4406 N MATILIJA AVE 91423

Certificate Information: 4406 N MATILIJA AVE 91423

Application / Permit
19010-30000-03708
Plan Check / Job No.
B19WL04701
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1185sf ADU per AB494 & SB229
Permit Issued
Issued on 4/21/2020
Issuing Office
Current Status
CofO Issued on 6/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2019 APPLICANT
Assigned to Plan Check Engineer 9/18/2019 KAVIAN REFAHI
Corrections Issued 9/25/2019 KAVIAN REFAHI
Quality Review Completed 10/4/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 10/29/2019 APPLICANT
Applicant returned to address corrections 1/28/2020 KAVIAN REFAHI
Applicant returned to address corrections 2/11/2020 KAVIAN REFAHI
Applicant returned to address corrections 2/24/2020 KAVIAN REFAHI
Plan Check Approved 3/13/2020 KAVIAN REFAHI
Issued 4/21/2020 APPLICANT
Building Plans Picked Up 4/22/2020 APPLICANT
CofO in Progress 6/6/2022 MISAEL ESPARZA
CofO Issued 6/6/2022 MICHAEL SMITH
Permit Finaled 6/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/22/2019 DINAH GARIN
Construction near power lines Cleared 11/4/2019 RIDWAN HARDY
Low Impact Development Cleared 1/14/2020 MITESH PATEL
Green Code Cleared 1/16/2020 RICHARD GARCIA
ZI Cleared 1/23/2020 DENZEL HENDERSON
Eng Process Fee Ord 176,300 Cleared 1/24/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 1/24/2020 DINAH GARIN
Sewer availability Cleared 1/24/2020 DINAH GARIN
Hydrant and Access approval Cleared 2/21/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/2/2020 Corrections Issued CHARLES POWELL
Excavation/Setback/Form/Re-Bar 6/4/2020 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 7/16/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 8/3/2020 Partial Approval CHARLES POWELL
Green Building Rough 8/3/2020 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 8/3/2020 Partial Approval CHARLES POWELL
Verify Sprinkler Sign Off 8/3/2020 Not Ready for Inspection CHARLES POWELL
Insulation 8/5/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 8/10/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 10/7/2020 Partial Approval ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 12/11/2020 Approved CHARLES POWELL
Rough-Elec/Plmb/HVAC 12/23/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 1/8/2021 Partial Approval CHARLES POWELL
Rough-Elec/Plmb/HVAC 1/8/2021 Partial Approval CHARLES POWELL
Rough-Elec/Plmb/HVAC 1/15/2021 Approved CHARLES POWELL
Insulation 1/21/2021 Approved CHARLES POWELL
Drywall Nailing 2/9/2021 Approved THOMAS FINNILA
Gas Test 7/19/2021 Approved CHARLES POWELL
PLUMBING-Final 7/19/2021 Not Ready for Inspection CHARLES POWELL
Sewer 7/19/2021 Corrections Issued CHARLES POWELL
Gas Test 7/26/2021 Approved CHARLES POWELL
PLUMBING-Final 7/26/2021 Not Ready for Inspection CHARLES POWELL
Sewer 7/26/2021 Approved CHARLES POWELL
PLUMBING-Final 8/12/2021 Not Ready for Inspection CHARLES POWELL
Sewer 8/12/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 9/23/2021 Approved MISAEL ESPARZA
Final 9/23/2021 Corrections Issued MISAEL ESPARZA
Green Building Final 9/23/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 9/23/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 9/23/2021 Corrections Issued MISAEL ESPARZA
Smoke Detectors 9/23/2021 Corrections Issued MISAEL ESPARZA
Verify Sprinkler Sign Off 9/23/2021 Approved MISAEL ESPARZA
Final 5/6/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 5/6/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Approved MISAEL ESPARZA
Service/Power Release 5/6/2022 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 5/6/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/3/2022 Approved MISAEL ESPARZA
Final 6/3/2022 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 6/3/2022 Approved MISAEL ESPARZA
PLUMBING-Final 6/3/2022 Approved MISAEL ESPARZA
Service/Power Release 6/6/2022 Approved MISAEL ESPARZA