728 N GENESEE AVE 90046
Certificate Information: 728 N GENESEE AVE 90046
- Application / Permit
- 19010-30000-04577
- Plan Check / Job No.
- B19WL05747
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ATTACHED GARAGE
- Permit Issued
- Issued on 1/30/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 10/30/2019 | VLADIMIR ARUTYUNYAN |
| Green Plans Picked Up | 11/4/2019 | APPLICANT |
| Quality Review Completed | 11/8/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 11/12/2019 | APPLICANT |
| Plan Check Approved | 1/30/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 1/30/2020 | LADBS |
| CofO in Progress | 1/8/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 1/11/2021 | DEROLD HAUFF |
| CofO Issued | 1/11/2021 | DEROLD HAUFF |
| Permit Finaled | 1/11/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/11/2019 | ROBERT DUFF |
| Green Code | Cleared | 12/12/2019 | DONALD CRICHLOW |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 12/17/2019 | AMMAR ELTAWIL |
| Permit | Cleared | 12/17/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 12/17/2019 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | DINAH GARIN |
| Trees in Parkway | Cleared | 1/27/2020 | HECTOR BANUELOS |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/22/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Reinf. Concrete | 4/30/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 4/30/2020 | Partial Approval | JOSEPH MCGARRY |
| Pre-Inspection | 5/13/2020 | Approved | CHRIS CHRISTENSEN |
| Sewer | 5/13/2020 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 5/13/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 5/29/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 5/29/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/7/2020 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/8/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 7/8/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/13/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/13/2020 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 7/13/2020 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/21/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 7/21/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 7/21/2020 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 7/21/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 7/27/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/4/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/4/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 10/2/2020 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/2/2020 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 10/14/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 10/14/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 10/14/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 10/14/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 10/14/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| METHANE-Barrier | 10/14/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 10/14/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 10/14/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 10/14/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 10/14/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/10/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 11/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 11/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 11/10/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/10/2020 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 11/10/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 11/24/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 11/24/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 1/8/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| HVAC-Final | 1/8/2021 | Approved | CHRIS CHRISTENSEN |