140 N BRISTOL AVE 90049
Certificate Information: 140 N BRISTOL AVE 90049
- Application / Permit
- 19010-30000-04009
- Plan Check / Job No.
- B19WL05107
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- New accessory living quarter with att. storage room
- Permit Issued
- Issued on 12/20/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | REZA HAGHIGHAT |
| Green Plans Picked Up | 9/26/2019 | APPLICANT |
| Corrections Issued | 9/27/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 10/4/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 10/8/2019 | APPLICANT |
| Applicant returned to address corrections | 10/24/2019 | REZA HAGHIGHAT |
| Plan Check Approved | 11/26/2019 | REZA HAGHIGHAT |
| Issued | 12/20/2019 | LADBS |
| CofO in Progress | 8/20/2021 | JUAN VALENZUELA |
| CofO Issued | 9/21/2021 | RONALD MYRICK |
| Permit Finaled | 9/21/2021 | RONALD MYRICK |
Permit Application Clearance Information
| ZA Case | Cleared | 10/15/2019 | SARAH GOLDMAN |
| Grading Pre-Inspection | Cleared | 10/24/2019 | REZA HAGHIGHAT |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | JOHN LIN |
| Hydrant and Access approval | Cleared | 11/14/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 11/14/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/14/2019 | JOHN LIN |
| Sewer availability | Cleared | 11/14/2019 | JOHN LIN |
| Public Works-Highway Ded. | Cleared | 11/14/2019 | JOHN LIN |
| Public Works-Open Permits | Cleared | 11/14/2019 | JOHN LIN |
| Public Works-Sewers | Cleared | 11/14/2019 | JOHN LIN |
| Green Code | Cleared | 11/26/2019 | RICHARD GARCIA |
Contact Information
| Contractor | Synergy General Contractors Inc; Lic. No.: 650318-B | 199 SADDLEBOW ROAD BELL CANYON, CA 91307 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Danz,, Joshua Franklin; Lic. No.: C84764 | 932 WITHERSPOON DRIVE THOUSAND OAKS, CA 91360 |
| Engineer | Padilla,, Juan C; Lic. No.: C79760 | 647 ERBES ROAD THOUSAND OAKS, CA 91362 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/29/2020 | Partial Approval | TIM CHRISTENSEN |
| Underground Mechanical | 9/21/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Underground Mechanical | 10/7/2020 | Corrections Issued | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 10/16/2020 | Approved | TIM CHRISTENSEN |
| Underground Mechanical | 10/16/2020 | Approved | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 11/6/2020 | Not Ready for Inspection | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/17/2021 | Conditional Approval | JUAN VALENZUELA |
| Drywall Nailing | 8/17/2021 | Approved | JUAN VALENZUELA |
| Final | 8/17/2021 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 8/17/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 8/17/2021 | Approved | JUAN VALENZUELA |
| HVAC-Final | 8/17/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 8/17/2021 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/17/2021 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 8/17/2021 | Approved | JUAN VALENZUELA |
| Smoke Detectors | 8/17/2021 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 8/17/2021 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/19/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 8/19/2021 | Approved | JUAN VALENZUELA |
| Final | 8/19/2021 | OK to Issue CofO | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 8/19/2021 | Approved | JUAN VALENZUELA |