Pre-Inspection
|
8/17/2020
|
Approved
|
DAVID HEINE
|
|
Piling/Pier/Caisson
|
8/19/2020
|
Not Ready for Inspection
|
DAVID HEINE
|
|
Piling/Pier/Caisson
|
8/20/2020
|
Not Ready for Inspection
|
DAVID HEINE
|
|
Piling/Pier/Caisson
|
8/25/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Piling/Pier/Caisson
|
8/26/2020
|
Partial Approval
|
DAVID HEINE
|
|
Excavation/Setback/Form/Re-Bar
|
10/27/2020
|
Partial Approval
|
DAVID HEINE
|
|
Footing/Foundation/Slab
|
11/12/2020
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
PLUMBING-Rough
|
12/8/2020
|
Corrections Issued
|
JOHNNY MIRANDA
|
|
ELECTRICAL-Rough
|
12/14/2020
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
12/14/2020
|
Approved
|
ENRIQUE MIRELES
|
|
PLUMBING-Rough
|
12/14/2020
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
ELECTRICAL-Rough
|
1/21/2021
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
1/21/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Other (see comments)
|
1/26/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Shotcrete
|
1/26/2021
|
Approved
|
ENRIQUE MIRELES
|
|
ELECTRICAL-Rough
|
1/28/2021
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
1/28/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
2/4/2021
|
Corrections Issued
|
EVAN COOPER
|
|
Deputy Shotcrete
|
2/5/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
2/5/2021
|
Approved
|
ENRIQUE MIRELES
|
|
ELECTRICAL-Rough
|
3/3/2021
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
3/4/2021
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
3/9/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Footing/Foundation/Slab
|
3/9/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
3/16/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Structural Steel Frame
|
3/31/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/13/2021
|
Partial Approval
|
ENRIQUE MIRELES
|
|
ELECTRICAL-Rough
|
4/20/2021
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
4/20/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
4/29/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Steel/Welding
|
5/21/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Structural Steel Frame
|
5/26/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/7/2021
|
Partial Approval
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/29/2021
|
Corrections Issued
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/1/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/10/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Wood Construction
|
8/11/2021
|
Approved
|
ENRIQUE MIRELES
|
|
HVAC-Rough
|
11/8/2021
|
Partial Inspection
|
KRISTEN CAUSEY
|
|
BUILDING-Rough-Frame
|
12/8/2021
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/8/2021
|
Approved
|
ENRIQUE MIRELES
|
|
Green Building Rough
|
12/8/2021
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Verify Sprinkler Sign Off
|
12/8/2021
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Interior/Exterior Lathing
|
1/18/2022
|
Approved
|
ENRIQUE MIRELES
|
|
Shower Pan
|
1/18/2022
|
Approved
|
ENRIQUE MIRELES
|
|
Insulation
|
1/19/2022
|
Approved
|
ENRIQUE MIRELES
|
|
Interior/Exterior Lathing
|
1/24/2022
|
Approved
|
ENRIQUE MIRELES
|
|
HVAC-Rough
|
3/30/2022
|
Approved
|
PATRICK QUALEY
|
|
Insulation
|
3/30/2022
|
Partial Approval
|
PATRICK QUALEY
|
|
PLUMBING-Rough
|
3/30/2022
|
Partial Approval
|
PATRICK QUALEY
|
|
Interior/Exterior Lathing
|
4/6/2022
|
Approved
|
PATRICK QUALEY
|
|
PLUMBING-Rough
|
4/19/2022
|
Corrections Issued
|
PATRICK QUALEY
|
|
Pre-Inspection
|
5/3/2022
|
Partial Inspection
|
PATRICK QUALEY
|
|
PLUMBING-Rough
|
5/10/2022
|
Approved
|
PATRICK QUALEY
|
|
Underground Mechanical
|
5/10/2022
|
Approved
|
PATRICK QUALEY
|
|
ELECTRICAL-Rough
|
5/12/2022
|
Conditional Approval
|
CLAYTON GRAHAM
|
|
BUILDING-Rough-Frame
|
5/16/2022
|
Corrections Issued
|
PATRICK QUALEY
|
|
Green Building Rough
|
5/16/2022
|
Approved
|
PATRICK QUALEY
|
|
Verify Sprinkler Sign Off
|
5/16/2022
|
Approved
|
PATRICK QUALEY
|
|
BUILDING-Rough-Frame
|
5/31/2022
|
Approved
|
PATRICK QUALEY
|
|
ELECTRICAL-Rough
|
5/31/2022
|
Approved
|
PATRICK QUALEY
|
|
Insulation
|
5/31/2022
|
Conditional Approval
|
PATRICK QUALEY
|
|
Drywall Nailing
|
6/13/2022
|
Partial Approval
|
JESUS RODRIGUEZ
|
|
Drywall Nailing
|
6/16/2022
|
Approved
|
PATRICK QUALEY
|
|
Gas Test
|
10/3/2022
|
Approved
|
CLAYTON GRAHAM
|
|
Final
|
1/24/2023
|
Corrections Issued
|
JESUS RODRIGUEZ
|
|
PLUMBING-Final
|
1/24/2023
|
Corrections Issued
|
JESUS RODRIGUEZ
|
|
ELECTRICAL-Final
|
1/31/2023
|
Corrections Issued
|
EVAN COOPER
|
|
ELECTRICAL-Final
|
2/3/2023
|
Conditional Approval
|
JESUS RODRIGUEZ
|
|
HVAC-Final
|
2/3/2023
|
Conditional Approval
|
JESUS RODRIGUEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
2/3/2023
|
SGSOV Approved
|
JESUS RODRIGUEZ
|
|
Service/Power Release
|
2/8/2023
|
Approved
|
JESUS RODRIGUEZ
|
|
ELECTRICAL-Final
|
3/20/2023
|
Approved
|
EVAN COOPER
|
|
HVAC-Final
|
3/20/2023
|
Approved
|
EVAN COOPER
|
|
Final
|
3/22/2023
|
Corrections Issued
|
EVAN COOPER
|
|
Green Building Final
|
3/22/2023
|
Approved
|
EVAN COOPER
|
|
Smoke Detectors
|
3/22/2023
|
Approved
|
EVAN COOPER
|
|
PLUMBING-Final
|
3/28/2023
|
Approved
|
JESUS RODRIGUEZ
|
|
Final
|
5/26/2023
|
OK to Issue CofO
|
JESUS RODRIGUEZ
|