved | BRENDAN LOONEY |
| Service/Power Release | 11/16/2022 | Approved | KENNETH NAGLE |