5327 S 2ND AVE 90043

Certificate Information: 5327 S 2ND AVE 90043

Application / Permit
19010-30000-03644
Plan Check / Job No.
B19WL04603
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY TYPE VB ACCESSORY DWELLING UNIT (ADU) PER AB 494 AND SB 229.
Permit Issued
Issued on 4/21/2020
Issuing Office
Current Status
CofO Issued on 7/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2019 APPLICANT
Assigned to Plan Check Engineer 9/11/2019 SERGIO SILVA
Green Plans Picked Up 9/17/2019 APPLICANT
Corrections Issued 9/18/2019 SERGIO SILVA
Quality Review Completed 9/26/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/30/2019 SERGIO SILVA
Applicant returned to address corrections 12/17/2019 SERGIO SILVA
Applicant returned to address corrections 2/14/2020 SERGIO SILVA
Plan Check Approved 2/25/2020 SERGIO SILVA
Issued 4/21/2020 APPLICANT
Building Plans Picked Up 5/18/2020 APPLICANT
CofO in Progress 7/21/2021 DAVID FEILER
Permit Finaled 7/27/2021 DEROLD HAUFF
CofO Issued 7/27/2021 DEROLD HAUFF
Permit Finaled 7/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/12/2019 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 11/12/2019 NIKTA MOUSAVI
Low Impact Development Cleared 1/29/2020 ORVAL HERNANDEZ-MARCI
Permit Cleared 2/10/2020 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 2/10/2020 ANTHONY MAINEZ
Sewer availability Cleared 2/10/2020 ANTHONY MAINEZ
Green Code Cleared 2/13/2020 RICHARD GARCIA
Hydrant and Access approval Cleared 2/20/2020 GEORGE SUCHAND
Miscellaneous Cleared 2/25/2020 SERGIO SILVA

Contact Information

Contractor Owner-Builder       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 2036 CREEK RD      KITTY HAWK, NC 27949

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/23/2020 Not Ready for Inspection COREY HUPP
Underground Mechanical 4/24/2020 Conditional Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 5/18/2020 Not Ready for Inspection COREY HUPP
Excavation/Setback/Form/Re-Bar 5/19/2020 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 6/4/2020 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Corrections Issued COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Corrections Issued COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 7/8/2020 Partial Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 7/23/2020 Approved COREY HUPP
Interior/Exterior Lathing 8/5/2020 Partial Approval COREY HUPP
PLUMBING-Rough 8/5/2020 Approved COREY HUPP
ELECTRICAL-Rough 8/6/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 8/12/2020 Corrections Issued COREY HUPP
BUILDING-Rough-Frame 8/20/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 8/20/2020 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 8/20/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 8/20/2020 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/28/2020 Approved COREY HUPP
HVAC-Rough 8/28/2020 Not Ready for Inspection COREY HUPP
Verify Sprinkler Sign Off 8/28/2020 Approved COREY HUPP
ELECTRICAL-Rough 9/1/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 9/10/2020 Approved COREY HUPP
HVAC-Rough 9/10/2020 Approved COREY HUPP
Drywall Nailing 9/23/2020 Corrections Issued DAVID FEILER
Insulation 9/29/2020 Not Ready for Inspection DAVID FEILER
Drywall Nailing 10/6/2020 Approved DAVID FEILER
Insulation 10/6/2020 Approved DAVID FEILER
Interior/Exterior Lathing 10/14/2020 Not Ready for Inspection DAVID FEILER
Underground Mechanical 10/14/2020 Partial Approval DAVID FEILER
Interior/Exterior Lathing 10/20/2020 Approved DAVID FEILER
Underground Mechanical 10/20/2020 Approved DAVID FEILER
PLUMBING-Final 12/22/2020 Corrections Issued DAVID FEILER
Service/Power Release 12/22/2020 Corrections Issued DAVID FEILER
ELECTRICAL-Final 1/13/2021 Partial Inspection DAVID FEILER
HVAC-Final 1/13/2021 Partial Inspection DAVID FEILER
PLUMBING-Final 1/13/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 1/15/2021 Partial Approval DAVID FEILER
Service/Power Release 1/15/2021 Partial Approval DAVID FEILER
SGSOV-Seismic Gas S/O Valve 2/11/2021 SGSOV Not Ready DAVID FEILER
Final 2/23/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 2/23/2021 Approved DAVID FEILER
Green Building Final 2/23/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Approved DAVID FEILER
Service/Power Release 2/23/2021 Not Ready for Inspection DAVID FEILER
Smoke Detectors 2/23/2021 Approved DAVID FEILER
Final 3/30/2021 Partial Inspection DAVID FEILER
Service/Power Release 3/30/2021 Not Ready for Inspection DAVID FEILER
Final 5/24/2021 Not Ready for Inspection ROBERT MCDOWELL
Service/Power Release 5/24/2021 Not Ready for Inspection ROBERT MCDOWELL
Final 6/25/2021 OK to Issue CofO DAVID FEILER
Service/Power Release 6/25/2021 Approved DAVID FEILER