4822 N LONGRIDGE AVE 91423

Certificate Information: 4822 N LONGRIDGE AVE 91423

Application / Permit
19010-30000-03707
Plan Check / Job No.
B19WL04700
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story single family dwelling w/ att. garage.
Permit Issued
Issued on 10/22/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 REZA HAGHIGHAT
Corrections Issued 9/3/2019 REZA HAGHIGHAT
Green Plans Picked Up 9/5/2019 APPLICANT
Quality Review Completed 9/13/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 9/13/2019 APPLICANT
Plan Check Approved 10/3/2019 REZA HAGHIGHAT
Issued 10/22/2019 LADBS
CofO in Progress 9/29/2020 BRENDAN LOONEY
CofO Issued 12/15/2020 MICHAEL SMITH
Permit Finaled 12/15/2020 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 9/26/2019 RICHARD GARCIA
Eng Process Fee Ord 176,300 Cleared 10/1/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 10/1/2019 JEREMY CARTER
Low Impact Development Cleared 10/1/2019 RYAN HUDSON
Permit Cleared 10/1/2019 ELENA LOPEZ
Roof/Waste drainage to street Cleared 10/1/2019 ELENA LOPEZ
Sewer availability Cleared 10/1/2019 ELENA LOPEZ
Trees in Parkway Cleared 10/21/2019 JOHN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/13/2019 Approved GREG ALLTON
Footing/Foundation/Slab 11/18/2019 Approved GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 12/3/2019 Partial Approval GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 1/15/2020 Partial Approval GREG ALLTON
PLUMBING-Rough 1/22/2020 Approved GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Corrections Issued DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 2/14/2020 Partial Inspection GREG ALLTON
Deputy Wood Construction 2/20/2020 Conditional Approval GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 2/20/2020 Approved GREG ALLTON
HVAC-Rough 2/20/2020 Partial Approval GREG ALLTON
BUILDING-Rough-Frame 2/24/2020 Not Ready for Inspection GREG ALLTON
ELECTRICAL-Rough 2/24/2020 Approved GREG ALLTON
Green Building Rough 2/24/2020 Not Ready for Inspection GREG ALLTON
Interior/Exterior Lathing 2/24/2020 Approved GREG ALLTON
MERV13>=Rough 2/24/2020 Approved GREG ALLTON
Verify Sprinkler Sign Off 2/24/2020 Not Ready for Inspection GREG ALLTON
BUILDING-Rough-Frame 2/28/2020 Corrections Issued DANIEL ORRANTE
Green Building Rough 2/28/2020 Approved DANIEL ORRANTE
Verify Sprinkler Sign Off 2/28/2020 Not Ready for Inspection DANIEL ORRANTE
Special/Order Compliance 3/4/2020 Approved GREG ALLTON
Insulation 3/9/2020 Approved GREG ALLTON
Shower Pan 3/9/2020 Approved GREG ALLTON
Drywall Nailing 3/12/2020 Approved GREG ALLTON
BUILDING-Rough-Frame 8/19/2020 Not Ready for Inspection BRENDAN LOONEY
Final 8/19/2020 Corrections Issued BRENDAN LOONEY
Green Building Final 8/19/2020 Not Ready for Inspection BRENDAN LOONEY
MERV13>=Final 8/19/2020 No Access for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 8/19/2020 SGSOV Approved BRENDAN LOONEY
Service/Power Release 8/19/2020 Not Ready for Inspection BRENDAN LOONEY
Smoke Detectors 8/19/2020 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 8/19/2020 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 8/24/2020 Approved ARAM AVEDISIAN
Final 8/24/2020 Corrections Issued ARAM AVEDISIAN
Green Building Final 8/24/2020 Approved ARAM AVEDISIAN
MERV13>=Final 8/24/2020 Approved ARAM AVEDISIAN
Service/Power Release 8/24/2020 Approved ARAM AVEDISIAN
Smoke Detectors 8/24/2020 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 8/24/2020 Approved ARAM AVEDISIAN
Final 9/28/2020 Corrections Issued ARAM AVEDISIAN
Final 9/29/2020 OK to Issue CofO BRENDAN LOONEY