6510 W 5TH ST 90048
Certificate Information: 6510 W 5TH ST 90048
- Application / Permit
- 19010-30000-04390
- Plan Check / Job No.
- B19WL05558
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2-story s.f.r.
- Permit Issued
- Issued on 7/21/2020
- Issuing Office
- Current Status
- CofO Issued on 1/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | KAVIAN REFAHI |
| Corrections Issued | 10/22/2019 | KAVIAN REFAHI |
| Green Plans Picked Up | 10/25/2019 | APPLICANT |
| Quality Review Completed | 10/31/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 11/4/2019 | APPLICANT |
| Applicant returned to address corrections | 12/2/2019 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/8/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/18/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 3/23/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 4/16/2020 | KAVIAN REFAHI |
| Plan Check Approved | 4/21/2020 | KAVIAN REFAHI |
| Issued | 7/21/2020 | APPLICANT |
| CofO in Progress | 3/16/2023 | JEREMY TODD |
| Permit Finaled | 1/18/2024 | DANIEL ORRANTE |
| CofO Issued | 1/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 11/6/2019 | JOHN KIM |
| Address approval | Cleared | 11/27/2019 | JAMES MORALEZ |
| CPC | Cleared | 11/27/2019 | ANNA VAN |
| CPC | Cleared | 11/27/2019 | ANNA VAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2019 | JAMES MORALEZ |
| Low Impact Development | Cleared | 12/31/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/31/2019 | ELENA LOPEZ |
| Hydrant and Access approval | Cleared | 1/7/2020 | JEREMY CARTER |
| ZI | Cleared | 1/30/2020 | TERRI OSBORNE |
| Green Code | Cleared | 3/25/2020 | RICHARD GARCIA |
| Sewer availability | Cleared | 3/31/2020 | ELAINE LEI |
| Permit | Cleared | 4/20/2020 | DINAH GARIN |
Contact Information
| Contractor | Mega Builders Inc; Lic. No.: 898347-B | 18375 VENTURA BLVD SUITE 520 TARZANA, CA 91356 |
| Engineer | Azarbin,, Hamid Reza; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/24/2020 | Partial Approval | EVAN COOPER |
| Special/Order Compliance | 8/27/2020 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 8/31/2020 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 8/31/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 8/31/2020 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 9/14/2020 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 9/14/2020 | Partial Approval | EVAN COOPER |
| Deputy Steel/Welding | 10/1/2020 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 10/2/2020 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 10/2/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 10/2/2020 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 10/2/2020 | Not Ready for Inspection | EVAN COOPER |
| Wood Frame | 10/27/2020 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 11/5/2020 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 11/5/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 11/5/2020 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 11/5/2020 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2020 | Partial Approval | EVAN COOPER |
| Deputy Steel/Welding | 11/20/2020 | Conditional Approval | EVAN COOPER |
| ELECTRICAL-Rough | 1/19/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 1/19/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 1/19/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 2/5/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 2/5/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/10/2021 | Partial Approval | EVAN COOPER |
| Green Building Rough | 2/10/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 2/10/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 2/10/2021 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 2/22/2021 | No Access for Inspection | EVAN COOPER |
| Drywall Nailing | 3/18/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 3/18/2021 | Approved | KEVIN SARGSYAN |
| Shower Pan | 3/18/2021 | Approved | KEVIN SARGSYAN |
| Special/Order Compliance | 7/16/2021 | Approved | EVAN COOPER |
| Service/Power Release | 9/28/2021 | Not Ready for Inspection | EVAN COOPER |
| Gas Test | 11/1/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 11/1/2021 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 11/1/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 12/6/2021 | Corrections Issued | EVAN COOPER |
| Special/Order Compliance | 1/25/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 1/27/2022 | Approved | EVAN COOPER |
| Service/Power Release | 2/7/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 2/16/2022 | Approved | EVAN COOPER |
| Service/Power Release | 2/16/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | EVAN COOPER |
| Final | 5/11/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 5/11/2022 | Approved | EVAN COOPER |
| Green Building Final | 5/11/2022 | Approved | EVAN COOPER |
| Green Building Rough | 5/11/2022 | Approved | EVAN COOPER |
| METHANE-Barrier | 5/11/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 5/11/2022 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 5/11/2022 | Approved | EVAN COOPER |
| Final | 6/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| Final | 6/16/2022 | Corrections Issued | EVAN COOPER |
| Final | 3/15/2023 | OK to Issue CofO | JEREMY TODD |
| HVAC-Final | 3/15/2023 | Approved | JEREMY TODD |
| Smoke Detectors | 3/15/2023 | Approved | JEREMY TODD |