Deputy Reinf. Concrete
|
1/25/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
1/25/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
1/25/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
2/3/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Deputy Drilled-In Anchors
|
4/28/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Deputy Shotcrete
|
5/6/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Deputy Shotcrete
|
5/7/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Deputy Shotcrete
|
5/11/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
5/21/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
5/21/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
5/25/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
5/25/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
5/25/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
5/27/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
5/27/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Shotcrete
|
6/15/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
6/15/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
7/9/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
7/14/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
7/16/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
8/6/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
8/9/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
8/19/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
8/19/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
8/19/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
10/8/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/8/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Shotcrete
|
10/22/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/22/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Deputy Shotcrete
|
10/26/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/26/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Underground Mechanical
|
11/18/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Underground Mechanical
|
12/3/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
12/7/2021
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
12/8/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/7/2022
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Special/Order Compliance
|
3/14/2022
|
Partial Inspection
|
JUAN VALENZUELA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/3/2022
|
No Access for Inspection
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/22/2022
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
8/19/2022
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/14/2022
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/27/2022
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Special/Order Compliance
|
10/27/2022
|
Corrections Issued
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/3/2022
|
Partial Approval
|
MICHAEL PELHAM
|
|
Special/Order Compliance
|
11/3/2022
|
Corrections Issued
|
MICHAEL PELHAM
|
|
Deputy Wood Construction
|
11/18/2022
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/13/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Structural Steel Frame
|
1/19/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/13/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Interior/Exterior Lathing
|
8/3/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
PLUMBING-Rough
|
8/22/2023
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
9/8/2023
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
HVAC-Rough
|
9/15/2023
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
PLUMBING-Rough
|
9/15/2023
|
Approved
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Rough
|
9/22/2023
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Rough
|
10/13/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/13/2023
|
Approved
|
CARLOS MATAMOROS
|
|
HVAC-Rough
|
10/13/2023
|
Approved
|
CARLOS MATAMOROS
|
|
BUILDING-Rough-Frame
|
10/17/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Green Building Rough
|
10/17/2023
|
Approved
|
CARLOS MATAMOROS
|
|
MERV13>=Rough
|
10/17/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Verify Sprinkler Sign Off
|
10/17/2023
|
Approved
|
CARLOS MATAMOROS
|
|
Drywall Nailing
|
11/14/2023
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Interior/Exterior Lathing
|
11/22/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Shower Pan
|
12/8/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Interior/Exterior Lathing
|
1/18/2024
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Shower Pan
|
1/18/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Deputy Drilled-In Anchors
|
4/18/2024
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
4/23/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Gas Test
|
4/23/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
6/3/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
7/10/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Sewer
|
7/23/2024
|
Approved
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
9/9/2024
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Service/Power Release
|
9/9/2024
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
10/8/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Service/Power Release
|
10/10/2024
|
Approved
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
2/4/2025
|
Approved
|
CARLOS MATAMOROS
|
|
Drywall Nailing
|
4/8/2025
|
Approved
|
CARLOS MATAMOROS
|
|
Final
|
4/8/2025
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
HVAC-Final
|
4/8/2025
|
Approved
|
CARLOS MATAMOROS
|
|
MERV13>=Final
|
4/8/2025
|
Approved
|
CARLOS MATAMOROS
|
|
PLUMBING-Final
|
4/8/2025
|
Approved
|
CARLOS MATAMOROS
|
|
SGSOV-Seismic Gas S/O Valve
|
4/8/2025
|
SGSOV Approved
|
CARLOS MATAMOROS
|
|
Smoke Detectors
|
4/8/2025
|
Approved
|
CARLOS MATAMOROS
|
|
Final
|
4/24/2025
|
OK to Issue CofO
|
CARLOS MATAMOROS
|
|
Green Building Final
|
4/24/2025
|
Approved
|
CARLOS MATAMOROS
|
|
Reinforced Concrete Frame
|
4/24/2025
|
Approved
|
CARLOS MATAMOROS
|