747-749 E 110TH ST 90059

Certificate Information: 747-749 E 110TH ST 90059

Application / Permit
19010-30000-03882
Plan Check / Job No.
B19WL04941
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY DUPLEX WITH ATTACHED CARAGE
Permit Issued
Issued on 1/29/2021
Issuing Office
Current Status
CofO Issued on 7/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 9/16/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 9/18/2019 APPLICANT
Quality Review Completed 9/19/2019 FELIX FIGUEROA
Plan Check Approved 12/24/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/24/2020 APPLICANT
Issued 1/29/2021 APPLICANT
CofO in Progress 7/11/2023 JAMES CHAVEZ
CofO Issued 7/11/2023 ANSON MAGLASANG
Permit Finaled 7/11/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/25/2019 JEANETTE VONG
Green Code Cleared 2/4/2020 RICHARD GARCIA
Hydrant and Access approval Cleared 2/19/2020 JOHN CONNEALLY
Low Impact Development Cleared 12/2/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/7/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/8/2020 CELINA MORENO
Sewer availability Cleared 12/11/2020 CELINA MORENO

Contact Information

Contractor C S W F Construction Inc; Lic. No.: 1021458-B 15831 SAN JOSE AVE      LA PUENTE, CA 91744
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/22/2021 Partial Approval EUGENE CASSIDY
Underground Mechanical 3/22/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 4/7/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 4/16/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 4/27/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/27/2021 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 7/8/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 7/8/2021 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 7/8/2021 Approved EUGENE CASSIDY
HVAC-Rough 7/8/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 7/8/2021 Corrections Issued EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 7/8/2021 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 7/8/2021 Approved EUGENE CASSIDY
Wood Frame 7/8/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 7/12/2021 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 7/12/2021 Corrections Issued EUGENE CASSIDY
Wood Frame 7/12/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 7/13/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 7/13/2021 Approved EUGENE CASSIDY
Wood Frame 7/13/2021 Approved EUGENE CASSIDY
Insulation 7/28/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/28/2021 Partial Approval EUGENE CASSIDY
Drywall Nailing 8/20/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/20/2021 Approved EUGENE CASSIDY
Sewer 11/2/2021 Approved EUGENE CASSIDY
Underground Mechanical 4/18/2022 Partial Approval JOHN KLARIN
Underground Mechanical 4/21/2022 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 4/20/2023 Approved JAMES CHAVEZ
Final 4/20/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 4/20/2023 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Approved JAMES CHAVEZ
Service/Power Release 4/20/2023 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 4/20/2023 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Final 4/27/2023 Approved JAMES CHAVEZ
Final 4/27/2023 Conditional Approval JAMES CHAVEZ
Green Building Final 4/27/2023 Approved JAMES CHAVEZ
HVAC-Final 4/27/2023 Approved JAMES CHAVEZ
PLUMBING-Final 4/27/2023 Approved JAMES CHAVEZ
Service/Power Release 4/27/2023 Approved JAMES CHAVEZ
Smoke Detectors 4/27/2023 Approved JAMES CHAVEZ
Final 6/27/2023 Corrections Issued JAMES CHAVEZ
Final 7/11/2023 OK to Issue CofO JAMES CHAVEZ