6510 W 5TH ST 90048

Certificate Information: 6510 W 5TH ST 90048

Application / Permit
19010-30000-04390
Plan Check / Job No.
B19WL05558
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 2-story s.f.r.
Permit Issued
Issued on 7/21/2020
Issuing Office
Current Status
CofO Issued on 1/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 KAVIAN REFAHI
Corrections Issued 10/22/2019 KAVIAN REFAHI
Green Plans Picked Up 10/25/2019 APPLICANT
Quality Review Completed 10/31/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 11/4/2019 APPLICANT
Applicant returned to address corrections 12/2/2019 KAVIAN REFAHI
Applicant returned to address corrections 1/8/2020 KAVIAN REFAHI
Applicant returned to address corrections 2/18/2020 KAVIAN REFAHI
Applicant returned to address corrections 3/23/2020 KAVIAN REFAHI
Applicant returned to address corrections 4/16/2020 KAVIAN REFAHI
Plan Check Approved 4/21/2020 KAVIAN REFAHI
Issued 7/21/2020 APPLICANT
CofO in Progress 3/16/2023 JEREMY TODD
Permit Finaled 1/18/2024 DANIEL ORRANTE
CofO Issued 1/18/2024 DANIEL ORRANTE
Permit Finaled 1/18/2024 DANIEL ORRANTE

Permit Application Clearance Information

Trees in Parkway Cleared 11/6/2019 JOHN KIM
Address approval Cleared 11/27/2019 JAMES MORALEZ
CPC Cleared 11/27/2019 ANNA VAN
CPC Cleared 11/27/2019 ANNA VAN
Eng Process Fee Ord 176,300 Cleared 11/27/2019 JAMES MORALEZ
Low Impact Development Cleared 12/31/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/31/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 1/7/2020 JEREMY CARTER
ZI Cleared 1/30/2020 TERRI OSBORNE
Green Code Cleared 3/25/2020 RICHARD GARCIA
Sewer availability Cleared 3/31/2020 ELAINE LEI
Permit Cleared 4/20/2020 DINAH GARIN

Contact Information

Contractor Mega Builders Inc; Lic. No.: 898347-B 18375 VENTURA BLVD SUITE 520      TARZANA, CA 91356
Engineer Azarbin,, Hamid Reza; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/24/2020 Partial Approval EVAN COOPER
Special/Order Compliance 8/27/2020 Approved EVAN COOPER
Footing/Foundation/Slab 8/31/2020 Partial Approval EVAN COOPER
METHANE-Barrier 8/31/2020 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 8/31/2020 Approved EVAN COOPER
Footing/Foundation/Slab 9/14/2020 Corrections Issued EVAN COOPER
METHANE-Barrier 9/14/2020 Partial Approval EVAN COOPER
Deputy Steel/Welding 10/1/2020 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 10/2/2020 Corrections Issued EVAN COOPER
Green Building Rough 10/2/2020 Not Ready for Inspection EVAN COOPER
METHANE-Rough 10/2/2020 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 10/2/2020 Not Ready for Inspection EVAN COOPER
Wood Frame 10/27/2020 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 11/5/2020 Not Ready for Inspection EVAN COOPER
Green Building Rough 11/5/2020 Not Ready for Inspection EVAN COOPER
METHANE-Rough 11/5/2020 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 11/5/2020 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Partial Approval EVAN COOPER
Deputy Steel/Welding 11/20/2020 Conditional Approval EVAN COOPER
ELECTRICAL-Rough 1/19/2021 Not Ready for Inspection EVAN COOPER
HVAC-Rough 1/19/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 1/19/2021 Approved EVAN COOPER
ELECTRICAL-Rough 2/5/2021 Approved EVAN COOPER
HVAC-Rough 2/5/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 2/10/2021 Partial Approval EVAN COOPER
Green Building Rough 2/10/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 2/10/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 2/10/2021 Not Ready for Inspection EVAN COOPER
Insulation 2/22/2021 No Access for Inspection EVAN COOPER
Drywall Nailing 3/18/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 3/18/2021 Approved KEVIN SARGSYAN
Shower Pan 3/18/2021 Approved KEVIN SARGSYAN
Special/Order Compliance 7/16/2021 Approved EVAN COOPER
Service/Power Release 9/28/2021 Not Ready for Inspection EVAN COOPER
Gas Test 11/1/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 11/1/2021 Approved JOHNNY MIRANDA
Service/Power Release 11/1/2021 Not Ready for Inspection JOHNNY MIRANDA
Final 12/6/2021 Corrections Issued EVAN COOPER
Special/Order Compliance 1/25/2022 Approved EVAN COOPER
Special/Order Compliance 1/27/2022 Approved EVAN COOPER
Service/Power Release 2/7/2022 Corrections Issued EVAN COOPER
ELECTRICAL-Final 2/16/2022 Approved EVAN COOPER
Service/Power Release 2/16/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 5/11/2022 Approved EVAN COOPER
Final 5/11/2022 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 5/11/2022 Approved EVAN COOPER
Green Building Final 5/11/2022 Approved EVAN COOPER
Green Building Rough 5/11/2022 Approved EVAN COOPER
METHANE-Barrier 5/11/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 5/11/2022 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 5/11/2022 Approved EVAN COOPER
Final 6/9/2022 Corrections Issued STEPHANIE SWANSON
Final 6/16/2022 Corrections Issued EVAN COOPER
Final 3/15/2023 OK to Issue CofO JEREMY TODD
HVAC-Final 3/15/2023 Approved JEREMY TODD
Smoke Detectors 3/15/2023 Approved JEREMY TODD