19404 W WELBY WAY 91335

Certificate Information: 19404 W WELBY WAY 91335

Application / Permit
19010-30000-03486
Plan Check / Job No.
B19WL04417
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY 934.76 SF A.D.U. PER ENG. CALCULATIONS & AB494 & SB229
Permit Issued
Issued on 8/18/2020
Issuing Office
Current Status
CofO Corrected on 5/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 KAVIAN REFAHI
Green Plans Picked Up 9/5/2019 APPLICANT
Corrections Issued 9/10/2019 KAVIAN REFAHI
Quality Review Completed 9/20/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/3/2020 KAVIAN REFAHI
Building Plans Picked Up 7/29/2020 APPLICANT
Plan Check Approved 8/18/2020 JEROME MAGAT PALMA
Issued 8/18/2020 APPLICANT
CofO in Progress 3/30/2021 VINCENT HANLEY
CofO Issued-Status Void 3/30/2021 MICHAEL SMITH
Permit Finaled-Status Void 3/30/2021 MICHAEL SMITH
Re-Activate Permit 4/6/2021 MICHAEL SMITH
CofO Corrected 5/2/2023 MICHAEL SMITH
Permit Finaled 5/2/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/17/2019 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/18/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/18/2019 APEKSHYA BAJRACHARYA
Construction within easement Cleared 1/9/2020 RIDWAN HARDY
Low Impact Development Cleared 3/11/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/11/2020 RENZ SORIANO
Green Code Cleared 4/22/2020 RICHARD GARCIA
ZI Cleared 5/4/2020 JASON CHAN
Hydrant and Access approval Cleared 5/8/2020 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/11/2020 Approved VINCENT HANLEY
Underground Mechanical 9/16/2020 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 9/18/2020 Partial Approval VINCENT HANLEY
PLUMBING-Rough 9/18/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/28/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Approved VINCENT HANLEY
Green Building Rough 9/28/2020 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 9/28/2020 Approved VINCENT HANLEY
Sewer 10/1/2020 Approved VINCENT HANLEY
Shower Pan 10/1/2020 Approved VINCENT HANLEY
Underground Mechanical 10/1/2020 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 10/21/2020 Corrections Issued HENRY KIM
Insulation 10/21/2020 Corrections Issued HENRY KIM
Interior/Exterior Lathing 10/21/2020 Approved HENRY KIM
Insulation 10/26/2020 Approved VINCENT HANLEY
Drywall Nailing 10/30/2020 Approved VINCENT HANLEY
Gas Test 11/18/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/26/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 1/26/2021 Approved VINCENT HANLEY
Final 1/26/2021 Corrections Issued VINCENT HANLEY
Green Building Final 1/26/2021 Approved VINCENT HANLEY
HVAC-Final 1/26/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Final 1/26/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/26/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 1/26/2021 Approved VINCENT HANLEY
Smoke Detectors 1/26/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 1/26/2021 Not Ready for Inspection VINCENT HANLEY
Final 3/30/2021 OK to Issue CofO VINCENT HANLEY