2117 S PURDUE AVE 90025
Certificate Information: 2117 S PURDUE AVE 90025
- Application / Permit
- 19010-30000-04249
- Plan Check / Job No.
- B19WL05398
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 3-story SFD wih attached garage (Back unit)
- Permit Issued
- Issued on 5/5/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | TARIK SAOUD |
| Corrections Issued | 10/13/2019 | TARIK SAOUD |
| Green Plans Picked Up | 10/15/2019 | APPLICANT |
| Quality Review Completed | 10/16/2019 | FELIX FIGUEROA |
| Plan Check Approved | 2/6/2020 | TARIK SAOUD |
| Issued | 5/5/2020 | LADBS |
| Building Plans Picked Up | 5/5/2020 | APPLICANT |
| CofO in Progress | 9/6/2022 | JOHN KIDWELL |
| Permit Finaled | 9/22/2022 | DANIEL ORRANTE |
| CofO Issued | 9/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2019 | CELINA MORENO |
| CPC | Cleared | 12/10/2019 | ANNA VAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2019 | CELINA MORENO |
| Permit | Cleared | 12/10/2019 | CELINA MORENO |
| Sewer availability | Cleared | 12/10/2019 | CELINA MORENO |
| Trees in Parkway | Cleared | 12/18/2019 | JOHN KIM |
| Low Impact Development | Cleared | 12/19/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 12/20/2019 | JEREMY CARTER |
| Green Code | Cleared | 1/2/2020 | RICHARD GARCIA |
Contact Information
| Architect | Daham,, Ramsey Walid; Lic. No.: C34257 | 109 EUCALYPTUS DRIVE EL SEGUNDO, CA 90245 |
| Contractor | Owner-Builder | , |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/1/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 10/19/2020 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/21/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 10/28/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/2/2020 | Approved | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 11/30/2020 | No Access for Inspection | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 12/22/2020 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/24/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 12/24/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 12/24/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 1/4/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 1/11/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 1/19/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/17/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 3/17/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 3/17/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/12/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/8/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/20/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 7/22/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/11/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Rough | 8/11/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 8/11/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/13/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 8/13/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/24/2021 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/30/2021 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 9/9/2021 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 9/14/2021 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 9/28/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/10/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/15/2021 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 2/7/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/20/2022 | Approved | ANDREW NAVE |
| HVAC-Final | 6/1/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 7/25/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 8/15/2022 | Approved | JOHN KIDWELL |
| Final | 8/29/2022 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 8/29/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 8/29/2022 | Approved | JOHN KIDWELL |
| Final | 9/6/2022 | OK to Issue CofO | JOHN KIDWELL |
| Service/Power Release | 9/6/2022 | Approved | JOHN KIDWELL |