845 S ST ANDREWS PL 90005

Certificate Information: 845 S ST ANDREWS PL 90005

Application / Permit
19010-30000-03223
Plan Check / Job No.
B19WL04244
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 6-story, 25 units apartment buiding with roof top deck over 1-level of subterranean garage, utilizing TOC Tier 3 (3 Extremely low income units)
Permit Issued
Issued on 12/20/2021
Issuing Office
Current Status
CofO Issued on 7/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 MARJAN SHENASI
Corrections Issued 9/26/2019 MARJAN SHENASI
Quality Review Completed 10/3/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/4/2020 MARJAN SHENASI
Applicant returned to address corrections 2/10/2020 MARJAN SHENASI
Applicant returned to address corrections 2/18/2020 MARJAN SHENASI
Applicant returned to address corrections 4/16/2020 MARJAN SHENASI
Applicant returned to address corrections 7/22/2020 MARJAN SHENASI
Disabled Access Plans Picked Up 8/14/2020 APPLICANT
Applicant returned to address corrections 12/2/2020 MARJAN SHENASI
Building Plans Picked Up 12/15/2020 APPLICANT
Green Plans Picked Up 12/18/2020 APPLICANT
Applicant returned to address corrections 4/21/2021 MARJAN SHENASI
Plan Check Approved 5/10/2021 MARJAN SHENASI
Issued 12/20/2021 APPLICANT
TCO Issued (Expire Date: 12-02-2025) 6/5/2025 RAFAEL ESPINOZA
CofO in Progress 7/9/2025 EDWIN GREGORYONA
CofO Issued 7/9/2025 ERNESTO CORRAL
Permit Finaled 7/9/2025 ERNESTO CORRAL

Permit Application Clearance Information

Trees in Parkway Cleared 11/27/2019 ADRIAN SANCHEZ
Address approval Cleared 2/5/2020 THOMAS LANG
Permit Cleared 2/5/2020 ELENA LOPEZ
DAS Clearance Cleared 2/12/2020 SOMKIAT SUPANYACHOTSKUL
Bicycle Parking Cleared 2/21/2020 ELAINE LEI
Construction near power lines Cleared 7/5/2020 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 9/9/2020 JEANIE LAM
Highway dedication Cleared 9/11/2020 JEANIE LAM
Density Bonus 12.22.A.31 Cleared 10/9/2020 NICHOLAS KAWAZOE
Hydrant and Access approval Cleared 11/24/2020 MATTHEW CRAIG
Fire Marshall Fire Life Safety Cleared 12/1/2020 ANDREW KO
Green Code Cleared 1/7/2021 RICHARD GARCIA
Low Impact Development Cleared 1/27/2021 MARTIN FRAGOSO
Sewer availability Cleared 2/16/2021 JEANIE LAM
Work Adjacent to Public Way Cleared 2/16/2021 CHIU TAM
Roof/Waste drainage to street Cleared 2/19/2021 JEANIE LAM
Miscellaneous Cleared 3/30/2021 LOUIS ORTEGA
Miscellaneous Cleared 3/30/2021 LOUIS ORTEGA
Building over 3-story or 36-ft Cleared 4/21/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/21/2021 CALOSHA APPROVED
Hold Not Cleared 6/16/2025 Department of Building and Safety

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Sma Builders Inc; Lic. No.: 457725-B 16134 LEADWELL ST      VAN NUYS, CA 91406
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Benichou,, Ety; Lic. No.: S5263 888 S FIGUEROA ST 18TH FLOOR      LOS ANGELES, CA 90017
Engineer Zweigler,, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/22/2021 Approved EDWIN GREGORYONA
Deputy Steel/Welding 1/7/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/12/2022 Partial Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/11/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/3/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/7/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/8/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/9/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 3/9/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 3/16/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 3/17/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 3/18/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 3/24/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 3/25/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 3/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 3/25/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 3/31/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 4/1/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/1/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 4/1/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/1/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 4/12/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/20/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 4/21/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 4/27/2022 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 5/9/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 5/10/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/10/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/10/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 5/11/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/13/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/8/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/17/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 6/17/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 6/17/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/17/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 6/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 6/22/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 6/29/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/30/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 6/30/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 6/30/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/30/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 7/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/12/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/12/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Seismic Resistance 7/14/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 7/14/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 7/14/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 7/14/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 7/21/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/21/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/27/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 7/28/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 7/28/2022 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 7/28/2022 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 8/16/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 8/29/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 8/29/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/29/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 9/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 9/16/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 9/20/2022 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 9/22/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/22/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 9/26/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/18/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/25/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/14/2022 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Partial Approval NICK DANERI
Deputy Wood Construction 12/1/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/13/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 12/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 1/13/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/23/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 2/3/2023 Approved EDWIN GREGORYONA
Deputy Wood Construction 3/23/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 4/12/2023 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/12/2023 Partial Approval EDWIN GREGORYONA
Insulation 4/19/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 5/8/2023 Partial Approval EDWIN GREGORYONA
Insulation 5/12/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 5/19/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 5/19/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 5/31/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval EDWIN GREGORYONA
Insulation 6/2/2023 Partial Approval EDWIN GREGORYONA
Insulation 6/26/2023 Partial Approval EDWIN GREGORYONA
Insulation 7/24/2023 Approved EDWIN GREGORYONA
Wood Frame 7/24/2023 Approved EDWIN GREGORYONA
Drywall Nailing 7/31/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/7/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/15/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 9/13/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 9/28/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 10/6/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 11/21/2023 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 11/21/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 11/21/2023 Approved EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/28/2023 Partial Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 12/5/2023 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 5/2/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 5/7/2024 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 7/1/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/11/2024 Partial Inspection EDWIN GREGORYONA
Special/Order Compliance 7/17/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/13/2025 Not Ready for Inspection EDWIN GREGORYONA
Final 4/15/2025 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 4/15/2025 Approved EDWIN GREGORYONA
Green Building Final 4/15/2025 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 4/15/2025 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 4/15/2025 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 4/15/2025 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 4/15/2025 Not Ready for Inspection EDWIN GREGORYONA
Final 4/22/2025 OK to Issue CofO EDWIN GREGORYONA
Green Building Final 4/22/2025 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 4/22/2025 Approved EDWIN GREGORYONA