Excavation/Setback/Form/Re-Bar
|
12/2/2021
|
Partial Approval
|
STUART CHAPMAN
|
|
FLOOD-Elevation Certificate
|
12/2/2021
|
Partial Approval
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
12/2/2021
|
Corrections Issued
|
STUART CHAPMAN
|
|
PLUMBING-Rough
|
12/2/2021
|
Partial Approval
|
STUART CHAPMAN
|
|
Sewer
|
12/2/2021
|
Corrections Issued
|
STUART CHAPMAN
|
|
FLOOD-Elevation Certificate
|
12/6/2021
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
12/6/2021
|
Corrections Issued
|
STUART CHAPMAN
|
|
FLOOD-Elevation Certificate
|
2/10/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
2/10/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Deputy Reinf. Concrete
|
2/16/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
FLOOD-Elevation Certificate
|
3/10/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
3/10/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Excavation/Setback/Form/Re-Bar
|
4/1/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
FLOOD-Elevation Certificate
|
4/8/2022
|
Approved
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
4/8/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
BUILDING-Rough-Frame
|
5/9/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
FLOOD-Proofing Certificate
|
5/9/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Green Building Rough
|
5/9/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Verify Sprinkler Sign Off
|
5/9/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/11/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Insulation
|
5/11/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/24/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
5/26/2022
|
Corrections Issued
|
SCOTT FINNILA
|
|
Drywall Nailing
|
6/3/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Wood Frame
|
6/3/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
6/10/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
ELECTRICAL-Rough
|
6/10/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/10/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Green Building Rough
|
6/10/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Insulation
|
6/10/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Wood Frame
|
6/10/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Drywall Nailing
|
6/22/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Green Building Rough
|
6/22/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Drywall Nailing
|
7/11/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Green Building Rough
|
7/11/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/18/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Drywall Nailing
|
7/27/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Green Building Rough
|
7/27/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Wood Frame
|
7/27/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Drywall Nailing
|
8/2/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Green Building Rough
|
8/2/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/22/2022
|
Conditional Approval
|
SCOTT FINNILA
|
|
Wood Frame
|
9/19/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Wood Frame
|
10/19/2022
|
Corrections Issued
|
STUART CHAPMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/23/2022
|
Not Ready for Inspection
|
ALIZAH MAYAGOITIA
|
|
ELECTRICAL-Rough
|
12/28/2022
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
HVAC-Rough
|
12/28/2022
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/7/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
Deputy Wood Construction
|
2/17/2023
|
Conditional Approval
|
ALIZAH MAYAGOITIA
|
|
Gas Test
|
4/5/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
HVAC-Rough
|
4/5/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
PLUMBING-Rough
|
4/5/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/10/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Green Building Rough
|
4/10/2023
|
Not Ready for Inspection
|
ALIZAH MAYAGOITIA
|
|
HVAC-Rough
|
4/10/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
Drywall Nailing
|
4/19/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Green Building Rough
|
4/19/2023
|
Not Ready for Inspection
|
ALIZAH MAYAGOITIA
|
|
HVAC-Rough
|
4/19/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
|
Drywall Nailing
|
4/27/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Green Building Rough
|
4/27/2023
|
Not Ready for Inspection
|
ALIZAH MAYAGOITIA
|
|
Insulation
|
5/12/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
6/8/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
|
Interior/Exterior Lathing
|
6/8/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Pre-Inspection
|
6/28/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
Footing/Foundation/Slab
|
7/27/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
|
ELECTRICAL-Rough
|
10/31/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/31/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
BUILDING-Rough-Frame
|
3/12/2024
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Insulation
|
3/12/2024
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Interior/Exterior Lathing
|
3/12/2024
|
Approved
|
JOSEPH MCGARRY
|
|
Shower Pan
|
3/12/2024
|
Approved
|
JOSEPH MCGARRY
|
|
BUILDING-Rough-Frame
|
3/19/2024
|
Conditional Approval
|
JOSEPH MCGARRY
|
|
FLOOD-Proofing Certificate
|
3/19/2024
|
Approved
|
JOSEPH MCGARRY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/19/2024
|
Approved
|
JOSEPH MCGARRY
|
|
Green Building Rough
|
3/19/2024
|
Approved
|
JOSEPH MCGARRY
|
|
Verify Sprinkler Sign Off
|
3/19/2024
|
Approved
|
JOSEPH MCGARRY
|
|
Drywall Nailing
|
3/21/2024
|
Conditional Approval
|
JOSEPH MCGARRY
|
|
Special/Order Compliance
|
3/19/2025
|
Corrections Issued
|
BRENDAN MORELLI
|