725 W 140TH ST 90247

Certificate Information: 725 W 140TH ST 90247

Application / Permit
19010-30000-03838
Plan Check / Job No.
B19WL04911
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ADU per AB494 and SB229.
Permit Issued
Issued on 2/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 MANUEL GARCIA
Green Plans Picked Up 10/2/2019 APPLICANT
Corrections Issued 10/8/2019 MANUEL GARCIA
Quality Review Completed 10/17/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 10/18/2019 APPLICANT
Applicant returned to address corrections 11/5/2019 MANUEL GARCIA
Applicant returned to address corrections 1/31/2020 MANUEL GARCIA
Plan Check Approved 2/4/2020 MANUEL GARCIA
Issued 2/10/2020 LADBS
CofO in Progress 4/23/2021 JOHN KLARIN
Permit Finaled 6/4/2021 DEROLD HAUFF
CofO Issued 6/4/2021 DEROLD HAUFF
Permit Finaled 6/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/24/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/24/2019 JEANIE LAM
Sewer availability Cleared 10/24/2019 JEANIE LAM
Low Impact Development Cleared 11/1/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/1/2019 EMIL KYUPELYAN
Green Code Cleared 12/12/2019 RICHARD GARCIA
Construction near power lines Cleared 1/18/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adefeso,, Wole Dayo; Lic. No.: C63361 1608 CENTINELA AVE #13      INGLEWOOD, CA 90302

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/24/2020 Corrections Issued JOHN KLARIN
METHANE-Barrier 2/24/2020 Not Ready for Inspection JOHN KLARIN
METHANE-Subgrade 2/24/2020 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 2/28/2020 Approved JOHN KLARIN
PLUMBING-Rough 3/26/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval EUGENE CASSIDY
Insulation 3/27/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/1/2020 Partial Approval BRIAN CHRISTIAN
BUILDING-Rough-Frame 6/16/2020 Corrections Issued BRIAN CHRISTIAN
ELECTRICAL-Rough 6/16/2020 Not Ready for Inspection BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval BRIAN CHRISTIAN
Green Building Rough 6/16/2020 Corrections Issued BRIAN CHRISTIAN
HVAC-Rough 6/16/2020 Corrections Issued BRIAN CHRISTIAN
METHANE-Rough 6/16/2020 Not Ready for Inspection BRIAN CHRISTIAN
PLUMBING-Rough 6/16/2020 Corrections Issued BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Approved BRIAN CHRISTIAN
HVAC-Rough 6/17/2020 Approved BRIAN CHRISTIAN
PLUMBING-Rough 6/17/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 6/18/2020 Not Ready for Inspection BRIAN CHRISTIAN
ELECTRICAL-Rough 6/18/2020 Not Ready for Inspection BRIAN CHRISTIAN
Green Building Rough 6/18/2020 Approved BRIAN CHRISTIAN
MERV13>=Rough 6/18/2020 Not Ready for Inspection BRIAN CHRISTIAN
METHANE-Rough 6/18/2020 Not Ready for Inspection BRIAN CHRISTIAN
Verify Sprinkler Sign Off 6/18/2020 Not Ready for Inspection BRIAN CHRISTIAN
ELECTRICAL-Rough 6/19/2020 Approved EUGENE CASSIDY
Wood Frame 6/19/2020 Conditional Approval EUGENE CASSIDY
Insulation 6/23/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 7/2/2020 Approved JOHN KLARIN
Drywall Nailing 7/2/2020 Approved JOHN KLARIN
Footing/Foundation/Slab 7/2/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 7/2/2020 Corrections Issued JOHN KLARIN
MERV13>=Rough 7/2/2020 Approved JOHN KLARIN
METHANE-Barrier 7/2/2020 Approved JOHN KLARIN
METHANE-Rough 7/2/2020 Approved JOHN KLARIN
METHANE-Subgrade 7/2/2020 Approved JOHN KLARIN
Verify Sprinkler Sign Off 7/2/2020 Approved JOHN KLARIN
Wood Frame 7/2/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 7/6/2020 Approved EUGENE CASSIDY
Final 9/2/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 9/2/2020 Corrections Issued EUGENE CASSIDY
MERV13>=Final 9/2/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/2/2020 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 9/2/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 9/2/2020 Approved EUGENE CASSIDY
Final 9/10/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 9/10/2020 Corrections Issued EUGENE CASSIDY
MERV13>=Final 9/10/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/10/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 9/10/2020 Not Ready for Inspection EUGENE CASSIDY
Final 9/17/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 9/17/2020 Approved EUGENE CASSIDY
MERV13>=Final 9/17/2020 Approved EUGENE CASSIDY
Service/Power Release 9/17/2020 Corrections Issued EUGENE CASSIDY
Final 11/19/2020 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 11/19/2020 Corrections Issued EUGENE CASSIDY
Final 12/7/2020 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 12/7/2020 Corrections Issued EUGENE CASSIDY
Final 1/5/2021 Corrections Issued EUGENE CASSIDY
Service/Power Release 1/5/2021 Not Ready for Inspection EUGENE CASSIDY
Final 2/10/2021 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 2/10/2021 Corrections Issued EUGENE CASSIDY
Final 3/9/2021 Not Ready for Inspection JOHN KLARIN
Service/Power Release 3/9/2021 Not Ready for Inspection JOHN KLARIN
Final 4/22/2021 OK to Issue CofO JOHN KLARIN
Service/Power Release 4/22/2021 Approved JOHN KLARIN