15228 W DE PAUW ST 90272
Certificate Information: 15228 W DE PAUW ST 90272
- Application / Permit
- 19010-30000-03943
- Plan Check / Job No.
- B19WL04981
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2 story s.f.d. over basement with attached garage.
- Permit Issued
- Issued on 12/17/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 9/24/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 9/30/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 10/1/2019 | APPLICANT |
| Green Plans Picked Up | 10/1/2019 | APPLICANT |
| Applicant returned to address corrections | 10/17/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/12/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/25/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 12/11/2019 | KAMRAN GHOTBI RAVANDI |
| Issued | 12/17/2019 | LADBS |
| CofO in Progress | 7/8/2021 | ANDREW NAVE |
| Permit Finaled | 7/9/2021 | KENNETH NAGLE |
| CofO Issued | 7/9/2021 | KENNETH NAGLE |
| Permit Finaled | 7/9/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Permit | Cleared | 10/17/2019 | DINAH GARIN |
| Green Code | Cleared | 11/6/2019 | DONALD CRICHLOW |
| Hydrant and Access approval | Cleared | 11/8/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 11/18/2019 | ORVAL HERNANDEZ-MARCIAL |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2019 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 11/25/2019 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 11/25/2019 | JOHN KIM |
| Coastal Zone | Cleared | 11/27/2019 | NOAH MCCOY |
| ZI | Cleared | 11/27/2019 | NOAH MCCOY |
| Roof/Waste drainage to street | Cleared | 12/10/2019 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 12/11/2019 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 1/16/2020 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 1/28/2020 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 2/19/2020 | Partial Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 3/9/2020 | Partial Approval | ANDREW NAVE |
| Deputy Shotcrete | 3/19/2020 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Rough | 4/7/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 4/27/2020 | Partial Approval | DANNY TOLENTINO |
| Deputy Wood Construction | 5/12/2020 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2020 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 7/21/2020 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 8/10/2020 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 8/10/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 8/12/2020 | Approved | ANDREW NAVE |
| Deputy Wood Construction | 8/20/2020 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2020 | Approved | ANDREW NAVE |
| Underground Mechanical | 8/21/2020 | Partial Approval | ANDREW NAVE |
| Green Building Rough | 8/28/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 8/28/2020 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 8/31/2020 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 8/31/2020 | Approved | ANDREW NAVE |
| Insulation | 9/10/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 9/21/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 9/21/2020 | Corrections Issued | ANDREW NAVE |
| Interior/Exterior Lathing | 9/25/2020 | Approved | ANDREW NAVE |
| Sewer | 11/9/2020 | Approved | ANDREW NAVE |
| Gas Test | 3/22/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 4/12/2021 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Final | 4/12/2021 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 4/13/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 4/19/2021 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 4/19/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 4/23/2021 | Approved | ANDREW NAVE |
| HVAC-Final | 4/23/2021 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 5/7/2021 | No Access for Inspection | ANDREW NAVE |
| Service/Power Release | 5/19/2021 | Approved | KENNETH NAGLE |
| Final | 7/7/2021 | Partial Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 7/7/2021 | Approved | ANDREW NAVE |
| Green Building Final | 7/7/2021 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 7/7/2021 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 7/7/2021 | Approved | ANDREW NAVE |
| Final | 7/8/2021 | OK to Issue CofO | ANDREW NAVE |