4406 N MATILIJA AVE 91423
Certificate Information: 4406 N MATILIJA AVE 91423
- Application / Permit
- 19010-30000-03708
- Plan Check / Job No.
- B19WL04701
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1185sf ADU per AB494 & SB229
- Permit Issued
- Issued on 4/21/2020
- Issuing Office
- Current Status
- CofO Issued on 6/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2019 | KAVIAN REFAHI |
| Corrections Issued | 9/25/2019 | KAVIAN REFAHI |
| Quality Review Completed | 10/4/2019 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 10/29/2019 | APPLICANT |
| Applicant returned to address corrections | 1/28/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/11/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/24/2020 | KAVIAN REFAHI |
| Plan Check Approved | 3/13/2020 | KAVIAN REFAHI |
| Issued | 4/21/2020 | APPLICANT |
| Building Plans Picked Up | 4/22/2020 | APPLICANT |
| CofO in Progress | 6/6/2022 | MISAEL ESPARZA |
| CofO Issued | 6/6/2022 | MICHAEL SMITH |
| Permit Finaled | 6/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/22/2019 | DINAH GARIN |
| Construction near power lines | Cleared | 11/4/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/14/2020 | MITESH PATEL |
| Green Code | Cleared | 1/16/2020 | RICHARD GARCIA |
| ZI | Cleared | 1/23/2020 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2020 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 1/24/2020 | DINAH GARIN |
| Sewer availability | Cleared | 1/24/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 2/21/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/2/2020 | Corrections Issued | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 6/4/2020 | Not Ready for Inspection | CHARLES POWELL |
| Footing/Foundation/Slab | 7/16/2020 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 8/3/2020 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 8/3/2020 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 8/3/2020 | Partial Approval | CHARLES POWELL |
| Verify Sprinkler Sign Off | 8/3/2020 | Not Ready for Inspection | CHARLES POWELL |
| Insulation | 8/5/2020 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2020 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Partial Approval | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 12/11/2020 | Approved | CHARLES POWELL |
| Rough-Elec/Plmb/HVAC | 12/23/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 1/8/2021 | Partial Approval | CHARLES POWELL |
| Rough-Elec/Plmb/HVAC | 1/8/2021 | Partial Approval | CHARLES POWELL |
| Rough-Elec/Plmb/HVAC | 1/15/2021 | Approved | CHARLES POWELL |
| Insulation | 1/21/2021 | Approved | CHARLES POWELL |
| Drywall Nailing | 2/9/2021 | Approved | THOMAS FINNILA |
| Gas Test | 7/19/2021 | Approved | CHARLES POWELL |
| PLUMBING-Final | 7/19/2021 | Not Ready for Inspection | CHARLES POWELL |
| Sewer | 7/19/2021 | Corrections Issued | CHARLES POWELL |
| Gas Test | 7/26/2021 | Approved | CHARLES POWELL |
| PLUMBING-Final | 7/26/2021 | Not Ready for Inspection | CHARLES POWELL |
| Sewer | 7/26/2021 | Approved | CHARLES POWELL |
| PLUMBING-Final | 8/12/2021 | Not Ready for Inspection | CHARLES POWELL |
| Sewer | 8/12/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 9/23/2021 | Approved | MISAEL ESPARZA |
| Final | 9/23/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 9/23/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 9/23/2021 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 9/23/2021 | Corrections Issued | MISAEL ESPARZA |
| Smoke Detectors | 9/23/2021 | Corrections Issued | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 9/23/2021 | Approved | MISAEL ESPARZA |
| Final | 5/6/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/6/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/6/2022 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 5/6/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 5/6/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 6/3/2022 | Approved | MISAEL ESPARZA |
| Final | 6/3/2022 | OK to Issue CofO | MISAEL ESPARZA |
| HVAC-Final | 6/3/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 6/3/2022 | Approved | MISAEL ESPARZA |
| Service/Power Release | 6/6/2022 | Approved | MISAEL ESPARZA |