3761 S 4TH AVE 90018
Certificate Information: 3761 S 4TH AVE 90018
- Application / Permit
- 19010-30000-04181
- Plan Check / Job No.
- B19WL05341
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT (ADU) (23' X 36') W/ ATT. COVERED PATIO (5' X 23') PER AB 494 AND SB 229 IN REAR OF THE PROPERTY.
- Permit Issued
- Issued on 10/28/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | REZA HAGHIGHAT |
| Corrections Issued | 10/15/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 10/24/2019 | FELIX FIGUEROA |
| Green Plans Picked Up | 6/23/2020 | APPLICANT |
| Plan Check Approved | 10/1/2020 | REZA HAGHIGHAT |
| Building Plans Picked Up | 10/5/2020 | APPLICANT |
| Issued | 10/28/2020 | APPLICANT |
| CofO in Progress | 6/9/2021 | STUART CHAPMAN |
| Permit Finaled | 7/1/2021 | DEROLD HAUFF |
| CofO Issued | 7/1/2021 | DEROLD HAUFF |
| Permit Finaled | 7/1/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/13/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 2/13/2020 | ROBERT DUFF |
| Sewer availability | Cleared | 2/13/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 5/5/2020 | ORVAL HERNANDEZ-MARCI |
| Green Code | Cleared | 6/16/2020 | RICHARD GARCIA |
| Roof/Waste drainage to street | Cleared | 7/20/2020 | JEANIE LAM |
| Construction near power lines | Cleared | 9/14/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Monroy M W Construction Inc; Lic. No.: 1066342-B | 710 W 66TH ST LOS ANGELES, CA 90044 |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2320 SANTA CRUZ CT TORRANCE, CA 90501 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2020 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2020 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 11/17/2020 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2020 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/18/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 12/18/2020 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 12/18/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 12/18/2020 | Approved | STUART CHAPMAN |
| Insulation | 12/24/2020 | Approved | STUART CHAPMAN |
| Drywall Nailing | 12/31/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 12/31/2020 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/31/2021 | Approved | STUART CHAPMAN |
| Final | 3/31/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 3/31/2021 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2021 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 3/31/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 3/31/2021 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 3/31/2021 | Approved | STUART CHAPMAN |
| Green Building Final | 4/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 5/5/2021 | Approved | STUART CHAPMAN |
| Final | 5/5/2021 | Conditional Approval | STUART CHAPMAN |
| Green Building Final | 5/5/2021 | Approved | STUART CHAPMAN |
| HVAC-Final | 5/5/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 5/5/2021 | Approved | STUART CHAPMAN |
| Service/Power Release | 5/5/2021 | Approved | STUART CHAPMAN |