501-515 S BARRINGTON AVE 90049

Certificate Information: 501-515 S BARRINGTON AVE 90049

Application / Permit
19010-30000-03885
Plan Check / Job No.
B19WL04944
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(23) Recreation Room
Work Description
(N) DETACHED ACCESSORY STRUCTURE/ GYM AS PART OF REQUIRED OPEN SPACE FOR 505 BARRINGTON APT BLDG UNDER PERMIT # 16010-20000-05223.
Permit Issued
Issued on 7/5/2022
Issuing Office
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 9/16/2019 KAMRAN GHOTBI RAVANDI
Quality Review Completed 9/27/2019 FELIX FIGUEROA
Applicant returned to address corrections 11/5/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/28/2021 MANUEL GARCIA
Applicant returned to address corrections 1/3/2022 MANUEL GARCIA
Plan Check Approved 7/5/2022 REZA HAGHIGHAT
Issued 7/5/2022 APPLICANT
Building Plans Picked Up 7/6/2022 APPLICANT
CofO in Progress 3/5/2025 DERRICK SPENCER
Permit Finaled 3/6/2025 HENRY BAGHDASSARIAN
CofO Issued 3/6/2025 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Green Code Cleared 10/16/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 10/17/2019 ROBERT DUFF
DAS Clearance Cleared 10/21/2019 NORLITO MEDRANO
Miscellaneous Cleared 10/25/2019 SARAH GOLDMAN
Opn space landscape/Water mgmt Cleared 10/25/2019 SARAH GOLDMAN
Specific Plan Cleared 11/19/2019 VALERIA CEJA
Eng Process Fee Ord 176,300 Cleared 12/7/2021 ANTHONY MAINEZ
Sewer availability Cleared 12/7/2021 ANTHONY MAINEZ
Low Impact Development Cleared 12/13/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/6/2022 MAHELET GEBEYHU
Watercourse Cleared 1/6/2022 MAHELET GEBEYHU
Construction near power lines Cleared 3/30/2022 WALTER RAMIREZ
GPI Written Notices Cleared 6/16/2022 KAMRAN GHOTBI RAVANDI
Grading Pre-Inspection Cleared 6/16/2022 KAMRAN GHOTBI RAVANDI

Contact Information

Architect Hefner, Charles David; Lic. No.: C23963 28378 ROADSIDE DRIVE      AGOURA HILLS, CA 91301
Contractor P And N Construction Inc; Lic. No.: 800653-A 8730 WILSHIRE BLVD #202      BEVERLY HILLS, CA 90211
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Naim, Soleiman Israel; Lic. No.: S2454 403 21ST ST      SANTA MONICA, CA 90402

Inspector Information

DERRICK SPENCER, (310) 914-3919 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 8/4/2022 Partial Approval DERRICK SPENCER
Deputy Wood Construction 8/11/2022 Approved DERRICK SPENCER
Footing/Foundation/Slab 8/30/2022 Partial Approval DERRICK SPENCER
METHANE-Barrier 8/30/2022 Not Ready for Inspection DERRICK SPENCER
METHANE-Subgrade 8/30/2022 Not Ready for Inspection DERRICK SPENCER
Masonry Wall/Backfill 9/6/2022 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 9/14/2022 Approved DERRICK SPENCER
METHANE-Barrier 9/14/2022 Approved DERRICK SPENCER
METHANE-Subgrade 9/14/2022 Approved DERRICK SPENCER
Green Building Rough 10/28/2022 Not Ready for Inspection DERRICK SPENCER
METHANE-Rough 10/28/2022 Approved DERRICK SPENCER
Verify Sprinkler Sign Off 10/28/2022 Approved DERRICK SPENCER
Wood Frame 10/28/2022 Partial Approval DERRICK SPENCER
Green Building Rough 5/9/2023 Approved ALAN NOVAK
Interior/Exterior Lathing 5/9/2023 Partial Inspection ALAN NOVAK
Interior/Exterior Lathing 6/21/2023 Approved DERRICK SPENCER
Insulation 8/29/2023 Partial Approval DERRICK SPENCER
Drywall Nailing 9/5/2023 Approved DERRICK SPENCER
Final 12/23/2024 Not Ready for Inspection DERRICK SPENCER
Green Building Final 12/23/2024 Not Ready for Inspection DERRICK SPENCER
Reinforced Masonry Frame 12/23/2024 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Approved DERRICK SPENCER
Smoke Detectors 12/23/2024 Approved DERRICK SPENCER
Wood Frame 12/23/2024 Approved DERRICK SPENCER
Special/Order Compliance 12/30/2024 Approved DERRICK SPENCER
Final 1/3/2025 Not Ready for Inspection DERRICK SPENCER
Green Building Final 1/3/2025 Approved DERRICK SPENCER
Special/Order Compliance 1/6/2025 Approved DERRICK SPENCER
Final 2/12/2025 Not Ready for Inspection DERRICK SPENCER
Final 2/24/2025 OK to Issue CofO DERRICK SPENCER