1635 S GENESEE AVE 90019
Certificate Information: 1635 S GENESEE AVE 90019
- Application / Permit
- 19010-30000-04548
- Plan Check / Job No.
- B19WL05720
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story accessory dwelling unit (ADU) w/ att. storage room in rear of the lot per AB 494 and SB 229.
- Permit Issued
- Issued on 3/16/2021
- Issuing Office
- Current Status
- Issued on 3/16/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | REZA HAGHIGHAT |
| Corrections Issued | 11/12/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 11/18/2019 | FELIX FIGUEROA |
| Green Plans Picked Up | 12/4/2019 | APPLICANT |
| Applicant returned to address corrections | 4/20/2020 | REZA HAGHIGHAT |
| Plan Check Approved | 4/20/2020 | REZA HAGHIGHAT |
| Building Plans Picked Up | 1/20/2021 | APPLICANT |
| Issued | 3/16/2021 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/24/2020 | ROBERT DUFF |
| Low Impact Development | Cleared | 2/24/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/24/2020 | CELINA MORENO |
| Address approval | Cleared | 2/26/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 3/6/2020 | RIDWAN HARDY |
| Green Code | Cleared | 3/12/2020 | RICHARD GARCIA |
| Sewer availability | Cleared | 3/12/2020 | ANTHONY MAINEZ |
Contact Information
| Architect | Devarajan,, Anand; Lic. No.: C30243 | 12641 MARCO PLACE LOS ANGELES, CA 90066 |
| Contractor | Bedrock Build And Design Inc; Lic. No.: 961595-B | P O BOX 1086 SIMI VALLEY, CA 93062 |
| Engineer | Varela, Olivas, Benjamin; Lic. No.: S5714 | 12831 PANAMA STREET LOS ANGELES, CA 90066 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 5/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 5/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/19/2021 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 5/19/2021 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 5/19/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 5/19/2021 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/4/2021 | Approved | STUART CHAPMAN |
| Deputy Reinf. Concrete | 6/8/2021 | No Access for Inspection | ELMER BLAND |
| Pre-Inspection | 6/9/2021 | Approved | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 6/16/2021 | Approved | ALFREDO BALANDRA |
| Excavation/Setback/Form/Re-Bar | 6/17/2021 | Approved | STUART CHAPMAN |
| Deputy Reinf. Concrete | 6/18/2021 | No Access for Inspection | ELMER BLAND |
| PLUMBING-Rough | 7/6/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2021 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 10/6/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 10/6/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| METHANE-Rough | 10/6/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| Special/Order Compliance | 10/6/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 10/6/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/26/2021 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 11/19/2021 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 11/19/2021 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 11/19/2021 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 11/19/2021 | Corrections Issued | JOSE AVILA |
| METHANE-Rough | 11/19/2021 | Approved | JOSE AVILA |
| PLUMBING-Rough | 11/19/2021 | Approved | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 11/19/2021 | Corrections Issued | JOSE AVILA |
| Verify Sprinkler Sign Off | 11/19/2021 | Conditional Approval | JOSE AVILA |
| Insulation | 12/17/2021 | Corrections Issued | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 12/17/2021 | Approved | JOSE AVILA |
| Drywall Nailing | 12/28/2021 | Not Ready for Inspection | JOSE AVILA |
| Green Building Rough | 12/28/2021 | Approved | JOSE AVILA |
| Insulation | 12/28/2021 | Approved | JOSE AVILA |
| Drywall Nailing | 1/4/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/4/2022 | Approved | JOSE AVILA |
| Shower Pan | 1/18/2022 | Approved | JOSE AVILA |
| Sewer | 4/5/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/12/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/12/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 12/12/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 12/12/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 12/12/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 12/12/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Not Required | ALIZAH MAYAGOITIA |
| Service/Power Release | 12/12/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 12/12/2022 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 12/12/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/16/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 5/16/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/11/2025 | Corrections Issued | ARTHUR NEGRETE |
| HVAC-Final | 2/11/2025 | Approved | ARTHUR NEGRETE |
| Final | 11/19/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 11/19/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Service/Power Release | 11/19/2025 | Not Ready for Inspection | ARTHUR NEGRETE |