8802 S KITTYHAWK AVE 90045

Certificate Information: 8802 S KITTYHAWK AVE 90045

Application / Permit
19010-30000-04404
Plan Check / Job No.
B19WL05569
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ADU at rear of property per AB 494 & SB 229.
Permit Issued
Issued on 1/22/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 MANUEL GARCIA
Corrections Issued 11/15/2019 MANUEL GARCIA
Quality Review Completed 11/18/2019 FELIX FIGUEROA
Green Plans Picked Up 11/19/2019 APPLICANT
Plan Check Approved 1/22/2020 MANUEL GARCIA
Issued 1/22/2020 LADBS
Building Plans Picked Up 5/29/2020 APPLICANT
CofO in Progress 10/19/2020 PIERRE VEGA
CofO Issued 10/19/2020 VINCENT COTTON
Permit Finaled 10/19/2020 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 12/5/2019 EMIL KYUPELYAN
Construction near power lines Cleared 12/5/2019 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 12/5/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/5/2019 EMIL KYUPELYAN
Low Impact Development Cleared 12/13/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 12/13/2019 JAMES MORALEZ
Green Code Cleared 1/16/2020 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Ananian,, Vatche; Lic. No.: C79073 19528 VENTURA BLVD #374      TARZANA, CA 91356

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/27/2020 Partial Inspection JUAN VALENZUELA
Underground Mechanical 3/11/2020 Partial Inspection JUAN VALENZUELA
Underground Mechanical 3/12/2020 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 3/18/2020 Conditional Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 4/10/2020 Conditional Approval JUAN VALENZUELA
Special/Order Compliance 4/10/2020 Approved JUAN VALENZUELA
Special/Order Compliance 4/23/2020 Approved CRAIG DAVIS
BUILDING-Rough-Frame 4/30/2020 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 4/30/2020 Corrections Issued JUAN VALENZUELA
Green Building Rough 4/30/2020 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 4/30/2020 Corrections Issued JUAN VALENZUELA
Sewer 4/30/2020 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 4/30/2020 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 5/14/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 5/14/2020 Approved JOHNNY MIRANDA
Green Building Rough 5/14/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/14/2020 Partial Approval JOHNNY MIRANDA
Verify Sprinkler Sign Off 5/14/2020 Approved JOHNNY MIRANDA
HVAC-Rough 5/15/2020 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 5/15/2020 Approved CRAIG DAVIS
HVAC-Rough 6/29/2020 Approved JUAN VALENZUELA
Insulation 6/29/2020 Approved JUAN VALENZUELA
Drywall Nailing 7/13/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 7/13/2020 Not Ready for Inspection JUAN VALENZUELA
Interior/Exterior Lathing 7/15/2020 Approved JUAN VALENZUELA
Shower Pan 7/15/2020 Approved JUAN VALENZUELA
ELECTRICAL-Final 8/31/2020 Not Ready for Inspection MATT KELLERMAN
Final 8/31/2020 Not Ready for Inspection MATT KELLERMAN
Footing/Foundation/Slab 8/31/2020 Not Ready for Inspection MATT KELLERMAN
Gas Test 8/31/2020 Approved MATT KELLERMAN
Green Building Final 8/31/2020 Not Ready for Inspection MATT KELLERMAN
HVAC-Final 8/31/2020 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Final 8/31/2020 Not Ready for Inspection MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 8/31/2020 SGSOV No Gas MATT KELLERMAN
Service/Power Release 8/31/2020 Not Ready for Inspection MATT KELLERMAN
Smoke Detectors 8/31/2020 Not Ready for Inspection MATT KELLERMAN
ELECTRICAL-Final 9/15/2020 Corrections Issued JUAN VALENZUELA
Final 9/15/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 9/15/2020 Conditional Approval JUAN VALENZUELA
Green Building Final 9/15/2020 Corrections Issued JUAN VALENZUELA
HVAC-Final 9/15/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Final 9/15/2020 Corrections Issued JUAN VALENZUELA
Service/Power Release 9/15/2020 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 9/15/2020 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 10/2/2020 Approved JOHNNY MIRANDA
Final 10/2/2020 OK to Issue CofO JOHNNY MIRANDA
Footing/Foundation/Slab 10/2/2020 Approved JOHNNY MIRANDA
Green Building Final 10/2/2020 Approved JOHNNY MIRANDA
HVAC-Final 10/2/2020 Approved JOHNNY MIRANDA
PLUMBING-Final 10/2/2020 Approved JOHNNY MIRANDA
Service/Power Release 10/2/2020 Approved JOHNNY MIRANDA
Smoke Detectors 10/2/2020 Approved JOHNNY MIRANDA