320 S CANYON VIEW DR 90049
Certificate Information: 320 S CANYON VIEW DR 90049
- Application / Permit
- 19010-30000-04047
- Plan Check / Job No.
- B19WL05145
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New single family house with basement and attached garage
- Permit Issued
- Issued on 1/15/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 9/30/2019 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 10/1/2019 | APPLICANT |
| Quality Review Completed | 10/3/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 10/3/2019 | APPLICANT |
| Applicant returned to address corrections | 10/17/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/8/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/20/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/10/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/26/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/15/2020 | KAMRAN GHOTBI RAVANDI |
| Issued | 1/15/2020 | LADBS |
| CofO in Progress | 2/22/2022 | JOHN KIDWELL |
| Permit Finaled | 2/28/2022 | DANIEL ORRANTE |
| CofO Issued | 2/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2019 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 10/4/2019 | JEREMY CARTER |
| Sewer availability | Cleared | 10/4/2019 | JEANETTE VONG |
| Trees in Parkway | Cleared | 10/4/2019 | JOHN KIM |
| Low Impact Development | Cleared | 10/9/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/9/2019 | CELINA MORENO |
| Permit | Cleared | 10/10/2019 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 10/16/2019 | MAHELET GEBEYHU |
| Watercourse | Cleared | 10/16/2019 | MAHELET GEBEYHU |
| Specific Plan | Cleared | 10/24/2019 | VALERIA CEJA |
| Green Code | Cleared | 11/19/2019 | RICHARD GARCIA |
| Excavation more than 5-ft deep | Cleared | 11/20/2019 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Haro,, Ruben; Lic. No.: GE2990 | 1554 CIPRES CT CAMARILLO, CA 93010 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 1836 PARNELL AVE 202 LOS ANGELES, CA 90025 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/20/2020 | Partial Approval | DANNY TOLENTINO |
| FLOOD-Elevation Certificate | 2/28/2020 | Approved | DANNY TOLENTINO |
| Footing/Foundation/Slab | 2/28/2020 | Partial Approval | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 3/6/2020 | Partial Approval | ROBERT SHELLY |
| PLUMBING-Rough | 3/23/2020 | Corrections Issued | DANNY TOLENTINO |
| PLUMBING-Rough | 3/27/2020 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/1/2020 | Partial Approval | DANNY TOLENTINO |
| Deputy Steel/Welding | 5/4/2020 | No Access for Inspection | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2020 | Conditional Approval | DANNY TOLENTINO |
| Deputy Steel/Welding | 5/21/2020 | No Access for Inspection | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2020 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2020 | Approved | TIM CHRISTENSEN |
| HVAC-Rough | 9/23/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 9/23/2020 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/25/2020 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 9/28/2020 | Partial Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/2/2020 | Approved | JOHN KIDWELL |
| Rough-Elec/Plmb/HVAC | 10/2/2020 | Approved | JOHN KIDWELL |
| Shower Pan | 10/2/2020 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/8/2020 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 10/8/2020 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/14/2020 | Approved | JOHN KIDWELL |
| FLOOD-Proofing Certificate | 10/14/2020 | Approved | JOHN KIDWELL |
| Green Building Rough | 10/14/2020 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 10/14/2020 | Approved | JOHN KIDWELL |
| Drywall Nailing | 11/13/2020 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 8/16/2021 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 8/25/2021 | Partial Inspection | JOHN KIDWELL |
| Service/Power Release | 9/20/2021 | Approved | KENNETH NAGLE |
| Sewer | 11/1/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 11/18/2021 | Corrections Issued | JOHN KIDWELL |
| ELECTRICAL-Final | 11/22/2021 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 12/3/2021 | Approved | JOHN KIDWELL |
| Green Building Final | 12/3/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 12/3/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 12/3/2021 | Approved | JOHN KIDWELL |
| Final | 12/13/2021 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/13/2021 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 12/13/2021 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 12/13/2021 | Approved | JUAN VALENZUELA |
| Pre-Inspection | 2/8/2022 | Partial Inspection | JOHN KIDWELL |
| Final | 2/22/2022 | OK to Issue CofO | JOHN KIDWELL |