8729 N AMBOY AVE 91352
Certificate Information: 8729 N AMBOY AVE 91352
- Application / Permit
- 19010-30000-04485
- Plan Check / Job No.
- B19WL05628
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT (ADU) AT REAR OF THE PROPERTY PER PER AB 494 & SB 229.
- Permit Issued
- Issued on 2/10/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | REZA HAGHIGHAT |
| Green Plans Picked Up | 10/17/2019 | APPLICANT |
| Corrections Issued | 10/21/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 11/1/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 11/1/2019 | APPLICANT |
| Plan Check Approved | 2/4/2020 | REZA HAGHIGHAT |
| Issued | 2/10/2020 | LADBS |
| CofO in Progress | 2/5/2021 | JOHN HAYES |
| CofO Issued | 2/9/2021 | MICHAEL SMITH |
| Permit Finaled | 2/9/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2019 | ERIK BEASLEY |
| Clean Up Green Up | Cleared | 11/5/2019 | TERRI OSBORNE |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 12/17/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 12/17/2019 | ORVAL HERNANDEZ-MARCI |
| Sewer availability | Cleared | 12/17/2019 | ERIK BEASLEY |
| Construction near power lines | Cleared | 1/15/2020 | RIDWAN HARDY |
| Green Code | Cleared | 1/22/2020 | DONALD CRICHLOW |
| Roof/Waste drainage to street | Cleared | 1/29/2020 | TRACY TATE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 5525 CANOGA AVE APT 208 WOODLAND HILLS, CA 91367 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/14/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 5/14/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 5/14/2020 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 5/14/2020 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 5/14/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/10/2020 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 6/10/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 7/2/2020 | No Access for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 7/7/2020 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 7/24/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 7/24/2020 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 7/24/2020 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 7/24/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 8/24/2020 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 8/24/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 8/24/2020 | Approved | MISAEL ESPARZA |
| Wood Frame | 8/24/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/28/2020 | No Access for Inspection | BEAU COLLINS |
| HVAC-Rough | 8/28/2020 | No Access for Inspection | BEAU COLLINS |
| Wood Frame | 8/28/2020 | No Access for Inspection | BEAU COLLINS |
| BUILDING-Rough-Frame | 9/9/2020 | Partial Approval | DANIEL ORRANTE |
| Interior/Exterior Lathing | 9/9/2020 | Approved | DANIEL ORRANTE |
| Insulation | 9/14/2020 | Approved | DAVID MATSON |
| Shower Pan | 9/14/2020 | Partial Approval | DAVID MATSON |
| Drywall Nailing | 9/17/2020 | Not Ready for Inspection | DAVID MATSON |
| Green Building Rough | 9/17/2020 | Approved | DAVID MATSON |
| Shower Pan | 9/17/2020 | Corrections Issued | DAVID MATSON |
| Drywall Nailing | 9/21/2020 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 9/21/2020 | Partial Approval | DAVID MATSON |
| Shower Pan | 9/21/2020 | Not Ready for Inspection | DAVID MATSON |
| Interior/Exterior Lathing | 9/24/2020 | Approved | MATTHEW NELSON |
| Shower Pan | 9/24/2020 | Approved | MATTHEW NELSON |
| Gas Test | 9/29/2020 | Approved | JOHN HAYES |
| PLUMBING-Rough | 9/29/2020 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 9/29/2020 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Final | 10/5/2020 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 10/5/2020 | Approved | JOHN HAYES |
| Service/Power Release | 10/14/2020 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 10/14/2020 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 12/4/2020 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 12/4/2020 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 12/4/2020 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 12/4/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 12/8/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 12/8/2020 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 12/10/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 12/10/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/10/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 12/10/2020 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 12/10/2020 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 12/10/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 12/10/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 12/10/2020 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 12/10/2020 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 12/10/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/5/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 1/5/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 1/5/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 1/5/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/5/2021 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 1/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 1/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 1/5/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/29/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 1/29/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 1/29/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 1/29/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/29/2021 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 1/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 1/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 1/29/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/4/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 2/4/2021 | Approved | JOHN HAYES |
| Final | 2/4/2021 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 2/4/2021 | Approved | JOHN HAYES |
| MERV13>=Final | 2/4/2021 | Approved | JOHN HAYES |
| MERV13>=Rough | 2/4/2021 | Approved | JOHN HAYES |
| PLUMBING-Final | 2/4/2021 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/4/2021 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 2/4/2021 | Approved | JOHN HAYES |
| Smoke Detectors | 2/4/2021 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 2/4/2021 | Approved | JOHN HAYES |