725 W 140TH ST 90247
Certificate Information: 725 W 140TH ST 90247
- Application / Permit
- 19010-30000-03838
- Plan Check / Job No.
- B19WL04911
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New ADU per AB494 and SB229.
- Permit Issued
- Issued on 2/10/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | MANUEL GARCIA |
| Green Plans Picked Up | 10/2/2019 | APPLICANT |
| Corrections Issued | 10/8/2019 | MANUEL GARCIA |
| Quality Review Completed | 10/17/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 10/18/2019 | APPLICANT |
| Applicant returned to address corrections | 11/5/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 1/31/2020 | MANUEL GARCIA |
| Plan Check Approved | 2/4/2020 | MANUEL GARCIA |
| Issued | 2/10/2020 | LADBS |
| CofO in Progress | 4/23/2021 | JOHN KLARIN |
| Permit Finaled | 6/4/2021 | DEROLD HAUFF |
| CofO Issued | 6/4/2021 | DEROLD HAUFF |
| Permit Finaled | 6/4/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/24/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2019 | JEANIE LAM |
| Sewer availability | Cleared | 10/24/2019 | JEANIE LAM |
| Low Impact Development | Cleared | 11/1/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 11/1/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 12/12/2019 | RICHARD GARCIA |
| Construction near power lines | Cleared | 1/18/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1608 CENTINELA AVE #13 INGLEWOOD, CA 90302 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2020 | Corrections Issued | JOHN KLARIN |
| METHANE-Barrier | 2/24/2020 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Subgrade | 2/24/2020 | Not Ready for Inspection | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 2/28/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 3/26/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2020 | Partial Approval | EUGENE CASSIDY |
| Insulation | 3/27/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2020 | Partial Approval | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 6/16/2020 | Corrections Issued | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 6/16/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2020 | Partial Approval | BRIAN CHRISTIAN |
| Green Building Rough | 6/16/2020 | Corrections Issued | BRIAN CHRISTIAN |
| HVAC-Rough | 6/16/2020 | Corrections Issued | BRIAN CHRISTIAN |
| METHANE-Rough | 6/16/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| PLUMBING-Rough | 6/16/2020 | Corrections Issued | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2020 | Approved | BRIAN CHRISTIAN |
| HVAC-Rough | 6/17/2020 | Approved | BRIAN CHRISTIAN |
| PLUMBING-Rough | 6/17/2020 | Approved | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 6/18/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 6/18/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Green Building Rough | 6/18/2020 | Approved | BRIAN CHRISTIAN |
| MERV13>=Rough | 6/18/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| METHANE-Rough | 6/18/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Verify Sprinkler Sign Off | 6/18/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 6/19/2020 | Approved | EUGENE CASSIDY |
| Wood Frame | 6/19/2020 | Conditional Approval | EUGENE CASSIDY |
| Insulation | 6/23/2020 | Approved | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 7/2/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 7/2/2020 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 7/2/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 7/2/2020 | Corrections Issued | JOHN KLARIN |
| MERV13>=Rough | 7/2/2020 | Approved | JOHN KLARIN |
| METHANE-Barrier | 7/2/2020 | Approved | JOHN KLARIN |
| METHANE-Rough | 7/2/2020 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 7/2/2020 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/2/2020 | Approved | JOHN KLARIN |
| Wood Frame | 7/2/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 7/6/2020 | Approved | EUGENE CASSIDY |
| Final | 9/2/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/2/2020 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Final | 9/2/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/2/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 9/2/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 9/2/2020 | Approved | EUGENE CASSIDY |
| Final | 9/10/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 9/10/2020 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Final | 9/10/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/10/2020 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 9/10/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 9/17/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 9/17/2020 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 9/17/2020 | Approved | EUGENE CASSIDY |
| Service/Power Release | 9/17/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 11/19/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 11/19/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 12/7/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 12/7/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 1/5/2021 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 1/5/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/10/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 2/10/2021 | Corrections Issued | EUGENE CASSIDY |
| Final | 3/9/2021 | Not Ready for Inspection | JOHN KLARIN |
| Service/Power Release | 3/9/2021 | Not Ready for Inspection | JOHN KLARIN |
| Final | 4/22/2021 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 4/22/2021 | Approved | JOHN KLARIN |