289 N TIGERTAIL ROAD 90049
Certificate Information: 289 N TIGERTAIL ROAD 90049
- Application / Permit
- 19010-30000-04365
- Plan Check / Job No.
- B19WL05535
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 1-STORY REC-ROOM IN REAR OF THE PROPERTY.
- Permit Issued
- Issued on 12/1/2020
- Issuing Office
- Current Status
- CofO Issued on 10/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | REZA HAGHIGHAT |
| Corrections Issued | 10/15/2019 | REZA HAGHIGHAT |
| Green Plans Picked Up | 10/17/2019 | APPLICANT |
| Quality Review Completed | 10/31/2019 | MARJAN SHENASI |
| Applicant returned to address corrections | 12/13/2019 | REZA HAGHIGHAT |
| Plan Check Approved | 11/21/2020 | REZA HAGHIGHAT |
| Issued | 12/1/2020 | APPLICANT |
| Building Plans Picked Up | 12/2/2020 | APPLICANT |
| CofO in Progress | 5/10/2021 | JUAN VALENZUELA |
| Permit Finaled | 10/16/2021 | DANIEL ORRANTE |
| CofO Issued | 10/16/2021 | DANIEL ORRANTE |
| Permit Finaled | 10/16/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 12/3/2019 | RICHARD GARCIA |
| BHO/Hillside ordinance | Cleared | 12/12/2019 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 12/12/2019 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 12/12/2019 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2019 | CATHERINE ADROVER |
| Sewer availability | Cleared | 12/12/2019 | CATHERINE ADROVER |
| Grading Pre-Inspection | Cleared | 12/13/2019 | REZA HAGHIGHAT |
| Hydrant and Access approval | Cleared | 8/12/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/28/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/13/2020 | MAHELET GEBEYHU |
| Watercourse | Cleared | 11/13/2020 | MAHELET GEBEYHU |
Contact Information
| Architect | Whitten,, Charles Alexander; Lic. No.: C30241 | 10716 ESTHER AVE LOS ANGELES, CA 90064 |
| Contractor | Saltair Group Inc; Lic. No.: 960192-B | PO BOX 689 PACIFIC PALISADES, CA 90272 |
| Engineer | Nguyen,, Tuan Minh; Lic. No.: S5883 | 5552 W 123RD PLACE HAWTHORNE, CA 90250 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/14/2020 | Approved | JOHN KIDWELL |
| FLOOD-Elevation Certificate | 12/14/2020 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 12/14/2020 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 1/22/2021 | Corrections Issued | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 1/22/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 1/22/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 2/4/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/17/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 2/17/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Drywall Nailing | 3/4/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Rough | 3/4/2021 | Approved | JUAN VALENZUELA |
| Insulation | 3/4/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 3/4/2021 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 3/12/2021 | Approved | JUAN VALENZUELA |
| Final | 4/15/2021 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 4/15/2021 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 4/15/2021 | SGSOV Not Required | JUAN VALENZUELA |
| Service/Power Release | 4/15/2021 | Not Required | JUAN VALENZUELA |
| Smoke Detectors | 4/15/2021 | Approved | JUAN VALENZUELA |
| Structural Steel Frame | 4/15/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 4/30/2021 | Approved | JUAN VALENZUELA |
| Final | 4/30/2021 | OK to Issue CofO | JUAN VALENZUELA |
| Green Building Final | 4/30/2021 | Approved | JUAN VALENZUELA |
| HVAC-Final | 4/30/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 4/30/2021 | Approved | JUAN VALENZUELA |