4119 W CAMERO AVE 90027
Certificate Information: 4119 W CAMERO AVE 90027
- Application / Permit
- 19010-30000-03920
- Plan Check / Job No.
- B19LA18525
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- new one car garage with attched storage room
- Permit Issued
- Issued on 3/5/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | SAMUEL GONZALEZ |
| Green Plans Picked Up | 9/27/2019 | APPLICANT |
| Corrections Issued | 10/1/2019 | SAMUEL GONZALEZ |
| Quality Review Completed | 10/10/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 10/15/2019 | APPLICANT |
| Plan Check Approved | 2/4/2020 | SAMUEL GONZALEZ |
| Issued | 3/5/2020 | LADBS |
| CofO in Progress | 2/5/2021 | JOSEPH MCGARRY |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
| CofO Issued | 2/6/2021 | DEROLD HAUFF |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2020 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 1/21/2020 | ERIK BEASLEY |
| Green Code | Cleared | 1/24/2020 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 2/4/2020 | SAMUEL GONZALEZ |
Contact Information
| Contractor | Avon Construction; Lic. No.: 798325-B | PO BOX 16891 BEVERLY HILLS, CA 90209 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/1/2020 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 6/26/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 8/10/2020 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 8/10/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/10/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 11/20/2020 | Approved | JOSEPH MCGARRY |
| Final | 11/20/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Final | 11/20/2020 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 11/20/2020 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 11/20/2020 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 11/20/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 1/29/2021 | Approved | JOSEPH MCGARRY |
| Final | 1/29/2021 | OK to Issue CofO | JOSEPH MCGARRY |
| HVAC-Final | 1/29/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 1/29/2021 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 1/29/2021 | Approved | JOSEPH MCGARRY |